BS 7671 Cable Sizing and Voltage Drop Explained

BS 7671 cable sizing and voltage drop explained: current-carrying capacity, correction factors, the 3% and 5% limits and a three-phase submain example.

By Shadai García, CEO and protection engineer at Tiza Group.

DNO transformerPENPE and N linkedmain boardbreaker25 mm² Cu60 A, 80 m8.4 V2.1 %distributionboard10 mm² Cu3.52 V1.53 %NPEMETload, 32 A, 25 mLineN, PEsubmain 1.75 x 60 x 80 / 1000 = 8.4 V = 2.1 %final 4.4 x 32 x 25 / 1000 = 3.52 V = 1.53 %total 2.1 + 1.53 = 3.63 %power circuits, limit 5 %: passeslighting circuits, limit 3 %: failshalf-drop submain saves about 1.05 %: 2.58 %%01234563 % lighting5 % powertoday: 2.1 + 1.53 = 3.63 %half-drop submain: 1.05 + 1.53 = 2.58 %illustrative values; cable data assumedDrop pathMain boardSubmainDist. boardFinalLoad© tizagrp.comDNO transformerPENPE and N linkedmain boardbreaker25 mm² Cu60 A, 80 m8.4 V2.1 %distributionboard10 mm² Cu3.52 V1.53 %NPEMETload, 32 A, 25 mLineN, PEsubmain 1.75 x 60 x 80 / 1000 = 8.4 V = 2.1 %final 4.4 x 32 x 25 / 1000 = 3.52 V = 1.53 %total 2.1 + 1.53 = 3.63 %power circuits, limit 5 %: passeslighting circuits, limit 3 %: failshalf-drop submain saves about 1.05 %: 2.58 %%01234563 % lighting5 % powertoday: 2.1 + 1.53 = 3.63 %half-drop submain: 1.05 + 1.53 = 2.58 %illustrative values; cable data assumedDrop pathMain boardSubmainDist. boardFinalLoad© tizagrp.com
BS 7671 Chapter 52: a TN-C-S supply feeding a main board, a three-phase 400 V submain of 25 mm² carrying 60 A over 80 m to a distribution board, and a final circuit of 10 mm² carrying 32 A over 25 m, with the voltage drop of 2.1 % and 1.53 % adding to 3.63 % against the limits of 5 % for power and 3 % for lighting. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Cable sizing under BS 7671 combines Chapter 52, which sets the rules for wiring systems, and Appendix 4, which gives the method and the data. A cable is chosen so that its corrected current-carrying capacity meets the protective device rating, then checked for voltage drop and for fault withstand. The common limits are 3% for lighting and 5% for other uses, measured from the origin of the installation to the load.

Cable sizing is where design, cost and safety meet, and a wrong choice either wastes copper or leaves a load starved of voltage. In BS 7671, Chapter 52 sets the rules for wiring systems and Appendix 4 gives the method and the data. The standard is introduced in the BS 7671 18th edition guide, and the wider UK picture is in the UK electrical codes and grid connection guide.

Short answer: how do you size a cable under BS 7671?

Select a cable whose current-carrying capacity, after correction factors, is at least the rating of the protective device, then check the voltage drop and the fault withstand. Appendix 4 of BS 7671 gives the tabulated current for each cable type and installation method and the correction factors for ambient temperature, grouping and thermal insulation. It also gives the voltage drop in millivolts per ampere per metre. The voltage drop is limited to 3% of the nominal voltage for lighting and 5% for other uses on a public supply, and Regulation 525 and Appendix 4 are where the limits are stated.

The sizing chain

  1. Design current Ib. From the load, including diversity where it applies.
  2. Protective device In. At or above Ib. See Chapter 43.
  3. Installation method. Clipped direct, in conduit, in trunking, buried, in thermal insulation. Each method gives a different tabulated current.
  4. Correction factors. Ambient temperature, grouping, thermal insulation and other factors multiply the tabulated current.
  5. Cable capacity Iz. The corrected current must be at least In.
  6. Voltage drop. The sum of the drops along the path from the origin, compared with the limit.
  7. Fault checks. The disconnection time in Chapter 41 and the thermal withstand in Chapter 43.

The conductor material changes the data. See copper or aluminum in cables and busbars. Electronic loads with large third harmonic currents heat the neutral; see harmonics in cables and neutrals.

How the voltage drop is calculated

The method uses the value of millivolts per ampere per metre, which is tabulated for each cable size and type. The drop is that value multiplied by the design current and by the length of the run in metres, divided by 1000 to get volts. A designer then expresses it as a percentage of the nominal voltage and adds the parts of the path: the submain and the final circuit. For the formula and its derivation, see AC cable voltage drop: formula and sizing. The solar side has its own rules; see PV conductor sizing.

Worked example: a three-phase submain and a final circuit

The values are illustrative and the cable data are assumed, not taken from Appendix 4. A three-phase 400 V submain carries 60 A over 80 m to a distribution board. From that board, a single-phase 230 V final circuit carries 32 A over 25 m.

  1. Submain cable: assumed 25 mm² copper with a three-phase voltage drop of 1.75 mV per ampere per metre.
  2. Submain drop: 1.75 × 60 × 80 / 1000 = 8.4 V. As a percentage of 400 V, that is 2.1%.
  3. Final circuit cable: assumed 10 mm² copper with a single-phase drop of 4.4 mV per ampere per metre.
  4. Final circuit drop: 4.4 × 32 × 25 / 1000 = 3.52 V. As a percentage of 230 V, that is 1.53%.
  5. Total: 2.1 + 1.53 = 3.63%.
  6. Compare with the limits. For a power circuit the limit is 5%, so the path passes with 1.4% to spare. For a lighting circuit the limit is 3%, so the same path would fail. The options are a larger submain cable or a shorter final circuit.

In the example, increasing the submain to a size with half the voltage drop per metre saves about 1.05% and brings a lighting path under 3%. The cost of copper against the cost of the voltage drop is a design choice, and the data of the maker decide the numbers.

Figure: a single-line diagram of a main switchboard feeding a distribution board through a three-phase submain, and a final circuit to the load, with the voltage drop at each stage.

Common problems in practice

  • Applying the limit to each cable and not to the whole path from the origin.
  • Mixing the three-phase millivolt value with a single-phase length, or the reverse.
  • Using the tabulated current of a cable in free air for a cable buried or in thermal insulation.
  • Forgetting grouping when several circuits share a tray or conduit.
  • Ignoring the extra drop caused by harmonic currents.

Checklist for the engineer

  • Record the edition and amendment of BS 7671 used.
  • Fix Ib and In for each circuit and the installation method.
  • Apply every correction factor and record its source.
  • Add the voltage drops along the path and compare with the limit for the load type.
  • Check the fault disconnection time and the thermal withstand of the cable.
  • Check the neutral where harmonics are expected.
  • Keep the calculation sheet for the reviewing engineer.

In the UK there is no statutory stamp for electrical designs. A chartered engineer or other competent person reviews the design and signs it under their own responsibility. The legal duty to keep systems safe is in the Electricity at Work Regulations 1989, covered in the EAWR guide.

How Tiza can help

If your project needs cable schedules and voltage drop calculations, Tiza prepares the engineering design remotely and in English: cable selection with the correction factors, voltage drop budgets for each part of the path and fault withstand checks. Tiza does not stamp, sign or certify designs in the UK; we deliver engineering ready for your chartered engineer to review and sign. Contact us with the load list, the cable routes and the supply data.

Frequently asked questions

What are the voltage drop limits in BS 7671?

For an installation supplied from the public low-voltage network, the usual limits are 3% of the nominal voltage for lighting circuits and 5% for other uses, measured from the origin of the installation to the point of use. They are set in Regulation 525 and Appendix 4, and a private supply has higher limits.

Where do the cable data come from?

Appendix 4 of BS 7671 holds the tables of current-carrying capacity and of voltage drop in millivolts per ampere per metre for each cable type, size and installation method. Cable makers publish the same data for their products.

Which comes first, current rating or voltage drop?

Both are checks on the same cable. The designer picks the size from the current rating with the correction factors, then tests the voltage drop. On long runs the voltage drop usually decides the size, and on short runs the current rating does.