Part 6 Distributed Generation: Connecting in New Zealand

Part 6 distributed generation in New Zealand: the 10 kW and above-10 kW routes, decision deadlines by size and a worked timeline for a 3 MW solar plant.

By Shadai García, CEO and protection engineer at Tiza Group.

over 10 kWin total?noPart 1, 1A:one stage,10 kW or lessyes, Part 2Initial application: complete in 5 days (cl. 11)Distributor information in 30 days (cl. 12)Final application within 12 months (cl. 15)Decision by size (cl. 19): 45 days under 1 MW,60 from 1 to under 5 MW, 80 at 5 MW or moreNotice, 30 days (cl. 20); negotiation, 30 days (cl. 21)Testing and connection (cl. 22 to 24)3 MW plant: band 1 MW to under 5 MWmaximum periods, no extensions5 + 30 + 60 + 30 + 30 = 155 business days155 / 5 = 31 weeksCompleteness, cl. 115Information, cl. 1230Decision, cl. 1960Notice, cl. 2030Negotiation, cl. 2130050100155business daysbefore holidays, extensions, studies and testingSchedule 6.1InitialInformationFinalDecisionContract© tizagrp.comover 10 kWin total?noPart 1, 1A:one stage,10 kW or lessyes, Part 2Initial application: complete in 5 days (cl. 11)Distributor information in 30 days (cl. 12)Final application within 12 months (cl. 15)Decision by size (cl. 19): 45 days under 1 MW,60 from 1 to under 5 MW, 80 at 5 MW or moreNotice, 30 days (cl. 20); negotiation, 30 days (cl. 21)Testing and connection (cl. 22 to 24)3 MW plant: band 1 MW to under 5 MWmaximum periods, no extensions5 + 30 + 60 + 30 + 30 = 155 business days155 / 5 = 31 weeksCompleteness, cl. 115Information, cl. 1230Decision, cl. 1960Notice, cl. 2030Negotiation, cl. 2130050100155business daysbefore holidays, extensions, studies and testingSchedule 6.1InitialInformationFinalDecisionContract© tizagrp.com
Schedule 6.1 flow of Part 6 distributed generation: the route by size, 10 kW or less in one stage (Parts 1 and 1A) or more than 10 kW in two stages (Part 2) with the initial application, distributor information in 30 business days, final application within 12 months, decision in 45, 60 or 80 business days by size, notice and negotiation of 30 business days each, and testing and connection; and the maximum timeline of a 3 MW plant, 155 business days or 31 weeks. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Part 6 of the Electricity Industry Participation Code sets how distributed generation connects to a local distribution network. Schedule 6.1 gives a one-stage route for systems of 10 kW or less and a two-stage route, initial then final application, above 10 kW, with decision deadlines of 45, 60 or 80 business days by size. Distributors publish their application forms, standards and approved inverters.

Short answer: Part 6 distributed generation

Part 6 of the Electricity Industry Participation Code 2010 governs distributed generation in New Zealand: generation connected to a distribution network or to a consumer installation that is itself connected to one. Its purpose, in clause 6.2, is to let distributed generation connect where this is consistent with connection and operation standards. Distributors, the local network companies, process the applications. Part 6 sets the steps, the deadlines and the information they must publish.

The clauses cited are those of the Part 6 version on the Electricity Authority website, including the Export Limits Amendment of 11 May 2026. Confirm the version date before you apply. The Ireland and New Zealand grid codes guide shows how Part 6 fits with Part 8.

What the distributor must publish

Under clause 6.3, each distributor must make public:

  • Its application forms and connection and operation standards.
  • Its regulated terms and how they apply.
  • Where and when it may curtail generation, and its export-congestion locations.
  • Its fees, which may not exceed the prescribed maximums in Schedule 6.5.
  • The inverter makes and models it approves.
  • Contact details.

Start with these documents. They hold the technical requirements of the local network, such as protection and metering, which Part 6 does not set.

Two routes in Schedule 6.1

Part 1, systems of 10 kW or less, one stage. The Schedule gives the distributor 30 business days to decide, with extensions capped at 20 business days. After approval the generator has 10 business days to give notice of intent, then 30 business days to negotiate.

Part 1A, 10 kW or less in specified circumstances. A simplified one-stage route with inspection and export-congestion provisions.

Part 2, more than 10 kW in total, two stages.

  1. Initial application on the distributor’s form. Within 5 business days the distributor confirms whether it is complete (clause 11).
  2. Information from the distributor within 30 business days of a complete application (clause 12). It covers network capacity, possible breaches of standards, mitigation, costs, outage effects and any further studies, and says who may carry out those studies.
  3. Final application within 12 months of receiving that information, unless the parties agree it is unnecessary (clause 15). It includes the results of any studies assigned to the generator.
  4. Decision from receipt of the final application, with a deadline by size (clause 19): 45 business days under 1 MW, 60 from 1 MW to under 5 MW, and 80 at 5 MW or more.
  5. Notice and negotiation. The generator has 30 business days from the approval notice to say whether it will negotiate (clause 20). The parties then have 30 business days to negotiate a connection contract in good faith (clause 21).
  6. Testing and connection under the distributor’s timeframe (clause 22), on the contract terms or, without a contract, on the regulated terms (clauses 23 and 24).

Competing final applications for the same part of the network that arrive within 20 business days may be assessed against each other (clause 17).

Export limits and inverters

Two recent additions matter for solar and battery projects:

  • Export limits (clause 6.3A). Distributors may not limit nameplate capacity for Part 1 or 1A applications. For Part 1A applications they may set a maximum export threshold, which may not go below 10 kW unless a network study supports a lower figure. From 11 November 2026 the studies must use the export limits assessment methodology.
  • Inverters (clause 6.3B). From 11 September 2026, low-voltage inverters must apply the Australia A settings in AS/NZS 4777.2:2020, with Amendments 1 and 2, subject to network-study exceptions.

The Australian guides on the AS/NZS 4777 inverter standard and its response modes explain the family it belongs to.

Where Part 8 still applies

Part 6 governs the application. Part 8 can still bind the plant itself. Examples are clause 8.23A on reactive capability, for embedded stations of 10 MW or more at the grid supply busbar voltage, and the information duties for embedded stations over 10 MW. The Part 8 guide lists them. For a large project, Transpower may also be involved.

Worked example: the regulated timeline for a 3 MW plant

The figures are the maximum periods in Schedule 6.1 and assume each step uses its full time, with no extensions. A 3 MW plant falls in the 1 MW to under 5 MW band.

StepClauseBusiness days
Completeness check115
Information from the distributor1230
Decision on the final application1960
Notice on negotiating2030
Negotiation2130
Total155

At five business days a week, 155 business days is 31 weeks, before public holidays, extensions, further studies, the generator’s own time to prepare the final application, and testing. Starting the final application early and attaching complete study results is the main way to shorten the real timeline.

Checklist for the engineer

  • Collect the distributor’s forms, standards, curtailment rules and approved inverter list.
  • Decide the route: 10 kW or less, or above.
  • Confirm the Part 6 version date used.
  • Prepare single-line diagram, protection concept and inverter data for the final application.
  • Ask early which further studies the distributor will assign to you.
  • Check export limits and the network study behind any limit.
  • Plan testing and inspection with the distributor.
  • Keep the design ready for your Chartered Professional Engineer (CPEng).

Compare with other markets

The Australian route is described in the embedded generation guide. The UK route is in the G99 compliance process.

From the application to engineering ready for your engineer

A complete final application depends on good engineering: single-line diagram, protection approach, equipment data and the studies the distributor assigns. Tiza does not sign or certify designs in New Zealand. We deliver engineering design ready for your Chartered Professional Engineer (CPEng) to review and sign, and installation is done by electrical workers licensed by the Electrical Workers Registration Board (EWRB). Contact us with the distributor’s requirements and your site data.

Frequently asked questions

What does Part 6 of the Code cover?

It enables distributed generation to connect to a distribution network, or to a consumer installation connected to one, where this is consistent with connection and operation standards. Schedule 6.1 sets the approval process and Schedule 6.2 the regulated terms.

How long does a distributor have to decide an application above 10 kW?

From a final application, 45 business days if the capacity is under 1 MW, 60 business days from 1 MW to under 5 MW and 80 business days at 5 MW or more, under Schedule 6.1 clause 19. Extensions are possible by written notice.

Which inverter settings apply to low-voltage inverters?

From 11 September 2026, clause 6.3B requires the Australia A settings in AS/NZS 4777.2:2020 with Amendments 1 and 2, subject to exceptions supported by a network study. The distributor also publishes the inverter makes and models it approves.