The GB Distribution Code is the technical rulebook of the distribution network operators (DNOs). It sets planning, connection and operating rules for anyone who connects to a DNO network, and it points to the engineering recommendations of the Energy Networks Association (ENA), such as G99. A DNO connection offer applies those rules to one site. Knowing the code lets a developer see why the offer asks for a given study, protection or limit.
Short answer: what the Distribution Code does for a connection
The GB Distribution Code (DCode) is the technical rulebook of the distribution network operators (DNOs). The licensed DNOs maintain it under their licences, and the Distribution Code Review Panel (DCRP) manages changes, which Ofgem approves. It sets the rules for planning, connecting to and operating on a distribution network. A DNO connection offer is the document that applies those rules to one site. The current text is Distribution Code Issue 62, effective from 27 August 2026, published at dcode.org.uk. The wider UK layers are in the UK codes overview.
How the code relates to the other documents
A generation project meets several documents, and each has a role.
- Distribution Code: the network rules every user follows. It refers to the ENA engineering recommendations in its annexes.
- Energy Networks Association (ENA) documents (G98, G99, G100, G5, P28, S34, P2): the detailed technical requirements. G99 sorts generators by size and sets what each must do.
- Connection offer: the site-specific document, with the point of connection, the works, the technical conditions and the commercial terms.
- Grid Code: applies to plant on the transmission system and to larger plant in distribution. See the Grid Code overview.
A frequent mistake is to read the offer alone. The offer says what to do, and the code and the ENA documents explain why. When an offer sets a limit or asks for a study, the matching clause usually sits in one of them.
What the code asks of a generator
The Distribution Code has the same pattern as the Grid Code: planning, connection, operation and data registration. For a generator, the practical consequences are:
- Planning data. The DNO needs technical data to study the connection. The developer supplies it, and keeps it current.
- Connection conditions. The plant must meet the technical conditions for its Type, including power quality, protection and control, and the voltage limits.
- Operation. The plant operates within the agreed limits, follows instructions about outages and tests, and reports events.
- Review of the offer. The studies behind the offer follow the code. See the studies guide.
Worked example: voltage rise at the point of connection
Voltage rise is one of the first things a DNO checks. All values are illustrative and assumed.
Site: a 4 MW solar plant on an 11 kV feeder. The impedance from the primary substation to the point of connection is R = 0.8 ohm and X = 1.2 ohm. The plant exports at unity power factor.
The approximate voltage rise is ΔV ≈ (P × R + Q × X) ÷ V², with P in watts, Q in vars and V in volts.
- Unity power factor: Q = 0. ΔV = (4,000,000 × 0.8) ÷ (11,000)² = 3,200,000 ÷ 121,000,000 = 0.02645, which is 2.64 %.
- Now let the plant absorb reactive power at 0.95 power factor. Q = P × tan(acos 0.95) = 4 MW × 0.3287 = 1.315 Mvar.
- ΔV = (4,000,000 × 0.8 − 1,315,000 × 1.2) ÷ 121,000,000 = (3,200,000 − 1,578,000) ÷ 121,000,000 = 1.34 %.
Absorbing reactive power halves the rise. Suppose the DNO allows this connection 1.5 % of voltage rise (an assumption for the example, as part of a wider voltage band that it shares between users). Then unity power factor fails and the 0.95 absorbing mode passes. That is why offers often state a power factor or a voltage control mode. The DNO’s own limit and method may differ from this approximation, so the offer governs.
What to read in an offer against the code
- The point of connection and the voltage level.
- The registered capacity and the Type under G99.
- The power factor or voltage control mode the plant must use.
- The protection requirements and settings.
- The works the DNO will do and those the developer must do.
- Any export limit or flexibility arrangement.
The line-by-line reading is in how to read a DNO connection offer.
Where the code is silent
The Distribution Code sets general rules and refers detailed values to the ENA documents and to the offer. When a question is about a number, such as a protection setting, a voltage target or a flicker limit, look first at the offer and the ENA document it cites. When the question is about process, such as who must be told about an outage or a test, look at the operating part of the code. If neither answers, ask the DNO in writing and keep its reply with the design record.
Checklist for the engineer
- Record the Distribution Code issue and the ENA document issues the offer cites.
- Identify the DNO and ask for its generation connection requirements in writing.
- Compute registered capacity and the Type, and check them against the offer.
- Check voltage rise and the proposed power factor or voltage control mode.
- Review the protection and settings requirements with the DNO.
- List the data and models the DNO needs, and the dates.
- Check whether the Grid Code also applies.
- Route the design to your chartered engineer for review before submission.
Related guides
For voltage correction methods in a load flow, see correcting low voltage in a load flow. For harmonic limits at the point of connection, see IEEE 519 with inverter-based generation.
From the code to a package your chartered engineer can sign off
A DNO connection moves faster when the design package answers the code and the offer in the same order. We prepare the engineering design and the power-system studies behind a distribution connection: single-line diagram, voltage and fault-level inputs, and the protection and control concept. The package is ready for your chartered engineer to review and sign off before it goes to the network operator. Tiza does not sign or certify designs in the UK. Contact us with the site data and the connection offer.
Frequently asked questions
What is the GB Distribution Code?
It is the code that the licensed distribution network operators maintain under their licences. It sets technical rules for planning, connecting and operating on their networks. The Distribution Code Review Panel maintains it and Ofgem approves modifications.
How is the Distribution Code different from the Grid Code?
The Grid Code covers the transmission system and is maintained by NESO. The Distribution Code covers the distribution networks and is maintained by the DNOs. A large plant embedded in a distribution network can have to follow both.
Does the connection offer replace the Distribution Code?
No. The offer applies the code and the ENA documents to one site and adds site-specific conditions, such as the point of connection, works, and settings. The code remains the background rulebook.