Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

EirGrid Grid Code Explained for Generator Developers

How the EirGrid Grid Code is set out, which sections bind a wind or solar plant, and the three notifications leading from energisation to final operation.

By Shadai García, CEO and protection engineer at Tiza Group.

Sections of the Grid Code that bind a wind or solar plantGCGeneral ConditionsPCPlanning Code, PC.A8CCConnection ConditionsOCOperating ConditionsSDC1, SDC2Scheduling, DispatchPPM1wind and solar, replaces WFPS1Wind orsolar plant(PPM)PPM1.3.2 removesthe clauses forsynchronousmachinesEON, ION and FON in sequence, CC.15ION: no longer than 24 monthsno FON: derogation GC.9.3, then CRUOperational Date 15 Sep 2027 (illustrative)120 Business Days back: 25 Mar 20277 days back: 8 Sep 2027EONIONFONenergise internalnetworkup to24 monthsno time limitDerogationGC.9.3If rejected and unresolved:CRU, 6 months after25 Mar 2027: settings due (120 Business Days)8 Sep 2027: scheduling and dispatch (7 days)15 Sep 2027: Operational DateNotificationGrid CodePPM1EONIONFON© tizagrp.comSections of the Grid Code that bind a wind or solar plantGCGeneral ConditionsPCPlanning Code, PC.A8CCConnection ConditionsOCOperating ConditionsSDC1, SDC2Scheduling, DispatchPPM1wind and solar, replaces WFPS1Wind orsolar plant(PPM)PPM1.3.2 removesthe clauses forsynchronousmachinesEON, ION and FON in sequence, CC.15ION: no longer than 24 monthsno FON: derogation GC.9.3, then CRUOperational Date 15 Sep 2027 (illustrative)120 Business Days back: 25 Mar 20277 days back: 8 Sep 2027EONIONFONenergise internalnetworkup to24 monthsno time limitDerogationGC.9.3If rejected and unresolved:CRU, 6 months after25 Mar 2027: settings due (120 Business Days)8 Sep 2027: scheduling and dispatch (7 days)15 Sep 2027: Operational DateNotificationGrid CodePPM1EONIONFON© tizagrp.com
Block map of the EirGrid Grid Code sections that bind a wind or solar plant, General Conditions, Planning Code with appendix PC.A8, Connection Conditions, Operating Conditions, Scheduling and Dispatch Codes and PPM1 (which replaces WFPS1), all leading to the plant; and the commissioning chain of Energisation, Interim (up to 24 months) and Final Operational Notification with the GC.9.3 derogation and the CRU referral, with the worked example counting back from an Operational Date of 15 September 2027: settings due 25 March 2027 and dispatch obligations from 8 September 2027. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

The EirGrid Grid Code is the rulebook that the Irish transmission system operator applies to generators and large users. Its Version 18 runs to close to 500 pages in sections: general conditions, planning, connection, operating conditions, scheduling and dispatch, plus a dedicated section for wind and solar plants called PPM1. A developer reads the Planning Code and Connection Conditions first, then PPM1, and proves compliance through the energisation, interim and final operational notifications.

Short answer: what the EirGrid Grid Code is

The EirGrid Grid Code is the technical rulebook that EirGrid, the transmission system operator (TSO) for the Republic of Ireland, applies to generators, demand facilities and interconnectors. The current text is Version 18, issued on 27 October 2026. It is approved by the Commission for Regulation of Utilities (CRU), the energy regulator. For a wind or solar developer it answers three questions. What must the plant be able to do? What data and models must be supplied? How does the plant prove it before it operates commercially? The code covers the Republic of Ireland only; Northern Ireland has a separate system operator and code.

This overview sits inside the wider guide to the Irish and New Zealand grid codes. The sections that follow link to the detailed guides on wind and solar rules, ride-through, frequency response and testing.

How the document is organised

Version 18 is a single PDF of close to 500 pages. Its main parts are:

  • GC, General Conditions. Governance of the code, the Grid Code Review Panel, interpretation and derogations (clause GC.9).
  • PC, Planning Code and appendix. The data and the studies needed for a new connection. Appendix PC.A8 sets the model requirements.
  • CC, Connection Conditions. The technical design and performance standards, protection and power quality, signals, and commissioning (CC.15).
  • OC, Operating Conditions. System services, outage planning, operational testing and monitoring.
  • SDC1 and SDC2, Scheduling and Dispatch Codes.
  • PPM1, Controllable PPM Power Station Grid Code Provisions. The special section for wind and solar plants. Earlier versions of the code called this section WFPS1.
  • SCU1 for synchronous condensers, then the Glossary.

A power park module (PPM) is a plant made of many converter-based generating units that behave as one plant at the connection point. The code was first written around synchronous machines. PPM1 exists because wind and solar plants behave differently, and its scope clause lists the CC and OC clauses that do not apply to them.

How the sections fit for a wind or solar plant

A plant reads the code in layers. The General Conditions, Planning Code and most Connection Conditions apply to every user. Clause PPM1.3.2 then excludes the synchronous-machine clauses that do not suit a PPM and adds the requirements in PPM1. The parts of PPM1 are fault ride-through (PPM1.4), frequency ranges and response (PPM1.5), voltage and reactive power (PPM1.6), and signals, communication and control (PPM1.7).

The Grid Code also uses the EU Requirements for Generators (RfG) as a reference. Generation units that fall under RfG carry extra demarcated requirements in the CC text. The guide on wind and solar requirements goes through PPM1 in detail.

The path to operation: EON, ION and FON

Clause CC.15 sets the commissioning process. A generator completes three notifications in sequence:

  1. Energisation Operational Notification (EON). Issued once the EON checklist is complete, including agreement on protection and control settings at the connection point. It lets you energise the internal network and auxiliaries.
  2. Interim Operational Notification (ION). It lets the plant generate for a limited period agreed with EirGrid, no longer than 24 months.
  3. Final Operational Notification (FON). Issued after the FON checklist is complete. It lets the plant operate without the time limit.

If EirGrid sees a reason not to issue a FON, the generator can seek a derogation under GC.9.3. If the derogation is rejected and the gap is not resolved, either party may refer the matter to the CRU. The limit is six months after the rejection is notified.

Worked example: counting back from the Operational Date

The numbers are illustrative. Clause PPM1.5.3.6 says the TSO specifies the frequency response settings at least 120 Business Days before the scheduled Operational Date, and the plant implements them during commissioning. Clause CC.15.6 says generators are subject to the scheduling and dispatch codes at least 7 days before the Operational Date.

Assume a plant with a scheduled Operational Date of 15 September 2027.

  • Count back 120 working days, Monday to Friday, skipping the four 2027 public holidays in the period (29 March, 3 May, 7 June, 2 August). The settings are due by 25 March 2027.
  • Subtract 7 calendar days: scheduling and dispatch obligations start on 8 September 2027.

Your project plan needs the Grid Code settings request answered well before the 25 March date, because the settings feed your controller programming and your model. The Glossary defines a Business Day as Monday to Friday, excluding public holidays and holidays observed by the TSO. Check those holidays before fixing the dates in a plan.

Where this code differs from its neighbours

In Great Britain, the Grid Code is administered by a different body and uses its own compliance language; see the guide to the GB Grid Code for generation developers and the ECC compliance guide. Australia uses generator performance standards negotiated per plant, explained in the GPS guide. The US approach to inverter-based plants is covered in the IEEE 2800 guide. The ride-through comparison sets the numbers side by side. Do not carry a number from one regime into another; Irish values come only from the EirGrid text and your connection agreement.

Checklist for the engineer

  • Record the Grid Code version, its issue date and the clause numbers used on every submission.
  • Confirm which section binds the plant: PPM1 for wind and solar, with its list of excluded clauses.
  • Request the connection-point conditions: minimum short-circuit capacity and the settings EirGrid will specify.
  • List the data and models due under the Planning Code and PC.A8, with dates.
  • Draft the commissioning programme and the notice periods for tests that need dispatch.
  • Agree the protection and control settings needed for the EON checklist.
  • Check whether any requirement cannot be met, and open a derogation request early through GC.9.
  • Keep the design package ready for your chartered engineer to review and sign.

From the code to a design your engineer can sign

A connection application is judged on the studies, the models and the settings behind it. Tiza prepares power-system studies for generation projects: load flow, short-circuit and reactive capability checks at the connection point, with the assumptions written out so they can be audited. Tiza does not stamp, sign or certify. The studies and the engineering package are delivered ready for your chartered engineer, registered with Engineers Ireland, to review and sign. Contact us with the site data and the EirGrid connection documents.

Frequently asked questions

Which version of the EirGrid Grid Code applies to my project?

Version 18, issued on 27 October 2026, is the current version listed on the EirGrid website. Your connection agreement fixes the obligations that apply to your plant, so quote the version number and the clause numbers in every submission and check the website for modifications approved since the issue date.

Does the EirGrid Grid Code cover every generator in Ireland?

Not equally. The Planning Code (clause PC.3) applies to generators with a registered capacity above 10 MW and to every generator connected to the transmission system. Smaller plants on the ESB Networks distribution network are governed mainly by the Distribution Code and the ESB Networks connection process.

Who approves a change to the Grid Code?

EirGrid runs a Grid Code Review Panel that receives modification proposals. Each approved change is decided by the Commission for Regulation of Utilities (CRU), and the result is a new numbered version of the Grid Code.