Section 722 of BS 7671 sets the extra rules for electric vehicle charging installations in the UK. Three decisions drive most designs. The first is how the charge point is earthed, because PME earthing is restricted for outdoor charging. The second is the type of RCD, because vehicles can inject smooth DC fault current. The third is how supply capacity is shared, because charge points run for hours at full load. An illustrative car park example follows.
Charge points are ordinary electrical loads with an unusual combination of conditions: outdoors, rain, a metal car body that a person touches while barefoot on wet ground, and several hours at full load. Section 722 of BS 7671 exists because of those conditions. The rules belong to the 18th edition described in BS 7671 18th edition explained, and the wider framework is in the UK electrical codes and grid connection guide. The current edition is BS 7671:2018+A4:2026.
Short answer: what does BS 7671 Section 722 say about EV charging?
Section 722 of BS 7671 adds requirements for the supply of electric vehicles in an installation. It asks for a dedicated final circuit for each charging point connector, protection against electric shock that suits the special risk, and a decision on how the charge point is earthed. The headline rule is that a protective multiple earthing (PME, TN-C-S) facility shall not be used as the earthing of an outdoor charge point unless one of the listed measures is applied. The section also requires residual current device (RCD) protection that copes with smooth DC fault current from a vehicle.
Why PME is restricted
On a TN-C-S supply, the network combines neutral and earth in one conductor: the protective earth and neutral (PEN) conductor. If the PEN conductor breaks upstream, the installation neutral and earth can rise in voltage above the true ground. In a house this is managed by the bonding of all metalwork. Outdoors, a person standing on the ground and touching a vehicle connected to the charger earth is not protected by the house bonding. For this reason Regulation 722.411.4.1 restricts the use of PME.
The options are:
- Use a charge point or a separate device with open-PEN detection, which watches the voltage between line and neutral, or between the earth and a local electrode, and disconnects when the supply goes out of range.
- Earth the charge point as a TT system with its own earth electrode, isolated from the PME earth. Where there is buried metalwork connected to the supply PEN close to the electrode, separation can be hard to achieve and the TT route may not suit the site.
- Use another measure that gives at least the same level of safety, as the regulation allows.
The IET Code of Practice for Electric Vehicle Charging Equipment Installation describes the open-PEN devices in more detail, and it should be read with Section 722 when the design is prepared.
RCD and DC fault current
A vehicle has a battery charger inside, and a fault there can produce a smooth DC component that blinds an ordinary RCD. Section 722 therefore requires RCD protection that handles this. The standard answers are a type B RCD, or a type A RCD combined with a residual direct current detecting device (RDC-DD) that trips on smooth DC fault current of 6 mA or more. The 30 mA limit and the disconnection times of the Chapter 41 guide still apply. Each connector needs its own protection, so two sockets on one charger are protected separately.
Circuit design and supply capacity
Each charge point connector is supplied by a dedicated final circuit. Cable selection follows the Chapter 52 method, with the full rated current taken as continuous load; see the cable selection and voltage drop guide. A vehicle charges for hours, so cables sized with the diversity that suits a dwelling are not enough. Where the supply capacity cannot support all charge points at full rating, load management limits the total, and the design must show how.
For the sizing of a whole site, see how to size an EV charging station. For the choice between AC and DC charging, see AC versus DC EV charging, and for a home installation see the home charger checklist.
Worked example: a car park with load management
The numbers are illustrative and the data are assumed. An office car park has a three-phase supply of 63 A per phase at 400 V. Six 7.4 kW single-phase charge points are installed, two on each phase. The building uses 20 A per phase at peak.
- Current of one charge point: 7,400 / 230 = 32.2 A.
- Without management, two charge points on one phase draw 64.3 A.
- Adding the building load: 64.3 + 20 = 84.3 A, which is 34 % above the supply capacity of 63 A.
- The capacity left for charging is 63 − 20 = 43 A per phase.
- Shared between two charge points: 43 / 2 = 21.5 A each, which is 4.9 kW per charger (21.5 × 230 = 4,945 W).
- The charge points still work at 4.9 kW each. A vehicle with an 11 kWh top-up to add at that rate needs about 2.2 hours.
A dynamic load management system that reads the building load can give a better answer, because the building load is not always at its peak. The design must also say what happens when the load management communication fails, and the safe answer is that the charge points fall back to a fixed low current.
Figure: a single-line diagram of a three-phase supply feeding a building board and a charging board with six charge points and a load management controller.
Common problems in practice
- Using a PME earth for an outdoor charger with no open-PEN protection and no electrode.
- Placing a type A or type AC RCD upstream of a type B RCD, where DC leakage below the type B threshold can blind the upstream device.
- Sizing the circuit with diversity that does not apply to long charging sessions.
- Leaving the load management with no fallback state.
- Forgetting that a TT electrode must be tested and may change with the season.
- Installing the charger without telling the distribution network operator (DNO) when the load needs approval, which belongs to the connection process rather than to wiring rules.
Checklist for the engineer
- Confirm the supply earthing arrangement at the site.
- Decide how each outdoor charge point is earthed and record the reason.
- Specify the RCD type and where the DC fault detection is located.
- Calculate the supply capacity and the load management settings.
- Check the cable size, the route and the voltage drop.
- Check the equipment for the requirements of the smart charge point regulations that apply in Great Britain.
- Plan the tests; see the inspection and testing guide and the EV charger test equipment guide.
- Note the effect of solar and storage on the same supply; see Section 712.
Legal frame
In the UK there is no statutory stamp for electrical designs. A chartered engineer or other competent person reviews the design and signs it under their own responsibility. The wider duties sit in the Electricity at Work Regulations 1989, and the supply side is covered by the ESQCR 2002.
How Tiza can help
If your project needs a charging installation designed, Tiza prepares the engineering remotely and in English: supply capacity and load management studies, earthing choice, RCD coordination and cable calculations. Tiza does not stamp, sign or certify designs in the UK; we deliver engineering ready for your chartered engineer to review and sign. Contact us with the supply data and the number of charge points.
Frequently asked questions
Can an EV charger be earthed to a PME supply?
Regulation 722.411.4.1 restricts the use of a PME earthing facility for charge points outdoors, or where a vehicle is likely to be charged outdoors. It allows PME only when a listed measure is applied, such as an open-PEN detection device, or a separate earth electrode with TT arrangements. The reason is a broken neutral on the network, which can lift the earth of the charger above the ground the user stands on.
What RCD does an EV charger need?
Each charge point connector needs protection that copes with smooth DC fault current. The usual solutions are a type B RCD, or a type A RCD together with a device that detects DC fault current above 6 mA. Many chargers have the DC detection built in, so check the manufacturer's data before adding another device.
Does Amendment 4 change Section 722?
The IET announcement of Amendment 4 (15 January 2026) lists new chapters and a major revision of Section 710, but it does not itemise the changes to Section 722. Read Section 722 of BS 7671:2018+A4:2026 itself before relying on a summary.