The Transpower technical code is not a standalone Transpower document. The technical codes sit in Schedule 8.3 of Part 8 of the Electricity Industry Participation Code, written by the Electricity Authority and applied by Transpower as system operator. Technical Code A covers assets, B emergencies and D outage coordination; C was revoked. Detailed testing and information duties moved into a separate commissioning standard in July 2026.
Short answer: what the Transpower technical code is
Many readers look for the “Transpower technical code” and expect one document. There is none under that name. The technical codes are Schedule 8.3 of Part 8 (Common quality) of the Electricity Industry Participation Code 2010, which the Electricity Authority publishes. Transpower, as system operator, applies them to every asset connected to the New Zealand grid. Transpower adds its own guidelines on how to demonstrate compliance, but the binding text is in the Code.
The clauses cited are those of Part 8 as published by the Electricity Authority, with amendments up to 30 October 2026. Check the version date again before each application.
For the wider picture of both countries, see the Ireland and New Zealand grid codes guide.
What Schedule 8.3 contains
Schedule 8.3 groups the technical codes under letters:
- Technical Code A, Assets. The main code for generators, grid owners and connected asset owners.
- Technical Code B, Emergencies. Obligations during emergencies.
- Technical Code C, Operational communications. Revoked in the amendment that took effect on 1 July 2026.
- Technical Code D. Coordination of outages that affect common quality.
Appendices sit under these codes. Appendix B of Technical Code A, on routine testing and automatic under-frequency load shedding, was also revoked in July 2026.
Technical Code A: the part that binds a generator
Technical Code A is built in clauses. The headings below are the ones relevant to a project team.
- Purpose (clause 1). The code supports the system operator’s ability to meet its principal performance obligations.
- General requirements (clause 2). Assets are identified by a system number and operated within their asset capability statement. This clause also covers commissioning assessments and plans, connection studies and modelling information. Several subclauses were revoked or replaced on 1 July 2026.
- Asset information (clause 3). Limits on disclosing another party’s asset information, and secure storage of modelling data.
- Grid and grid interface (clause 4). Coordination of protection across the grid interface, circuit breaker provision, minimum protection standards and synchronisation checks. At 220 kV a.c. and above, main protection is duplicated, with a separate rule for 220 kV busbars.
- Specific requirements for generators (clause 5). Generating unit control, frequency control with its droop and dead band, and voltage control, including for embedded generators.
The text of the clauses should be read in the Code itself, because the figures and the exceptions matter.
Where the technical duties sit in Part 8
The technical codes are only half of the picture. Subpart 2 of Part 8, clauses 8.16 to 8.38, sets the asset owner performance obligations, called AOPOs. The codes give the detail, and the clauses give the obligation. Examples:
- Clause 8.17 and clause 8.19 deal with frequency contribution and generator behaviour in under-frequency events.
- Clause 8.22 sets the voltage ranges the assets must operate in.
- Clause 8.23 requires grid-connected generating stations to export at least 50% and import at least 33% of maximum continuous MW output as reactive power, within the applicable voltage range. The Code measures these figures at the generating unit terminals.
- Clause 8.23A, inserted on 1 July 2026, sets at least 33% export and import, measured at the point of connection, for embedded stations of 10 MW or more. It applies to stations connected at the nominal voltage of the closest busbar where the grid owner supplies the local network, unless agreed otherwise with the distributor.
- Clause 8.25A to 8.25D set fault ride-through. See the guide on Transpower ride-through and IBR requirements.
- Clause 8.21 excludes generating stations under 10 MW from several of these duties, unless the Authority directs otherwise under clause 8.38.
Since 1 July 2026, Subpart 7 (clauses 8.71 to 8.76) adds the connected asset commissioning, testing and information standard. Commissioning deliverables, asset capability statements, connection studies and periodic testing now live in that standard. The Part 8 guide walks through the subparts.
If you cannot comply: dispensations
Clauses 8.29 to 8.37 let an owner that cannot meet an obligation apply to the system operator for an equivalence arrangement or a dispensation. The system operator must approve an equivalence arrangement if the proposed arrangements achieve compliance in its reasonable opinion. A dispensation depends on the system operator still being able to meet its own obligations and on the costs to others being quantifiable. Approvals are specific to one owner and set no precedent.
Worked example: reactive capability at the grid connection
The numbers below are illustrative and use only the Code percentages.
A grid-connected solar plant has a maximum continuous output of 80 MW. Clause 8.23 asks for the capability to export at least 50% and import at least 33% of that output as reactive power.
- Export: Q = 0.50 × 80 = 40 Mvar.
- Import: Q = 0.33 × 80 = 26.4 Mvar.
- Apparent power at full export: S = √(80² + 40²) = √8 000 = 89.4 MVA.
- Apparent power at full import: S = √(80² + 26.4²) = 84.2 MVA.
The larger figure, 89.4 MVA, sets the size. Clause 8.23 measures the reactive power at the generating unit terminals. For an inverter plant, agree with the system operator where those terminals are taken. If they are taken at the grid connection, collector and transformer losses come on top, and the inverters must deliver more than 40 Mvar. The 50% export requirement is about 0.894 power factor, a more demanding duty than the 0.95 often used as a first guess.
Checklist for the engineer
- Record the Part 8 version date you designed against.
- Identify which of clauses 8.17 to 8.25D apply, and check the 10 MW exclusion in clause 8.21.
- Read Technical Code A, clauses 2 to 5, in the current Schedule 8.3.
- Confirm the asset capability statement matches the design data.
- Agree where the reactive capability is measured, and size for the losses up to that point.
- Check the protection at the grid interface against Technical Code A, clause 4.
- Check the commissioning standard under Subpart 7 for deliverables and timing.
- Decide early whether any duty needs an equivalence arrangement or dispensation.
Compare with other grid codes
The same question, “where do the technical rules live”, has a different answer elsewhere. In Australia, generator performance standards are agreed per project. In the United Kingdom, the Grid Code and the G99 process set the structure. In Ireland, the EirGrid Grid Code plays the same role.
From the code to a design ready for your engineer
Connecting to the New Zealand grid needs engineering that a Chartered Professional Engineer (CPEng) reviews and signs. Installation work is done by electrical workers licensed by the Electrical Workers Registration Board (EWRB). Tiza does not sign or certify designs in New Zealand. We deliver engineering design with the reactive capability, protection and equipment data worked out, ready for your CPEng to review and sign. Contact us with your site data and the Code version you are working from.
Frequently asked questions
Is the Transpower technical code a document Transpower writes?
No. The technical codes are Schedule 8.3 of Part 8 of the Electricity Industry Participation Code, issued by the Electricity Authority. Transpower, as system operator, applies them and publishes guidelines that explain how to meet them.
Which technical code applies to a new generator?
Technical Code A, which covers assets. It sets general requirements, grid interface protection and specific requirements for generators such as unit control and voltage control. Clause 8.23 and clause 8.23A of Part 8 add reactive power duties.
Do the technical codes change often?
Yes. Part 8 was amended on 1 July 2026, when Technical Code C was revoked and several Technical Code A subclauses were revoked or replaced, and again in later months. Quote the version date you used in every application.