Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

BS EN 61439 Switchboards in the UK: Specify and Verify

BS EN 61439 switchboards in the UK: design verification, the rated diversity factor, fault level at the board and a worked check for a distribution board.

By Shadai García, CEO and protection engineer at Tiza Group.

800 kVA transformerPENPE and N linked400 V, 5 %800 AMET, electrodeswitchboard, withstand 25 kA for 1 s400 A250 A160 A100 A24.2 kAat the busbarsLineN, PE400 + 250 + 160 + 100 = 910 A910 × 0.8 = 728 A; demand 650 A: pass800,000 / (√3 × 400) = 1,155 A1,155 / 0.05 = 23.1 kAc = 1.05: 24.2 kA25 kA for 1 s above 24.2 kA: adequatedemand of 780 A would fail the diversityoutgoing ratings 910 A× 0.8 = 728 Aexpected demand 650 A800 AA0250500750c = 1.0: 23.1 kAc = 1.05: 24.2 kA25 kAkA0102030illustrative values; network treated as strongSwitchboardTransformerIncomerBusbarsFeedersFault level© tizagrp.com800 kVA transformerPENPE and N linked400 V, 5 %800 AMET, electrodeswitchboard, withstand 25 kA for 1 s400 A250 A160 A100 A24.2 kAat the busbarsLineN, PE400 + 250 + 160 + 100 = 910 A910 × 0.8 = 728 A; demand 650 A: pass800,000 / (√3 × 400) = 1,155 A1,155 / 0.05 = 23.1 kAc = 1.05: 24.2 kA25 kA for 1 s above 24.2 kA: adequatedemand of 780 A would fail the diversityoutgoing ratings 910 A× 0.8 = 728 Aexpected demand 650 A800 AA0250500750c = 1.0: 23.1 kAc = 1.05: 24.2 kA25 kAkA0102030illustrative values; network treated as strongSwitchboardTransformerIncomerBusbarsFeedersFault level© tizagrp.com
BS EN 61439 switchboards: an 800 kVA 400 V transformer with 5 % impedance on a TN-C-S supply with the PEN conductor split at the origin, an 800 A incomer and four outgoing feeders of 400, 250, 160 and 100 A on a switchboard with a withstand of 25 kA for 1 s, the rated diversity factor of 0.8 giving 728 A against a demand of 650 A, and the fault level at the busbars of 23.1 kA, 24.2 kA with the voltage factor c of 1.05, below the 25 kA withstand. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

BS EN 61439 is the UK adoption of the IEC 61439 series for low-voltage switchgear and controlgear assemblies, and BS 7671 expects assemblies to comply with it. The 2021 editions of parts 1 and 2 are the reference for power switchgear assemblies. The practical questions for a UK project are who carries the design verification, whether the assembly's rated currents match the installation, and whether its short-circuit rating exceeds the fault level at the board. An illustrative example works through the last two.

A switchboard is the point where design intent, equipment and site conditions have to agree. A well-specified board is cheap to verify and easy to accept. A badly specified one starts arguments at the factory acceptance test. The focus here is the British angle: how BS EN 61439 is used in UK projects and what to ask for. The general rules are in IEC 61439-1: general rules for LV assemblies, and the wider frame is in the UK electrical codes and grid connection guide. The current editions are BS EN IEC 61439-1:2021 and BS EN IEC 61439-2:2021.

Short answer: how does BS EN 61439 apply to switchboards in the UK?

BS EN 61439 is the UK adoption of the IEC 61439 series for low-voltage switchgear and controlgear assemblies. Part 1 gives the general rules, and Part 2 covers power switchgear assemblies, which is what most people mean by a switchboard. Other parts cover distribution boards and busbar trunking. BS 7671 expects assemblies in an installation to meet the relevant standard, so a board built to it is the normal route. The standard splits the work between two roles: the original manufacturer who proves the design, and the assembly manufacturer who builds a board from that design and verifies each unit. Fully meeting Part 2 allows the assembly to be CE marked, and UK conformity marking follows the rules in force for the market where it is sold.

What a UK specifier has to supply

The standard cannot fix what it does not know. The specifier supplies the interface data. It includes the supply system and earthing arrangement, the rated voltage and the prospective short-circuit current at the board. It also covers the rated current of each circuit, the service conditions, the form of internal separation, and access and maintenance. BEAMA’s free guide on specifying an assembly lists these items. A frequent UK source of confusion is the coordination between the design current of the installation and the rated currents of the assembly, which BEAMA treats in a separate guide.

Verification: design and routine

Design verification proves that the design meets the standard. It covers strength of materials, degree of protection, clearances, protection against electric shock and the continuity of protective circuits, temperature rise, short-circuit withstand, EMC and mechanical operation. Each item can be proved by test, by calculation or by comparison with a verified reference design, according to the rules for that item. BEAMA notes that the verification does not have to be done on the exact arrangement to be supplied but on a representative sample, so the specifier should check that the verified design closely matches the offered one. For the short-circuit part, see the short-circuit test of an assembly.

Routine verification is done on each assembly: inspection, insulation and dielectric checks, and checks of protective measures and wiring. It is the record that the board built is the board designed.

Rated currents and the diversity factor

An assembly has several rated currents: for the busbars, for each outgoing unit and for the whole board. When the outgoing circuits add up to more than the incomer, the rated diversity factor decides whether the board can carry the real load. The manufacturer states it, and the designer checks it. The relevant guides are LV switchboard and MCC and PE circuit continuity; the shock protection side is in electric shock protection in an LV panel.

Worked example: a distribution board in a UK factory

The numbers are illustrative and the data are assumed. A factory board is fed by an 800 kVA, 400 V transformer with an impedance of 5 %. It has an 800 A incomer and four outgoing circuits of 400 A, 250 A, 160 A and 100 A. The manufacturer states a rated diversity factor of 0.8 for this arrangement.

  1. Sum of outgoing ratings: 400 + 250 + 160 + 100 = 910 A, which is more than the 800 A incomer.
  2. Maximum simultaneous load on the outgoing side, with each circuit at 80 % of its rating: 910 × 0.8 = 728 A.
  3. The expected maximum demand of the site is assumed to be 650 A, which is below 728 A and below 800 A. The board is acceptable.
  4. Transformer rated current: 800,000 / (√3 × 400) = 1,155 A.
  5. Prospective short-circuit current at the transformer terminals, treating the network as infinitely strong: 1,155 / 0.05 = 23.1 kA. With the voltage factor of 1.05 used in IEC 60909 for maximum fault current, it is 24.2 kA.
  6. The board has a rated short-time withstand current of 25 kA for 1 s. This is above 24.2 kA, so the withstand is adequate. With the cable between transformer and board, the real fault level at the board is lower.
  7. The protective device upstream must also limit the energy to what the board can withstand, so the verified withstand is checked with the actual device and its settings.

If the demand had been 780 A, the board would fail the diversity check even though the incomer is 800 A. The cure is a board verified for a higher diversity factor, a larger board or a different split of the load. The short-circuit result needs a margin as well: with 25 kA against 24.2 kA, a future transformer upgrade would remove it.

Figure: a single-line diagram of a transformer, an 800 A incomer and four outgoing feeders on a switchboard, with the prospective fault level marked at the busbars.

UK specifics worth noting

  • In domestic premises, BS 7671 asks for consumer units with non-combustible enclosures, and consumer units follow Part 3 of the series for distribution boards.
  • Network operator fault levels at the supply terminals are given in the connection offer; see how to read a DNO connection offer and the fault level guide.
  • Many UK specifications use the term form of separation for the internal division of the assembly, in the sense of the standard’s forms 1 to 4. State the form in the specification and not just the word.
  • Commissioning of the finished board is covered in switchgear and MCC commissioning.

Common problems in practice

  • Specifying a board with no prospective fault level, so the verifier has to guess.
  • Taking a manufacturer’s catalogue rating as the verified rating of the whole assembly.
  • Ignoring the diversity factor when outgoing circuits exceed the incomer.
  • Accepting a board with design verification for a different arrangement.
  • Confusing the rating of a device with the rating of the device installed in the enclosure.
  • No routine verification record handed over with the board.

Checklist for the engineer

  • Supply the interface data in the specification, including the fault level.
  • Ask for the design verification evidence and check that it matches the arrangement offered.
  • Check the rated currents against the installation design current.
  • Check the diversity factor against the real load, with a margin for growth.
  • Check the short-circuit withstand with the actual upstream device.
  • State the form of separation and the degree of protection.
  • Ask for the routine verification record and the declaration.

In the UK there is no statutory stamp for electrical designs or assembly specifications. A chartered engineer or other competent person reviews the design and signs it under their own responsibility. The manufacturer’s declaration of conformity is a separate document from the design review. The duty to keep the system safe sits in the Electricity at Work Regulations 1989.

How Tiza can help

If your project needs a switchboard specified, Tiza prepares the engineering remotely and in English: interface data sheets, fault level and diversity checks, and the list of verification evidence to ask the manufacturer for. Tiza does not stamp, sign or certify designs in the UK; we deliver engineering ready for your chartered engineer to review and sign. Contact us with the single-line diagram and the load list.

Frequently asked questions

What does BS EN 61439 require of a switchboard?

It requires the assembly to be verified against the standard in two stages. Design verification proves that the design meets the requirements, by test, calculation or comparison with a verified design. Routine verification checks every assembly that is built. The assembly manufacturer issues the declaration, and the specifier must give the data the assembly is to be built for.

What is the rated diversity factor?

It is the proportion of the sum of the outgoing circuit ratings that the assembly can carry at the same time without overheating. A board with outgoing circuits totalling more than its incomer is acceptable only if the load is less than the diversity factor allows. The manufacturer states the factor, and the designer checks the real load against it.

Where can I find free UK guidance on specifying an assembly?

BEAMA, the UK trade association for electrotechnical manufacturers, publishes free guides on specifying an assembly, on verification, and on the coordination between the installation design current and the assembly rated currents. They are written for BS EN IEC 61439-2:2021.

WhatsApp