Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

NZ Solar and Battery Connection Requirements by Distributor

New Zealand solar and battery connection requirements: what Part 6 sets, what each distributor adds, inverter standards, export limits and an example.

By Shadai García, CEO and protection engineer at Tiza Group.

PV 8 kWbattery5 kW=~8 kW inverter=~5 kW invertersite loadbreakerCTconnection pointgridexport limiter10 kW at PoCto distributordynamic exportPowerMeasure / controlComms8 kW solar + 5 kW battery, threshold 10 kWevening: 5 - 1.5 = 3.5 kWmidday: 8 + 5 - 0.5 = 12.5 kWexcess 12.5 - 10 = 2.5 kW to curtailevening export 3.5 kWmidday export 12.5 kWexport held at the limit: 10 kW2.5 kW curtailed10 kW threshold051012.5 kWillustrative valuesExportSolarBatteryExport measuredExport limiterSetpoint© tizagrp.comPV 8 kWbattery5 kW=~8 kW inverter=~5 kW invertersite loadbreakerCTconnection pointgridexport limiter10 kW at PoCto distributordynamic exportPowerMeasure / controlComms8 kW solar + 5 kW battery, threshold 10 kWevening: 5 - 1.5 = 3.5 kWmidday: 8 + 5 - 0.5 = 12.5 kWexcess 12.5 - 10 = 2.5 kW to curtailevening export 3.5 kWmidday export 12.5 kWexport held at the limit: 10 kW2.5 kW curtailed10 kW threshold051012.5 kWillustrative valuesExportSolarBatteryExport measuredExport limiterSetpoint© tizagrp.com
Export limit with solar and a battery: an 8 kW PV inverter and a 5 kW battery inverter on the site bus with its load, the connection point with its breaker, CT and VT feeding an export limiter that sends a setpoint to both inverters and talks to the distributor, with midday export of 12.5 kW against a 10 kW threshold, 2.5 kW to curtail. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

In New Zealand, Part 6 of the Electricity Industry Participation Code sets how solar and battery systems apply to a distributor. Each distributor then publishes its own connection and operation standards, approved inverter list, export thresholds and forms. Since 2026, low-voltage inverters apply the Australia A settings of AS/NZS 4777.2:2020 with Amendments 1 and 2, and designs follow AS/NZS 4777.1:2024. Batteries are declared in the application.

Short answer: New Zealand solar and battery connection requirements

In New Zealand, Part 6 of the Electricity Industry Participation Code 2010 governs how a solar or battery system applies to a distributor. The distributor then sets the technical detail in its own published connection and operation standards. That is why requirements differ between networks, even though the process and the deadlines are the same.

The clauses cited are those of Part 6 with the Export Limits Amendment 2026, in force from 11 May 2026. Confirm the version date before each application. The Part 6 guide walks through the application steps and deadlines. The sections below cover what a distributor asks of the system itself.

Figure: solar array, battery and inverter behind the point of connection, with the export limit measured at the connection point.

For how Part 6 fits with Part 8 and the wider codes, see the Ireland and New Zealand grid codes guide.

What the distributor publishes

Clause 6.3 requires each distributor to publish its application forms, connection and operation standards, curtailment circumstances, fees, approved inverter makes and models, and its maximum export power threshold with the assessment method behind it. It must also list areas with current or expected export congestion. Start there, because those documents are the local rulebook.

Two examples show how distributors use that freedom. One publishes a list of approved inverters that points to an Australian approved-inverter list, and asks for a datasheet and certificate of suitability if the inverter is not listed. Another recommends that an electrician or installer completes the forms and assesses larger three-phase systems case by case. Read the standard of your own distributor.

The inverter and installation standards

  • Settings. From 11 September 2026, clause 6.3B(1) requires low-voltage inverters to apply the Australia A settings in AS/NZS 4777.2:2020 with Amendments 1 and 2. A distributor may specify different settings only after a network study shows they are needed, and they must stay within the allowed range in that standard.
  • Part 1A route. A simpler route is available if the system is designed and installed under AS/NZS 4777.1:2024. Its inverter must also have a Declaration of Conformity to AS/NZS 4777.2:2020 from a laboratory accredited or recognised by International Accreditation New Zealand. The system also needs a volt-watt and a volt-var response mode, and its export must not exceed the distributor’s threshold.
  • Regulations. The 2025 amendment to the Electricity (Safety) Regulations cites a new version of AS/NZS 4777.1 for low-voltage mains parallel generation connected to the national grid.

The Australian guides explain the standard’s content: AS/NZS 4777 for inverter grid connection and its response modes. The comparison of inverter rules places it beside IEEE 1547 and G99.

Export limits

Distributors cannot limit nameplate capacity for Part 1 or Part 1A applications. For Part 1A applications they may set a maximum export power threshold, which may not be below 10 kW unless a network study supports it. From 11 November 2026, those studies use the export limits assessment methodology. A generator may still apply for more than the threshold or for different inverter settings, and the distributor must assess the application in good faith.

Some distributors also offer dynamic export, in which the network adjusts the limit over a secure communication link. One distributor makes it conditional on AS/NZS 4777.2 compliance and communication through the Common Smart Inverter Profile (CSIP). The limit applies only to export. It does not restrict generation or self-use.

Batteries

The application form in Schedule 6.1 asks for details of the inverter and battery storage. The Electricity Authority’s registry guidance records a battery’s maximum discharge rate separately from the generation rate, and that rate can be higher. Distributors may ask for the device type, the inverter characteristics and the maximum import and export capability at the connection point.

For the safety of the battery system, read the distributor’s standard and the manufacturer’s documentation. AS/NZS 5139 is the joint standard for battery systems used with power conversion equipment. Our guides on battery energy storage parts and standards and BESS commissioning cover the system side.

After approval

Wiring is installed to the Electricity (Safety) Regulations 2010 and AS/NZS 3000 as cited, as the AS/NZS 3000 guide for New Zealand explains. The licensed installer provides a certificate of compliance. One distributor asks for it within ten working days of installation, with the approval reference, and the certificate must refer to both AS/NZS 4777.1 and AS/NZS 3000.

For larger plants, studies and protection requirements apply as well. See the protection requirements guide and the Australian comparison for embedded generation.

Worked example: export limit with a battery

All values are illustrative. A commercial site has 8 kW of solar inverter capacity and a 5 kW battery inverter. The distributor’s threshold at the connection point is 10 kW.

  1. Evening: sun is gone, the battery discharges at 5 kW and the site load is 1.5 kW. Export = 5 − 1.5 = 3.5 kW, below the limit.
  2. Midday: solar produces 8 kW, the battery is full and discharges at 5 kW for a grid service, and the load is 0.5 kW. Export = 8 + 5 − 0.5 = 12.5 kW.
  3. The excess over the threshold is 12.5 − 10 = 2.5 kW.

Summing the two inverters is what matters. The site needs an export control that holds export at the connection point to 10 kW, for example by curtailing 2.5 kW. The application must say how this control works. Sizing the two inverters separately would not have revealed the problem.

Checklist for the engineer

  • Download the distributor’s connection and operation standard, forms and approved inverter list.
  • Record the Part 6 version date and the distributor’s threshold for the connection.
  • Check that the inverter meets AS/NZS 4777.2:2020 with Amendments 1 and 2 and applies the required settings.
  • Declare the inverter and the battery, including maximum discharge rate, in the application.
  • Add up all sources and storage at the connection point, not only the solar capacity.
  • Describe the export control and, where offered, the dynamic export communication.
  • Plan the certificate of compliance and its submission after installation.
  • Check for protection or study requirements as the capacity rises.

From the distributor’s rules to a design ready for your engineer

Distributors want an application they can assess without questions: single-line diagram, inverter and battery data, export control logic and, for larger systems, short-circuit and protection data. In New Zealand the design is reviewed and signed by a Chartered Professional Engineer (CPEng, registered with Engineering New Zealand), and licensed electrical workers carry out the installation. Tiza does not sign or certify designs in New Zealand. We deliver engineering design for solar and storage systems, ready for your CPEng to review and sign. Contact us with the site data and your distributor’s standard.

Frequently asked questions

Who sets the technical requirements for a solar or battery connection in New Zealand?

Part 6 of the Electricity Industry Participation Code sets the process and the information the distributor must publish. The distributor's own connection and operation standards set the technical detail, so requirements differ by network. Wiring is covered by the Electricity (Safety) Regulations 2010 and AS/NZS 3000.

Which inverter standards apply?

From 11 September 2026, clause 6.3B of Part 6 requires low-voltage inverters to apply the Australia A settings in AS/NZS 4777.2:2020 with Amendments 1 and 2, unless a network study supports other settings. The Part 1A route also refers to design and installation under AS/NZS 4777.1:2024.

Do batteries need an application?

Yes. The application form asks for details of the inverter and battery storage, and one distributor treats batteries as distributed energy resources. Distributors may ask for the battery's maximum import and export capability at the connection point.

WhatsApp