Section PPM1 of the EirGrid Grid Code (Version 18) is the special rulebook for wind and solar plants connected to the Irish transmission system, which earlier versions called WFPS1. It sets voltage operating ranges, a reactive capability of 0.95 power factor at the connection point, three reactive control modes, ramp rates, frequency response and a list of signals the plant must send to EirGrid. Capability is measured at the connection point, so the transformer and collector network count.
Short answer: what EirGrid asks of wind and solar plants
Wind and solar plants connected to the Irish transmission system follow section PPM1 of the EirGrid Grid Code, called Controllable PPM Power Station Grid Code Provisions in Version 18 (issued 27 October 2026). Earlier versions called the same section WFPS1, from wind farm power station. A power park module (PPM) is a plant of many converter-based units that acts as one plant at the connection point. PPM1 adds its own requirements and removes the clauses written for synchronous machines.
The general map of the code is in the guide to the EirGrid Grid Code, and the wider context is in the Ireland and New Zealand grid codes guide. The ride-through rules have their own guide.
Scope: what applies on top of PPM1
Clause PPM1.3.2 says a controllable PPM also complies with the General Conditions, the Planning Code and its appendix, the Connection Conditions, and most Operating Conditions, with a stated list of excluded clauses. The excluded items are mostly those that describe synchronous generators, such as machine-specific parts of CC.7.3.
PPM1.1 also deals with extensions to an existing plant. An extension that is not separately controllable is a Transmission Connected Type A extension. A separately controllable extension is treated as a unique PPM, except for the voltage requirements in PPM1.6, which are tested together with the existing plant. EirGrid can require full compliance testing of either type. If the existing plant holds a derogation, the extension is treated as separately controllable. Plan extensions at the start, because they reopen the plant’s compliance position.
Voltage operating range at the connection point
Clause PPM1.6.1 requires the plant to stay connected at maximum available power for normal and disturbed conditions and for voltage steps of up to 10 %. Version 18 prints two versions of this clause: one for plants under RfG and one for the others. Confirm in the connection agreement which one binds the plant. One gives 350 to 420 kV at 400 kV and 200 to 245 kV at 220 kV. The other gives these continuous ranges at the connection point:
| System | Continuous range | Per unit |
|---|---|---|
| 400 kV | 360 kV to 420 kV | 0.9 to 1.05 |
| 220 kV | 198 kV to 245 kV | 0.9 to about 1.11 |
| 110 kV | 99 kV to 123 kV | 0.9 to about 1.12 |
The grid-connected transformer must have a tap range able to hold nominal voltage on its lower-voltage side for any connection-point voltage within these ranges. This is a transformer specification item, and it is checked in the load-flow study.
Reactive capability and control modes
Clause PPM1.6.3.1 sets the minimum P-Q capability, measured at the connection point. At 100 % of registered capacity the plant must reach 0.95 power factor leading and lagging. It keeps the same Mvar capability as output falls to 12 % of registered capacity. Below that, the capability depends on the number of units generating. The plant must tell EirGrid if it can exceed these values, and it submits its actual P-Q diagram, based on the installed plant and collector network, during commissioning.
The voltage regulation system (PPM1.6.2) must offer three steady-state modes, with one active at all times and smooth transfer between them:
- Power factor control at the connection point, held within a tolerance of 0.5 %.
- Reactive power control to a Mvar set-point, with steps no greater than 5 Mvar or 5 % of maximum reactive power, whichever is smaller.
- Voltage regulation to a kV set-point between 0.95 and 1.05 per unit, with 90 % of the reactive response delivered within 1 second of a voltage step and settling within 5 seconds.
A change of set-point from EirGrid must be implemented within 20 seconds. The plant controller therefore has to accept all three modes from the remote control signal, not only the one used at commissioning.
Active power control, ramp rates and signals
PPM1.5.2 requires a control system that accepts an active power set-point from EirGrid and starts to implement it within 10 seconds. Three ramp rates apply, in priority order: the frequency response ramp rate, the set-point ramp rate and the resource-following ramp rate. EirGrid sets the last two as a percentage of registered capacity per minute. The frequency side is covered in the frequency response guide.
PPM1.7 lists the signals the plant sends to EirGrid. Signals List 1 applies to every plant. It includes active and reactive power, voltage and available active power at the low-voltage side of the grid-connected transformer. It also includes tap position, the status and feedback of each reactive control mode, and breaker positions. Further lists cover meteorological data, availability, active power control data and frequency response data. EirGrid specifies the circuit-breaker signals and site signal lists at least 120 Business Days before the Operational Date.
Worked example: reactive capability for a 30 MW solar plant
The figures are illustrative. A solar plant has a registered capacity of 30 MW. Its grid-connected transformer is 40 MVA with 10 % impedance on its own base. Cable charging and cable losses are ignored to keep the arithmetic visible.
- Required Q at the connection point at 0.95 power factor: Q = 30 × tan(arccos 0.95) = 30 × 0.3287 = 9.86 Mvar.
- Apparent power at the connection point: S = 30 ÷ 0.95 = 31.58 MVA.
- Transformer reactive loss: Q_loss = x × S² ÷ S_base = 0.10 × 31.58² ÷ 40 = 2.49 Mvar.
- Producing (lagging) case: the inverters must supply 9.86 + 2.49 = 12.35 Mvar on the low-voltage side, with 30 MW. Apparent power there is √(30² + 12.35²) = 32.44 MVA.
- Absorbing (leading) case: the transformer already consumes 2.49 Mvar, so the inverters absorb 9.86 − 2.49 = 7.37 Mvar.
- At 12 % output (3.6 MW) the same 9.86 Mvar is still required, which is a power factor of 3.6 ÷ √(3.6² + 9.86²) = 0.34.
The sizing lesson: inverter apparent power must cover about 32.4 MVA for a 30 MW plant in the producing case. The low-output requirement can also drive extra compensation if the inverters cannot deliver reactive power at low active power.
How this compares with other regimes
Great Britain sets a different reactive range; compare it in the GB reactive capability guide and in GB power park module ride-through. Australia negotiates the reactive range per plant, as in the S5.2.5.1 guide. The US inverter standard is in the IEEE 2800 guide.
Checklist for the engineer
- Confirm the Grid Code version and the PPM1 clauses used in the design basis.
- Check whether the project is a new PPM or an extension, and which type.
- Verify the voltage range for the connection voltage and the transformer tap range.
- Size inverters and compensation for the capability at the connection point, not at the inverter terminals.
- Check the capability at 12 % output as well as at full output.
- Configure the three reactive modes and the 20-second set-point implementation.
- Confirm the signal list and the meteorological signals for plants above 10 MW.
- Keep the design package ready for your chartered engineer to review and sign.
From PPM1 to a design your engineer can sign
PPM1 translates into transformer ratings, inverter and compensation sizing, controller functions and a signal list. Tiza prepares the engineering design for solar and wind plants, with the capability checks written out against the clauses. Tiza does not stamp, sign or certify. The package is delivered ready for your chartered engineer, registered with Engineers Ireland, to review and sign. Where the scope includes installation, a contractor registered with the Register of Electrical Contractors of Ireland (RECI) carries it out. Contact us with the plant data.
Frequently asked questions
What does WFPS mean in the EirGrid Grid Code?
WFPS stands for wind farm power station. Earlier versions of the Grid Code used it for the section covering wind plants. Version 18 calls the section PPM1 and covers controllable power park modules, a term that includes solar plants as well as wind.
Where must reactive power capability be met?
At the connection point. Clause PPM1.6.3.1 allows additional reactive compensation to cover the reactive demand of the connection between the connection point and the plant, so the transformer and the collector network are part of the design, not an afterthought.
Does a solar plant have to send weather data to EirGrid?
Clause PPM1.7.1.2 lists meteorological signals. For wind and solar plants above 10 MW of maximum export capacity the list includes wind speed for wind plants and irradiance values for solar plants. EirGrid fixes the actual signal list for each site at least 120 Business Days before the Operational Date.