In Ireland, a generator, storage or system-services project applies under the Enduring Connection Policy. Since the CRU decision of September 2024 the process runs in six-monthly batches called ECP-GSS, with a pre-application notice before each application. Projects with a total Maximum Export Capacity below 40 MW at one location apply first to ESB Networks for a distribution connection, and those of 40 MW or more apply first to EirGrid for a transmission connection. Applications use form NC5 or the shorter NC5A, sent electronically.
Short answer: the Ireland connection process
The Ireland connection process for generation, storage and system-services projects runs under the CRU’s Enduring Connection Policy. Applications are accepted in batches, not at any time. Under ECP-GSS, the current framework, the CRU decision of 26 September 2024 replaced the single yearly window with six-monthly batches. Before each batch, the applicant sends a pre-application notification (PAN). The grid application then goes to ESB Networks if the total Maximum Export Capacity (MEC) at one location is under 40 MW, or to EirGrid if it is 40 MW or more.
The overall picture of the Irish codes is in the Ireland and New Zealand grid codes guide. For the equivalent in Great Britain, see the UK battery storage connection process.
Who does what
Ireland has two network operators with separate roles. EirGrid is the transmission system operator. ESB Networks is the distribution system operator and also receives generator applications under 40 MW. Both operate under the CRU, which approves the connection policy and the Connection Offer Process.
- Under 40 MW total MEC at one location: apply to ESB Networks for a distribution connection.
- 40 MW or more total MEC at one location: apply to EirGrid for a transmission connection.
MEC is the maximum power the plant may export at the connection point. It is the figure that decides the route, so a project built in phases at one site counts every phase.
How the batches work
The policy has changed several times, so cite the decision that applies to your batch.
- ECP-2 to ECP-2.5. The earlier rounds used a single yearly window. The ECP-2.4 decision paper (CRU202326, April 2023) set the prioritisation used for the ECP-2.5 batch, whose window ran from 1 October to 30 November 2024.
- ECP-GSS. The CRU decision of 26 September 2024 (CRU/2024101) moved to six-monthly deadlines, with the first in September 2025. Completed planning applications need only to be acknowledged, not granted, to enter. It widened the opportunities for smaller and non-exporting projects, repowering and community-led projects.
- Pre-engagement and High-Level Technical Assessment. The CRU decision of 6 June 2025 (CRU202584) set the pre-application process for the September 2025 batch.
- September 2026 batch (ECP-GSS-3). A CRU information note of 2 June 2026 (CRU202689) removed the requirement that grid applications for projects covered by the Renewable Energy Directive (RED III) include a valid High-Level Technical Assessment. Both RED III and other projects had to submit the PAN by 30 June 2026.
Results appear as batch lists on the EirGrid and ESB Networks sites. EirGrid lists the September 2025 batch (ECP-GSS-1) as final in May 2026 and the March 2026 batch (ECP-GSS-2) as an initial publication.
What you send to ESB Networks
For a distribution application, ESB Networks describes these items:
- The PAN with the application fee deposit, by email, before the deadline. Late PANs are not accepted.
- Form NC5 when the generator make and model are known, or NC5A, a shorter form where the study uses assumed data.
- A 1:50,000 Discovery Series Ordnance Survey map, a detailed site plan and a draft single line diagram.
- The landowner consent confirmation and, where the planning permission names an MEC, a figure that matches the form.
The fee depends on installed generation capacity and Maximum Import Capacity, and the 2026/2027 table is on the ESB Networks page. A deposit is paid with the PAN and the balance with the grid application. Check the amounts there before budgeting.
Beyond the application
After a project is in a batch, ESB Networks and EirGrid process the studies and issue the connection offer. The offer fixes the connection method, the works, the charges and the conditions to energise. Reading it is covered in the ESB connection offer guide. Technical requirements that the plant must then meet come from the ESB Networks Distribution Code or from the Grid Code, with grid forming as a future topic.
Worked example: which route for a phased site
The figures are illustrative. A developer plans solar and storage in three phases at one location. Phase 1 has an MEC of 15 MW, Phase 2 has 12 MW and Phase 3 has 16 MW.
- After Phase 1 the total MEC is 15 MW. That is under 40 MW, so the application goes to ESB Networks.
- After Phase 2 the total is 15 + 12 = 27 MW. It is still under 40 MW, so the distribution route still applies.
- After Phase 3 the total is 27 + 16 = 43 MW. It is above the 40 MW threshold, so the project falls under the transmission route through EirGrid.
The lesson is to decide the full build-out before the first application. The route follows the total MEC at one location, so a later phase can move the whole site to the other operator. Define the site MEC for all phases from the start.
Checklist for the engineer
- Add up the total MEC at the location, including planned phases, and choose the operator.
- Identify the current batch, its PAN deadline and the CRU document that governs it.
- Decide whether the generator model is known (NC5) or assumed (NC5A).
- Prepare the map, site plan and single line diagram to the operator’s format.
- Confirm that the planning application status meets the batch rule.
- Check that the PAN and fee deposit arrived. The applicant must confirm receipt.
- Put the batch rules, forms and dates in the design basis for the engineer of record.
From the application to a design your engineer can sign
An application is only as good as its single line diagram, load flow and short-circuit inputs. We prepare the engineering design and power-system studies that support a connection file. Tiza does not sign, stamp or certify designs in Ireland. We deliver engineering and studies ready for your Chartered Engineer (Engineers Ireland) to review and sign. Installation is left to a contractor registered with the Register of Electrical Contractors of Ireland (RECI). Contact us with the site data and the batch you are targeting.
Related guides: which interconnection study each market requires, UK DNO connection offers, Australia embedded generation connection, US interconnection studies and power flow study.
Frequently asked questions
Who do I apply to for a generator connection in Ireland?
It depends on the total Maximum Export Capacity at one location. Under 40 MW, apply first to ESB Networks for a distribution connection. At 40 MW or more, apply first to EirGrid for a transmission connection. Both operators publish the current batch rules on their sites.
What is ECP-GSS?
The Electricity Connection Policy for Generation and System Services, set by the Commission for Regulation of Utilities (CRU) in a decision published on 26 September 2024. It moved applications from one annual window to six-monthly batches and added a pre-engagement step before the application.
What is the difference between the NC5 and NC5A forms?
ESB Networks asks for the NC5 when the generator make and model are known, and the shorter NC5A when the study is done on assumed data. Both go in electronically, within a combined file size limit set by ESB Networks.