ESB Connection Offer and Grid Assessment, Explained

How to review an ESB Networks generator connection offer: what it fixes, staged payments, contestable works, the studies behind it and an export check.

By Shadai García, CEO and protection engineer at Tiza Group.

Offer: MEC, node, works,charges, conditionsWorkscontestable?NoYesNon-contestable:ESB NetworksbuildsContestable:developer buildsto functional specsTransfer: H&S file,wayleaves, warranties,consentsConditions to energise:settings, studies, payments22 MW possible, MEC 18 MW; hourly outputtotal 4+9+15+20+22+20+15+9+4 = 118 MWhabove 18 MW: 2 + 4 + 2 = 8 MWhexported: 118 - 8 = 110 MWhlost: 8 / 118 = 6.8 % on this sample day41921532042252061579849MEC 18 MWhour of the sample dayillustrative; one day, not a yearly figureOfferOfferContestable?BuildTransferEnergise© tizagrp.comOffer: MEC, node, works,charges, conditionsWorkscontestable?NoYesNon-contestable:ESB NetworksbuildsContestable:developer buildsto functional specsTransfer: H&S file,wayleaves, warranties,consentsConditions to energise:settings, studies, payments22 MW possible, MEC 18 MW; hourly outputtotal 4+9+15+20+22+20+15+9+4 = 118 MWhabove 18 MW: 2 + 4 + 2 = 8 MWhexported: 118 - 8 = 110 MWhlost: 8 / 118 = 6.8 % on this sample day41921532042252061579849MEC 18 MWhour of the sample dayillustrative; one day, not a yearly figureOfferOfferContestable?BuildTransferEnergise© tizagrp.com
Flow chart of an ESB Networks connection offer: the offer fixes the Maximum Export Capacity, the node, the works, the charges and the conditions, then a decision on whether the works are contestable, non-contestable works built by ESB Networks, contestable works built by the developer to functional specifications and transferred with the health and safety file, wayleaves, warranties and consents, both ending in the conditions to energise; with the MEC check of an 18 MW offer against a 22 MW solar plant, 118 MWh available, 8 MWh above the MEC and 6.8 percent lost on the sample day. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

An ESB Networks connection offer for a generator is issued after the grid studies behind a batch application. It sets the connection method, the works, the charges and the conditions to energise, and it becomes a Connection Agreement when accepted. ESB Networks guidance describes staged payments, a split between non-contestable works built by ESB Networks and contestable works built by the developer, project-specific protection settings and EirGrid dynamic studies before energisation. The engineer should check the Maximum Export Capacity, the point of connection, the payment stages and the technical conditions line by line.

Short answer: the ESB connection offer

An ESB connection offer is the document that turns a batch application into a defined connection: the connection method and works, the charges, the payment stages and the conditions to energise. When it is accepted it forms the basis of the Connection Agreement, which the Distribution Code says contains the detail specific to each user’s connection. The offer rests on the grid studies done for the application. The checks are set out below; the application steps are in the Ireland connection process guide.

For the framework see the Ireland and New Zealand grid codes guide. The Great Britain comparison is the UK DNO connection offer guide.

What documents sit around the offer

  • The quotation letter and offer. ESB Networks guidance says staged payments are usually set in a clause of the quotation letter, and the detail is then in the Connection Agreement.
  • The Distribution Code, Version 8.0. It sets the technical conditions the plant must meet (DCC10 and DCC11) and requires the user to comply with it through the Connection Agreement (DCC1.4).
  • ESB Networks company standards. The medium voltage conditions (DTIS-250701-BDW, Version 2, 25 July 2019) cover interface protection and testing before parallel operation.
  • ESB Networks information pack for generator projects (DOC-040214-BQQ, dated 4 February 2014), written for developers with an export capacity above 200 kW. It is guidance only and the Connection Agreement governs, so use it for the structure of the process and not for current timelines.
  • Standard prices for generator connections. ESB Networks publishes a 2026 price document alongside the ECP pages.

What to read first in the offer

  1. Maximum Export Capacity and point of connection. Check the MEC value, the voltage level and the node. All other terms hang from them.
  2. The works and who builds them. The pack separates non-contestable works, built by ESB Networks, from contestable ones, which the developer can build to functional specifications and then transfer. Transfer brings health and safety file, site transfers, wayleaves, warranties and consents.
  3. Charges and payment stages. Staged payments follow the Connection Agreement. In the pack’s description the first stage is due at offer acceptance and covers preliminary design and consent, including planning, and later stages follow as detailed design and construction proceed. Where an offer has three stages, the full capital contribution is payable before energisation. A single payment may apply where the works are small.
  4. Technical conditions. Protection standard, metering and telecoms, supervisory control and data acquisition (SCADA) signals, grid code compliance testing, and any special arrangements.
  5. Modifications. A change to the generator data or a connection that was applied for on assumed data can require a modification, and late changes can carry a fee and delay energisation.
  6. Group offers. The pack notes that offers are typically issued around a hub station and can be accepted by different developers at different times, after which the group is assessed again.

The grid assessment behind the offer

The offer is only as good as the study that supports it. Three layers are worth understanding:

  • Network studies for the application. The batch application is assessed against the network, which sets the connection method and any reinforcement.
  • Dynamic studies by EirGrid. The pack says EirGrid carries out these to determine the effect of the proposed generators on the system, and they must be done before energisation. Changed turbine or inverter data, or an application based on assumed data, can need revised studies.
  • Protection settings. They are project specific and are requested before energisation. For contestable projects the developer prepares the settings request. The standard of protection is advised in the connection conditions.

The ESB Networks protection requirements guide covers what those settings contain, and the Distribution Code guide covers the generator types.

Worked example: does the offered MEC fit the plant?

The figures are illustrative. A solar plant has inverters that can deliver up to 22 MW at the connection point at midday, but the offer gives an MEC of 18 MW. A nine-hour sample of hourly average output in MW is: 4, 9, 15, 20, 22, 20, 15, 9, 4.

  1. Total available energy = 4 + 9 + 15 + 20 + 22 + 20 + 15 + 9 + 4 = 118 MWh.
  2. Hours above 18 MW are the three middle-day hours: excess = (20 − 18) + (22 − 18) + (20 − 18) = 2 + 4 + 2 = 8 MWh.
  3. Energy exported = 118 − 8 = 110 MWh.
  4. Share lost = 8 ÷ 118 = 6.8% on that sample day.

This is one day, not a yearly figure, so it shows the method and not the result. Repeat it with a full year of production data before you decide. The options are to accept 18 MW, ask for a larger MEC in a modification, or add storage that absorbs the peak. The offer fixes the MEC, and changing it later has a cost.

Checklist for the engineer

  • Compare MEC, voltage level and node in the offer with the application.
  • Draw the connection arrangement from the offer on a single line diagram and check it matches the plan.
  • List which works are contestable and what the transfer to ESB Networks requires.
  • Map each payment stage to a project milestone and a date in the programme.
  • Read the technical conditions and cross-check them against the Distribution Code version.
  • Confirm which protection standard and relay types ESB Networks will require.
  • Check the generator data used in the studies against the equipment you will buy.
  • Record every assumption and ask ESB Networks in writing about anything unclear.

From the offer to a design your engineer can sign

Before accepting an offer, the plant design has to be shown to fit it. We prepare the engineering design and the power-system studies for that check: single line diagram, short-circuit and load flow, protection philosophy and the data the operator asks for. Tiza does not sign, stamp or certify designs in Ireland. We deliver engineering and studies ready for your Chartered Engineer (Engineers Ireland) to review and sign. Contact us with the offer and the project data.

Related guides: UK Distribution Code and DNO offers, UK connection studies, which interconnection study each market requires and short-circuit study.

Frequently asked questions

What does an ESB Networks connection offer contain?

The offer and its quotation letter set out the connection method and the works, the charges and the payment stages, and the conditions that apply. Once accepted, it forms the basis of the Connection Agreement, which also sets details such as the type of communications for metering.

What are contestable and non-contestable works?

Non-contestable works are designed and built by ESB Networks. Contestable works can be built by the developer, to functional specifications issued by ESB Networks, and then transfer to ESB Networks once legal and technical requirements are met.

Which studies sit behind the offer?

The offer follows the network studies done for the batch. Before energisation, EirGrid also carries out dynamic studies on the proposed generators, and ESB Networks issues project-specific protection settings. The details required for those depend on the project and are set out in the offer conditions.