Transpower runs a staged connection process for generation and large load: concept assessment, application, investigation and delivery. Grid-scale generation and storage needing new Transpower assets submit an application form to enter a pipeline, and spare capacity goes to projects on a first ready, first served basis. Technical studies follow Transpower's connection study requirements, and the developer pays the incremental connection cost.
Short answer: the Transpower connection process
The Transpower connection process is a staged route from first idea to energisation, led by Transpower as owner of the transmission grid. For generation and storage, it runs as a concept assessment, an application, an investigation and delivery. Transpower says the route is tailored to each project, and its guidance and forms change, so check its connections pages before you plan dates.
In November 2026, Transpower’s connections pages list the Connection Management Framework process document version 3.0, dated 22 December 2025. The Ireland and New Zealand grid codes guide shows where this process sits among the other rules.
When Transpower is involved
New Zealand has one national grid, with Transpower as owner and as system operator. A project may meet Transpower in three ways:
- Direct connection to a Transpower substation, for grid-scale generation, storage or a large industrial load.
- Embedded generation connected to a distributor, where the distributor processes the application under Part 6. Transpower publishes guidance for these projects, including protection and study guidance for distributed energy resources.
- A shared upgrade, where several projects use the same new assets.
Transpower asks for information on generation over 1 MW, including projects connected to a distribution network. The Part 6 guide covers the distributor side.
The stages
- Concept assessment. Transpower works with you to define the service level you need, from double-circuit designs that stay on after a fault to lower-cost options with less resilience. In constrained locations it assesses options, feasibility, high-level cost, timeframes and risks.
- Application. Grid-scale generation and storage projects that need new Transpower assets submit an application form showing project readiness. The applicant agrees to limited public disclosure of project information and pays an application fee.
- Investigation. Transpower leads the studies and sets milestones that the project must meet.
- Delivery. Transpower builds the connection against agreed milestones.
Spare local capacity is committed to projects on a first ready, first served basis once an application is accepted. The commitment depends on reasonable progress against milestones. Slippage can put a project on hold, delay it while resources are reallocated, or end it. Transpower does not let companies reserve capacity early.
Transpower withdrew its original customer-led connection guideline while it reviews when that approach is allowed. Transpower involvement is always required.
Studies and the documents behind them
The Code makes the asset owner responsible for showing that the asset meets its performance obligations. Transpower publishes the documents that say how.
| Document | Purpose |
|---|---|
| GL-EA-953, Connection Study Requirements | The technical studies that demonstrate an asset can meet its performance obligations |
| GL-SD-1343, Generation Connection Guide | Connection, commissioning, registration and dispatch |
| GL-EA-404, Generation Commissioning Process | Phases and timings of commissioning |
| GL-EA-1311, Modelling Requirements for Inverter-based Resources | Models for wind, solar and battery assets |
| Generic investigation scopes | Scopes for high-voltage bus, supply bus and embedded generation connections |
| Grid Protection Assessments for Distributed Energy Resources, version 1 | Protection checks for distributed energy resources, dated 13 February 2026 |
The Code side is in Part 8 of the Electricity Industry Participation Code. Since 1 July 2026, the connected asset commissioning, testing and information standard sets the deliverables and timeframes. The Part 8 guide explains the subparts.
What the studies usually ask of your design data
An investigation needs the same building blocks in every country:
- Single-line diagram with transformer, cable and inverter data.
- A steady-state model for load flow and reactive capability.
- Short-circuit data, because the plant adds fault current.
- Dynamic models for the plant controller and the inverters.
- The protection approach at the point of connection.
The Australian model guidelines and the UK connection offer guide show how other markets use the same inputs.
Worked example: fault current added by a solar plant
The numbers are illustrative, not a Transpower figure. A 50 MW solar plant connects at 110 kV. Assume the plant can supply 1.1 times its rated current during a fault.
- Rated current: I = 50 MW ÷ (√3 × 110 kV) = 0.262 kA.
- Fault contribution: 1.1 × 0.262 = 0.289 kA, about 55 MVA of short-circuit contribution at 110 kV.
A grid operator compares such figures with the breaker ratings at the connection point. Inverter plants add far less fault current than synchronous machines of the same size, but the extra 0.29 kA still enters the study. Replace the 1.1 factor with the manufacturer’s data when you have it.
Checklist for the engineer
- Read the current Transpower connection pages and note the process document version.
- Decide whether the project is a direct connection or embedded.
- Prepare the readiness evidence the application form asks for.
- Collect equipment data and plan the models before the investigation begins.
- Map the connection study requirements to your own study plan.
- Track the milestones, because progress holds the capacity.
- Keep the design package ready for your Chartered Professional Engineer (CPEng) to review.
Reading the offer and managing the timeline
A Transpower investigation produces a scope, a cost and a set of milestones. Read them as a plan, not as a quote. Check which studies Transpower will run and which the developer must supply, who owns each model, and what happens to the capacity if a milestone slips. Ask early how the project interacts with other applications at the same location, because Transpower tells applicants when a competing request arrives.
Keep a register of the data you have supplied, with version and date, so that any later question about the studies can be traced back to the inputs. This also makes the later handover to commissioning easier, because the asset capability statement and the models must match the built plant.
Compare with other markets
Other systems reach the same goal by different routes. See the UK battery and G99 connection process, the comparison of study types by market and the Australian embedded generation guide.
From the process to studies ready for your engineer
The investigation is only as good as the data behind it. We carry out power-system studies: load flow, short-circuit and reactive capability checks, with protection input data, set out for review. Tiza does not sign or certify studies in New Zealand. We deliver studies ready for your Chartered Professional Engineer (CPEng) to review and sign. Contact us with the site data and the Transpower documents you hold.
Frequently asked questions
What are the stages of the Transpower connection process?
Transpower describes a concept assessment, an application for generation and storage projects, an investigation led by Transpower, and delivery against agreed milestones. The route is tailored to each project, so confirm the current stages with Transpower.
Who pays for a new Transpower connection?
Transpower states that the developer covers the incremental costs of the connection. It publishes indicative options and cost ranges for typical generation and load connections, but your project cost comes from the investigation.
Does a generator connected to a local network still deal with Transpower?
Often yes. Transpower asks for information on generation over 1 MW, including projects connected to a distribution network, and publishes protection and study guidance for distributed energy resources. Check its page on generation connecting to a distribution network.