BS EN 62305 is the UK adoption of the IEC 62305 series on protection against lightning. The 2024 editions, published in the UK as BS EN IEC 62305, replace the 2011 versions, and the older versions are to be withdrawn on 31 October 2027. The risk assessment in Part 2 decides whether a structure needs protection, and it does not assume that every building does. Below are the four parts in UK practice, the structure of the risk assessment and a strike frequency example.
Lightning protection is a field where the same building can be treated in three ways: ignored, covered with air terminals, or protected only at the equipment level. The standard does not pick one by habit. It picks one by risk. The scheme for the whole series is in IEC 62305: what each part covers, and the UK frame is in the UK electrical codes and grid connection guide. The current editions are the 2024 editions of BS EN IEC 62305.
Short answer: how is BS EN 62305 used in the UK?
BS EN 62305 is the UK adoption of the IEC 62305 series, with four parts. Part 1 gives the principles, Part 2 the risk management, Part 3 the protection of structures against physical damage and danger to people, and Part 4 the protection of electrical and electronic systems inside the structure. BSI published the 2024 editions as BS EN IEC 62305-1 to 62305-4, and the earlier 2011 versions are to be withdrawn on 31 October 2027. Standards are not applied retrospectively, so existing lightning protection systems do not need changes just because the edition changed. A new design states the edition it follows. The 2024 editions simplify the risk assessment and move from flash density to strike point density.
The risk assessment decides
Part 2 treats lightning as a risk to be calculated. The designer defines the structure and its services, identifies the types of loss that matter, such as loss of human life, loss of service to the public, loss of cultural heritage and economic loss, and works out the risk for each. If the risk is above the tolerable level, protection measures are added until it is below. The measures are chosen from an external lightning protection system (LPS), from surge protective devices (SPDs), from shielding and routing, and from other measures. A school with many people, a hospital with critical systems and a warehouse with valuable stock can each give a different answer.
The first quantity in the calculation is the expected number of dangerous strikes on the structure per year. It comes from the lightning density at the site, the collection area of the structure and the environment factor. In the UK, lightning density is low compared with tropical regions. Many small buildings therefore need no LPS, while tall, exposed or high-consequence ones often do.
Parts 3 and 4 in practice
If the assessment calls for an external LPS, Part 3 defines classes of protection and the design methods for air terminals, down conductors and earth terminations. The earthing arrangement is a lightning matter and an installation matter at once, and it must be coordinated with the installation earth under BS 7430 and BS 7671 Chapter 54. Industrial examples are in the guide to industrial lightning protection.
Part 4 deals with equipment inside through lightning protection zones and coordinated SPDs. See lightning protection zones and SPM against LEMP. The installation side, which decides when an SPD is fitted on a UK installation and how it is selected, is in the BS 7671 Chapter 44 guide. For substations, see lightning overvoltages in a substation.
Worked example: how often is a structure struck?
The numbers are illustrative and the data are assumed. A warehouse is 40 m long, 20 m wide and 10 m high, on an industrial estate with other buildings of similar height around. The lightning density is taken as 0.5 per km² per year, an assumed figure for the example; a real design uses lightning location data for the site. The collection area of an isolated structure is its footprint plus a strip of three times its height around it.
- Footprint: 40 × 20 = 800 m².
- Strip around the perimeter: 2 × (3 × 10) × (40 + 20) = 3,600 m².
- Four corner quarter-circles together make a full circle: π × (3 × 10)² = 2,827 m².
- Collection area: 800 + 3,600 + 2,827 = 7,227 m².
- Location factor for a structure surrounded by objects of similar height: 0.5, assumed.
- Expected dangerous events per year: 0.5 × 7,227 × 0.5 × 10⁻⁶ = 0.0018.
- That is about one event in 550 years for the structure.
The number does not by itself say whether protection is needed. It is the input to the risk components, which multiply it by the probability of damage and by the loss. A warehouse with few people and low-value stock can pass with no LPS, while the same strike frequency on a hospital with critical equipment can lead to protection. The point of the example is the scale: the answer is a frequency to be weighed against consequences, not a yes or no.
Figure: a plan and elevation sketch of a rectangular structure with the collection area around it marked at a distance of three times the height.
Common problems in practice
- Fitting air terminals because the client asked for lightning protection, with no assessment.
- Doing an assessment with a lightning density that does not belong to the site.
- Treating the LPS and the SPDs as one decision.
- Down conductors that are not connected to the installation earth system, or that are connected in a way that lets surge current enter the building.
- Citing the 2011 edition in a new specification without noting the transition.
- Ignoring the services that enter the structure, which can carry partial lightning currents inside.
Checklist for the engineer
- State the edition of each part that the design follows.
- Define the structure, the services and the types of loss.
- Use a site lightning density from a source that you can cite.
- Calculate the collection area and the expected number of events.
- Compute the risk components and compare them with the tolerable values.
- Decide the LPS class if one is needed, and the SPDs and zones for the systems inside.
- Coordinate the lightning earthing with the installation earth.
- Plan the periodic inspection of the system.
Legal frame
In the UK there is no statutory stamp for lightning protection designs. A chartered engineer or other competent person reviews the design and signs it under their own responsibility. The general duty to keep electrical systems safe sits in the Electricity at Work Regulations 1989.
How Tiza can help
If your project needs a lightning risk assessment or the protection designed from it, Tiza prepares the engineering remotely and in English: risk calculation, protection scheme, SPD coordination and earthing calculations. Tiza does not stamp, sign or certify designs in the UK; we deliver engineering ready for your chartered engineer to review and sign. Contact us with the structure drawings and the list of services.
Frequently asked questions
Is lightning protection compulsory for UK buildings?
There is no general UK law that makes a lightning protection system compulsory for every building. The need comes from a risk assessment under BS EN IEC 62305-2, from the client's or insurer's requirements, or from rules for specific hazards such as explosives or fuel storage. The assessment is also where the choice of protection level is made.
Which edition of BS EN 62305 is current?
The 2024 editions of all four parts, published in the UK as BS EN IEC 62305-1 to 62305-4, are current. The 2011 versions are to be withdrawn on 31 October 2027, and during the transition either may be cited in a specification. A design should state which edition it follows.
Does an SPD replace an external lightning protection system?
No. A lightning protection system (LPS) deals with direct strikes to the structure, and surge protective devices (SPDs) deal with the surges that reach the electrical and electronic systems. A building can need either, both or neither, and the risk assessment says which. The SPD rules in BS 7671 are covered in the Chapter 44 guide.