A battery storage system in Great Britain connects as a generator that also imports. G99 Issue 2 adds mandatory requirements for modules with storage from 1 March 2026, the Grid Code applies to larger plants, and the design must address import and export, protection and compliance evidence together.
Short answer: a battery is both a load and a generator
In Great Britain a battery storage system connects as a power generating module that also imports, so the connection must cover export and import, and both must be within the offer. For plants on the distribution network, ENA EREC G99 applies. Larger plants also follow the Grid Code. The queue reform affects the timing of offers.
The technical documents are introduced in the UK electrical codes and grid connection guide. The process follows the same stages as for a solar farm, described in the sister guide on solar farm grid connection. What changes for storage is set out below.
What is different about storage
- Two directions. The offer states an export capacity and an import capacity. The two can differ, and each is tied to its own limits and charges.
- Frequency response. Under G99 Issue 2, published on 10 March 2025, new mandatory requirements for modules that include electricity storage apply from 1 March 2026. One of them is that storage that is importing must respond to falling frequency, which clause 11.2.3.3 sets out. Confirm with the network operator which issue applies.
- Co-location. A battery beside a solar farm shares the point of connection. The combined export and import, and the way the plant controller limits them, must match the offer.
- Fault contribution. The inverters limit fault current, so the contribution is small, but it counts in the network operator’s fault level study. See the guide on fault level, G74 and P26.
- Safety. Stored energy, fire and thermal runaway shape the layout and are CDM design risks. See lithium-ion batteries: safety and service life.
Which route applies
| Item | Distribution connection | Larger plant |
|---|---|---|
| Rulebook | ENA EREC G99 | Grid Code compliance process |
| Who checks | The DNO | NESO and the network owner |
| Evidence | Statements of compliance, equipment certificates, commissioning records | Grid Code compliance submissions and tests |
| Storage-specific | G99 Issue 2 requirements for modules with storage | Grid Code requirements for the plant type |
G99 sorts modules into Types A to D by capacity and voltage: Type A from 0.8 kW, B from 1 MW, C from 10 MW, and D from 50 MW or at 110 kV and above. The queue reform decides when the project can move. Ofgem agreed on 3 June 2026 a timetable in which offers are issued in batches, with the last batch expected by mid-March 2027. Confirm the status of your project with the network operator.
The design topics the application raises
- Point of connection and metering, including a separate import meter if the offer asks for it.
- Plant controller that limits export and import to the offer, and responds to frequency as the rules require. See BESS parts and standards.
- Protection and interface settings for the connection. See interconnection relays for generation.
- Short-circuit data for the inverters and the transformer.
- Commissioning with tests that prove the controller and protection. See BESS commissioning: tests and requirements.
Worked example: ratings from import and export
All figures are illustrative.
- Battery system: 20 MW export, 20 MW import, 40 MWh usable energy.
- Connection voltage: 33 kV.
- Operating power factor at the point of connection: 0.95.
- Duration at full power: 40 MWh ÷ 20 MW = 2 hours.
- Apparent power at 0.95: 20 ÷ 0.95 = 21.05 MVA.
- Current at 33 kV: 21 050 kVA ÷ (√3 × 33 kV) = 21 050 ÷ 57.16 = 368 A.
- Type: 20 MW lies between 10 and 50 MW, so it is a G99 Type C module.
The same 368 A flows in both directions, so the switchgear and cable are rated for it either way. If the offer limited import to 15 MW while the battery could import 20 MW, the controller would have to limit charging to 15 MW. A full charge from empty would then take 40 ÷ 15 = 2.67 hours, against 2 hours. That shows why the import limit is an energy and operations question as well as a connection one.
Operating limits and how they are controlled
The offer sets limits that the plant must respect at the point of connection, and the battery controller is the device that enforces them. Typical limits are a maximum export, a maximum import, and a power factor or voltage control mode. A limit that the controller cannot hold is a compliance problem, not only a commercial one. The controller therefore needs a measurement at the point of connection, a defined response time and a safe state if the measurement or the communication fails.
Two points deserve early attention. First, the state of charge: a battery that is full cannot import and one that is empty cannot export, so the energy plan and the connection limits must agree. Second, the order of priorities: if frequency response, an export limit and a market instruction conflict, the controller needs a written rule on which wins. The network operator’s requirements come first, and the design documents should say so.
Checklist for the engineer
- Check export and import capacity separately against the offer.
- Confirm the G99 issue that applies and the storage requirements in it.
- Define how the plant controller limits power at the point of connection.
- Collect inverter fault current data and the transformer data for the fault level study.
- Add the protection and interface settings to the single-line diagram.
- Address fire, thermal runaway and access in the layout and in the design risk record.
- Plan commissioning tests for the controller and the protection.
- Route the design to your chartered engineer for review.
Related guides
See the sister guide on fault levels for the studies the network operator runs, and the CDM 2015 guide for the design risk duties that apply to a battery site.
From the process to engineering your chartered engineer can review
We prepare the engineering package for a battery connection: single-line diagram, controller and protection philosophy, fault data and the documents the network operator asks for. It is ready for your chartered engineer to review and sign off. Tiza does not sign, seal or certify designs in the UK. Contact us with the capacity, voltage and offer status.
Frequently asked questions
Does a battery need a G99 application?
Yes, when it connects to a distribution network and can export above the G98 limit of 16 A per phase. G99 treats a battery as a power generating module. It is assessed by Type, from its capacity and connection voltage.
What changed for storage in G99 Issue 2?
Issue 2 was published on 10 March 2025. Its new mandatory requirements for modules that include electricity storage apply from 1 March 2026. One of them is that storage that is importing must respond to falling frequency. Confirm with the network operator which issue applies to your application.
Is a battery connected alongside a solar farm one application or two?
That depends on the network operator and the arrangement. A co-located battery adds import and export that the offer must cover. The point of connection, metering and capacity limits determine how it is assessed, so raise it at the start.