The generating system model guidelines that the National Electricity Rules asked AEMO to write are now published as the Power System Model Guidelines, with a Power System Design Data Sheet and a Power System Setting Data Sheet. Version 3.0 followed the Package 1 access standards rule in 2025. A generator of 30 MW or more submits models, source code, parameters and a releasable user guide at the R1 stage, and updates them with measured data at the R2 stage after commissioning.
A new generator in the National Electricity Market (NEM) must give the Australian Energy Market Operator (AEMO) and the network service provider (NSP) models that behave like the real plant. The rules for those models live in the Power System Model Guidelines, which the National Electricity Rules (NER) first called the Generating System Model Guidelines. The data goes in two stages, R1 before connection and R2 after commissioning, and it is tuned against network inputs from the NSP. The wider framework is in the Australian electrical codes and grid connection guide.
Short answer
The National Electricity Amendment (Generating System Model Guidelines) Rule 2017 required AEMO to publish guidelines on the models and data a generating system must provide. AEMO publishes them under clause S5.5.7 of the NER as the Power System Model Guidelines. Two data sheets go with them: the Power System Design Data Sheet and the Power System Setting Data Sheet.
Version 2.0 took effect on 14 July 2023. Version 3.0, with the 2025 data sheets, followed the Improving the NEM access standards – Package 1 rule, which took effect on 21 August 2025. Version 3.0 is the one AEMO’s modelling requirements page names for new model packages.
What the generator submits
Clause S5.2.4 of the NER applies to a production system with a combined nameplate rating of 30 MW or more. It also applies to a synchronous condenser system of 30 MVA or more. The Schedule 5.2 participant provides:
- information on the protection systems and the control systems of the plant;
- functional block diagrams of every function between the feedback signals and the plant output;
- every parameter of each block: settings, gains, time constants, delays, deadbands and limits;
- the characteristics of non-linear elements;
- encrypted models in the software products AEMO nominates in the guidelines;
- the model source code, unencrypted, where the guidelines require it, in a form that can be converted for other nominated software;
- any other information in the guidelines and data sheets;
- a releasable user guide, which records the plant and its models in the form AEMO specifies.
AEMO’s Access Standard Assessment Guide of January 2019 summarises the minimum set. It lists site-specific models for positive-sequence studies and for electromagnetic transient (EMT) studies. It also lists a model acceptance test report, a complete parameter list, a releasable user guide and a benchmarking report that compares the two model types. It adds that AEMO mainly uses PSS®E for positive-sequence studies and PSCAD™/EMTDC™ for EMT studies. The next guide in the series covers those tools: PSS/E and PSCAD requirements for inverter-based resources.
R1 and R2
Schedule 5.5 of the NER separates the data into two stages.
- R1 is the data supplied before connection, starting with the connection application.
- R2 is the data updated after commissioning, once measurements from the real plant have validated the model. Clause S5.2.4 requires the update within three months after the commissioning tests are completed. It is also required when the generator learns that the information is out of date, or when AEMO or the NSP ask for it.
The commissioning tests are planned to produce the measurements that R2 needs, as explained in GPS compliance testing and hold points.
What the NSP provides
Control systems depend on the strength of the network they connect to. For that reason, clause S5.2.4 lists what the NSP must give the applicant on request:
- the highest and lowest single-phase and three-phase fault levels at the connection point, and the X/R ratio, with the plant not connected;
- the mid-point voltage for the reactive power requirement;
- the highest and typical system impedances at the connection point;
- the clearing times of the existing protection;
- the expected limits of voltage fluctuation, harmonic voltage distortion and voltage unbalance.
The same clause requires the control system tuning to be consistent with the range of fault levels and system impedances the NSP specifies. The releasable user guide records the levels used for tuning, including the X/R ratio seen from the connection point.
Worked example: the network equivalent
These numbers are illustrative. A 100 MW plant connects at 132 kV. The NSP gives a minimum three-phase fault level of 600 MVA with X/R = 8, and a maximum of 1,800 MVA with X/R = 12. On a 100 MVA base, the base impedance is 132² ÷ 100 = 174.24 ohm.
- Short-circuit ratio: 600 ÷ 100 = 6.0 at the minimum and 1,800 ÷ 100 = 18.0 at the maximum.
- Minimum case, impedance: Z = 132² ÷ 600 = 29.04 ohm, or 0.1667 per unit.
- Minimum case, parts: R = 29.04 ÷ √(1 + 8²) = 3.60 ohm and X = 8 × 3.60 = 28.82 ohm. In per unit that is 0.0207 + j0.1654.
- Maximum case: Z = 132² ÷ 1,800 = 9.68 ohm. With X/R = 12, R = 0.804 ohm and X = 9.647 ohm, or 0.0046 + j0.0554 per unit.
The short-circuit ratio is the fault level divided by the plant rating. The controllers must be tuned and shown stable across both equivalents. A model tuned only for the strong case can oscillate in the weak case. Getting the tuning range from the NSP in writing, and recording it, avoids that argument later.
Figure: the single-machine infinite-bus equivalent used to test the model, with the plant, the connection point and the network equivalent set from the NSP’s fault levels.
Checklist for the engineer
- Confirm the current version of the Power System Model Guidelines and the data sheets before you start.
- Ask the NSP in writing for the fault level range, X/R ratio, impedances and clearing times.
- Obtain models, source code and parameter lists from the equipment manufacturer early.
- Fill in the Design Data Sheet and the Setting Data Sheet consistently with the models.
- Prepare the releasable user guide, including the tuning range and X/R ratio used.
- Plan the R2 update from the commissioning measurements.
- Keep the models and the single-line diagram of the plant aligned with the as-built design.
Who certifies
Engineer registration is a state matter in Australia. In Queensland, professional engineering services must be provided by, or under the direct supervision of, a Registered Professional Engineer of Queensland (RPEQ). Your RPEQ (in Queensland) or chartered engineer reviews and certifies the studies and model documentation. Tiza does not stamp, sign or certify.
Related guides
For model types and their uses, see EMT study models. For the studies that feed the models, see the short-circuit study and harmonics and resonance in solar plants.
How Tiza can help
If your project needs plant models, network equivalents and the study documentation AEMO and the NSP ask for, Tiza prepares power-system studies remotely and in English. Tiza delivers engineering and studies ready for your RPEQ (in Queensland) or chartered engineer to review and certify, and does not stamp, sign or certify itself. Contact us with the plant data and the NSP’s connection requirements.
Frequently asked questions
Are the Generating System Model Guidelines and the Power System Model Guidelines the same thing?
They are the same requirement under a changed name. The National Electricity Amendment (Generating System Model Guidelines) Rule 2017 required AEMO to publish model guidelines. AEMO now publishes them as the Power System Model Guidelines, under clause S5.5.7 of the National Electricity Rules, with two data sheets that go with them.
What is the difference between R1 and R2 data?
R1 is the registered data and model package supplied before connection. R2 is the data validated with measurements from the plant after commissioning. Clause S5.2.4 requires the information for a plant of 30 MW or more at the connection application stage, and an update within three months after the commissioning tests.
What network data does the generator get from the network service provider?
On request, the network service provider provides the highest and lowest single-phase and three-phase fault levels and the X/R ratio at the connection point with the plant not connected, plus system impedances, mid-point voltage and protection clearing times. The generator tunes its control systems against that range.