Section 712 of BS 7671 adds rules for solar photovoltaic supply systems: DC cables and devices must be rated for the real string voltage at the coldest temperature, the DC side needs isolation, and the RCD on the AC side depends on whether the inverter separates AC from DC. Section 710 covers medical locations, where the risk is patients connected to equipment, and it was revised substantially in Amendment 4 of 2026. A string voltage example is worked below.
Section 712 matters on every roof and every ground-mounted array. Section 710 matters on a short list of sites where the people are connected to electrical equipment and cannot let go or move away. They are different sections of the same standard: the first is the main topic here, and the second gets a short comparison. The context is in the BS 7671 18th edition guide and the UK electrical codes and grid connection guide. The current edition is BS 7671:2018+A4:2026.
Short answer: what does BS 7671 Section 712 require for solar PV?
Section 712 of BS 7671 sets the rules for photovoltaic power supply systems on the customer side of the meter. Four themes cover most of it. The DC cables and devices are chosen for the highest voltage the string can reach, which happens at low temperature. The DC side is isolated for maintenance. Fault protection must account for the fact that an array cannot be switched off while the sun shines. And the residual current device (RCD) on the AC side depends on whether the inverter separates the DC from the AC side. Grid connection is a separate matter, handled under the ENA rules; see G98 versus G99.
DC side: voltage, current and isolation
A PV string is a current-limited source. Its short-circuit current is only slightly above its working current, so overcurrent devices do little on a single string, and the main DC hazards are insulation faults and arcs rather than overload. The design checks are:
- Open-circuit voltage at the lowest temperature. Module voltage rises as temperature falls, so the string maximum occurs on a cold, bright morning. Cables, connectors, isolators, surge protective devices (SPDs) and the inverter input must all be rated above it.
- Current rating. Components must carry the string current with the margin the design uses for irradiance above standard conditions.
- Isolation. Section 712 expects the array to be isolated from the inverter for maintenance. A DC isolator must be rated for DC at the string voltage, since an AC-rated switch cannot interrupt DC arcs. Whether a separate roof isolator is needed depends on the inverter and the current clause; see the gPV fuses and DC disconnects guide for the devices, and the solar cable and connectors guide for the cable.
- Surge protection. Roof arrays are exposed to induced surges. The SPD logic of Chapter 44 applies to the DC and AC sides.
AC side: RCD and earthing
The inverter converts DC to AC and can leak DC into the AC circuit in a fault. For this reason, where the inverter does not offer at least simple separation between the DC and AC sides, the RCD on the AC supply circuit has to be type B. If the inverter has simple separation, or the manufacturer confirms that a type B is unnecessary, a type A RCD may do. The RCD should disconnect all live conductors, including the neutral. The overall shock protection logic is in the Chapter 41 guide. Batteries added to the system bring in the new storage chapter of Amendment 4; see what changed in Amendment 4 and the hybrid system guide.
Worked example: string voltage on a cold morning
The numbers are illustrative and the data are assumed. A string has 14 modules in series. Each module has an open-circuit voltage of 41.2 V at standard test conditions (25 °C) and a voltage temperature coefficient of −0.27 % per kelvin. The design minimum temperature is −10 °C.
- Temperature change from the standard condition: −10 − 25 = −35 K.
- Voltage increase per module: 0.27 % × 35 = 9.45 %, so the factor is 1.0945.
- Module voltage at −10 °C: 41.2 × 1.0945 = 45.1 V.
- String voltage: 14 × 45.1 = 631 V, against 577 V at standard conditions.
- The inverter input, the DC isolator and the cable are all specified for 1,000 V DC, so there is a margin of 369 V (37 %).
- Adding a fifteenth module would give 15 × 45.1 = 676 V. That still fits the limit, so the real constraint then becomes the inverter’s maximum power point tracking (MPPT) window and not the isolator.
The calculation is simple but easy to skip. A designer who uses the 577 V standard figure for a device with a 600 V rating would be about 5 % over at the coldest hour.
Figure: a single-line diagram of a PV string, a DC isolator, a string inverter, an AC isolator, an RCD and the consumer unit, with the DC and AC sides marked.
Section 710: medical locations in brief
Section 710 covers medical locations such as hospitals, clinics and some dental or veterinary practices, where patients may be connected to equipment. Medical locations are classed in groups from the type of contact with the patient. The higher groups get measures such as supplementary protective equipotential bonding, a medical IT system supervised by an insulation monitor in the most critical areas, and a safety supply for essential services. The design question is the same as in the rest of the standard, only the tolerance for error is much lower: a current that would be harmless on the skin can be dangerous when it reaches the heart. The IET lists a major revision of Section 710 in Amendment 4 of 2026, plus a new schedule to record supplementary bonding resistance. Use the text of the section itself for any requirement.
Common problems in practice
- Using the standard test voltage instead of the cold-weather voltage for the isolator rating.
- Fitting an AC-rated switch on the DC side.
- Adding a type A RCD on an inverter without checking whether it gives simple separation.
- Running DC cables in a loop that collects induced surges.
- Mixing up the rules for the supply to the inverter with the grid connection requirements of the network operator.
- Applying domestic test limits to a hospital system.
Checklist for the engineer
- Calculate the string open-circuit voltage at the design minimum temperature.
- Confirm the rating of every DC component against that voltage and the string current.
- Decide how the array is isolated and who can operate the isolator.
- Select the RCD type from the inverter data sheet.
- Check the earthing and bonding of the array frame; see Chapter 54.
- Plan the tests; the solar commissioning guide and the I-V curve tracer guide cover the PV-specific measurements.
- For a medical location, identify the group of each room before any design choice.
Legal frame
In the UK there is no statutory stamp for electrical designs. A chartered engineer or other competent person reviews the design and signs it under their own responsibility. For PV with a grid connection, the network operator’s process applies in parallel; see the G99 compliance guide.
How Tiza can help
If your project needs a PV design, Tiza prepares the engineering remotely and in English: string and cable calculations, protection and earthing, and the documents for the connection application. Tiza does not stamp, sign or certify designs in the UK; we deliver engineering ready for your chartered engineer to review and sign. Contact us with the module data sheet and the single-line diagram.
Frequently asked questions
Does a PV system need a DC isolator in BS 7671?
Section 712 expects isolation of the PV array from the inverter for maintenance, and the isolator must be rated for DC at the string voltage and current. Some inverters have a compliant switch built in, so whether a separate roof isolator is needed depends on the product and on the current text of Regulation 712.537. Check the inverter data and the regulation.
What RCD is needed on a PV supply circuit?
Where the inverter does not give at least simple separation between AC and DC sides, an RCD on the AC supply to it must be type B, because DC fault current can pass through the inverter. If the inverter provides simple separation, or the manufacturer states a type B is not needed, a type A RCD may be used. Any RCD should switch all live conductors.
What changed in Section 710 medical locations?
The IET lists a major revision of Section 710 in Amendment 4 of 2026, together with a new schedule for recording the resistance of supplementary protective equipotential bonding conductors. The announcement does not detail the revision, so read the text of the section before applying a summary.