A power park module must supply and absorb reactive power at the grid entry point, and it must control voltage there. In the GB Grid Code the reactive capability sits in ECC.6.3.2. The inverters make the reactive power, but the transformer and cables consume some of it on the way, so the design checks the capability at the grid entry point and not at the inverter terminals.
Short answer: where reactive capability must be proven
A power park module (PPM) must be able to supply and absorb reactive power at the grid entry point and to control voltage there. In the GB Grid Code the reactive capability requirement is in ECC.6.3.2. The inverters make the reactive power, but the step-up transformer and the cables consume part of it on the way, so the capability the grid sees is smaller than the capability at the inverter terminals. A design checks the figure at the grid entry point. Voltage control is a separate clause of the same section. The current text is Grid Code Issue 6, Revision 46, dated 8 October 2026. The wider context is in the Grid Code overview.
Capability and control are two requirements
Keep two ideas apart.
- Capability is how much reactive power the plant can give or take at a given active power. It is a property of the equipment, shown as a PQ chart.
- Voltage control is how the plant uses that capability, through a plant controller that changes reactive output to hold a voltage target at the connection point.
The capability requirement defines the range, and the control requirement defines the behaviour inside it. The control mode, the target, the slope and the response time are set in the connection process, so the design should leave room for the network operator to specify them. See the connection offer guide for how such conditions appear in an offer.
Where the reactive power goes
Between the inverter terminals and the grid entry point there are three effects:
- Inverter limit. The inverter has an apparent power rating S. At active power P, the reactive power available is √(S² − P²).
- Transformer consumption. A transformer consumes reactive power in its leakage reactance: about I² × X, which grows with the square of the loading.
- Cable and filter effects. Cables produce reactive power through charging. Harmonic filters and capacitors add more. These effects can help or hurt, depending on loading.
Worked example: capability at the grid entry point
All values are illustrative and assumed. The example shows the method. The capability figure that applies comes from the Grid Code and the connection offer.
Plant: a PPM exporting 40 MW. The inverters are rated 44 MVA in total. The step-up transformer is 50 MVA with 10 % leakage reactance. Cable charging is ignored to keep the example simple.
Step 1, inverter capability at 40 MW. Reactive power available = √(44² − 40²) = √(1,936 − 1,600) = √336 = 18.33 Mvar.
Step 2, transformer consumption when the inverters supply 18.33 Mvar. The apparent power through the transformer is the full 44 MVA. Reactive consumption = 0.10 × 50 MVA × (44 ÷ 50)² = 5 × 0.7744 = 3.87 Mvar.
Step 3, net supply at the grid entry point (lagging). 18.33 − 3.87 = 14.46 Mvar. The power factor is 40 ÷ √(40² + 14.46²) = 40 ÷ 42.53 = 0.940 lagging.
Step 4, absorbing case. When the inverters absorb 18.33 Mvar, the transformer consumes another 3.87 Mvar from the grid. The grid sees 18.33 + 3.87 = 22.20 Mvar absorbed. The power factor is 40 ÷ √(40² + 22.2²) = 0.874 leading.
The two directions are not symmetrical, which is the point of the check. Suppose the requirement were a reactive range of 33 % of the 40 MW, which is 13.2 Mvar. This plant clears it on both sides: 14.46 and 22.20 Mvar are both above 13.2 Mvar. The 33 % figure is an assumption for the example. Use the value in the clause and in your connection offer.
The next step is to repeat the calculation at lower active power. Reactive capability at partial load is often larger at the inverter but the voltage at the grid entry point changes, so a load flow is needed. See the load flow guide.
Voltage control: what the plant controller does
A plant controller measures voltage at the connection point and sends reactive setpoints to the inverters. Points the design must settle:
- the voltage reference and the slope, set with the network operator;
- the response time, which depends on the controller scan and the inverter communications;
- the priority between reactive and active power when the inverter limit binds;
- what happens if communications fail.
For the plant communications architecture see communications of a solar plant. For the power-factor side of solar plants see solar panels and power factor.
Common design mistakes
- Quoting inverter capability as plant capability. The figure at the grid entry point is smaller on the supply side and larger on the absorbing side, as the example shows.
- Ignoring partial load. A plant spends most of its time below rated output, and the capability and the voltage at the grid entry point change with loading.
- Leaving the controller to the end. The control mode, slope and response time drive the plant controller design and the communications. Settle them while the design is still flexible.
Checklist for the engineer
- Record the Grid Code issue and revision, and check ECC.6.3.2 in that revision.
- Draw the PQ chart at the grid entry point, not at the inverter terminals.
- Include transformer and cable effects at both ends of the range.
- Check the capability at partial active power as well as at full output.
- Confirm the voltage control mode, target and slope with the network operator.
- Define the controller response time and the behaviour on communication loss.
- Run a load flow for the voltage at the connection point across the range.
- Route the design to your chartered engineer for review before submission.
Related guides
The fault-time behaviour of the same plant is in fault ride through for power park modules. The UK series starts at the UK codes overview.
From the clause to a design your chartered engineer can sign off
We prepare the power-system studies and the engineering design behind a reactive capability submission: PQ capability at the grid entry point, load flow, controller concept and the evidence list. The package is ready for your chartered engineer to review and sign off before it goes to the network operator. Tiza does not sign or certify designs in the UK. Contact us with the site data and the connection offer.
Frequently asked questions
Where is the reactive capability requirement in the Grid Code?
For power park modules it is in the European Connection Conditions, at ECC.6.3.2. Confirm the clause text in the issue and revision in force, because the Grid Code changes several times a year.
Is reactive capability measured at the inverter or at the grid entry point?
At the grid entry point, which is the connection to the network. Transformers and cables consume reactive power, so an inverter that meets the figure at its terminals can fall short at the grid entry point.
What is voltage control in this context?
The plant controller changes reactive output to hold the voltage at the connection point to a target, following a slope or other characteristic that the network operator specifies. The control mode and settings are agreed in the connection process.