EirGrid Frequency Response Requirements for IBR Plants

How the EirGrid Grid Code sets frequency ranges, droop, deadband and response times for wind, solar and storage plants, with a worked droop example in MW.

By Shadai García, CEO and protection engineer at Tiza Group.

Connection pointCTstep-uptransformercollector bussolar unitsVTPlant controllerfrequency responseset-pointstwo curves,mode signalsPowerControlCommunications50 MW plant, droop 4 %, deadband 15 mHz49.5 Hz: 0.5 / 50 = 1 %; 1 / 4 x 50 = 12.5 MW60 % = 7.5 MW in 5 s; all 12.5 MW in 15 s50.5 Hz, 40 MW available: 40 - 12.5 = 27.5curtailed to 30: headroom 10, so +10 MWchange in P (MW)Hz49.05051.012.5-12.5ABCDE49.5 Hz50.5 HzMWs0510157.512.560 % by 5 s100 % by 15 sResponseFrequencyDroop 4 %Set-pointInvertersResponse© tizagrp.comConnection pointCTstep-uptransformercollector bussolar unitsVTPlant controllerfrequency responseset-pointstwo curves,mode signalsPowerControlCommunications50 MW plant, droop 4 %, deadband 15 mHz49.5 Hz: 0.5 / 50 = 1 %; 1 / 4 x 50 = 12.5 MW60 % = 7.5 MW in 5 s; all 12.5 MW in 15 s50.5 Hz, 40 MW available: 40 - 12.5 = 27.5curtailed to 30: headroom 10, so +10 MWchange in P (MW)Hz49.05051.012.5-12.5ABCDE49.5 Hz50.5 HzMWs0510157.512.560 % by 5 s100 % by 15 sResponseFrequencyDroop 4 %Set-pointInvertersResponse© tizagrp.com
Single-line diagram of a solar plant whose controller measures frequency with a voltage transformer and power with a CT at the connection point, receives the two power-frequency curves and the mode signals from EirGrid over a communications link and sends active power set-points to the inverters; and the power-frequency curve of PPM1.5.3 with points A to E, the deadband of 15 mHz and a governor droop of 4 %, with the 50 MW example: 12.5 MW at 49.5 Hz, 60 % (7.5 MW) within 5 seconds and the full 12.5 MW within 15 seconds. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Clause PPM1.5 of the EirGrid Grid Code (Version 18) sets how wind, solar and storage plants, which are inverter-based resources, behave when frequency moves. Plants stay connected through defined frequency bands and a rate of change of 1 Hz per second, run a droop response with a default of 4 %, and deliver 60 % of the extra power within 5 seconds and all of it within 15 seconds. Energy storage plants have their own five-mode response curve.

Short answer: EirGrid frequency response for IBR plants

EirGrid frequency response requirements for wind, solar and storage, which are inverter-based resources (IBR), sit in clause PPM1.5 of the EirGrid Grid Code (Version 18, issued 27 October 2026). The clause has four parts: the frequency ranges a plant must ride through, active power control from EirGrid set-points, the frequency response itself, and ramp rates. A small island system with a high share of wind and solar sees fast frequency movement. The response must therefore be quick, and the plant must not trip on a rate of change of frequency of up to 1 Hz per second.

Read this together with the overview of the EirGrid Grid Code, the wind and solar requirements guide and the ride-through guide. The Irish and New Zealand context is in the parent guide.

Frequency ranges and rate of change

Clause PPM1.5.1 requires a controllable PPM to operate continuously at normal rated output between 49.5 Hz and 50.5 Hz. Table PPM1.5.1(e) lists the minimum times a generation unit stays connected outside that band:

Frequency rangeMinimum time
47.0 to 47.5 Hz20 seconds
47.5 to 49.0 Hz90 minutes
49.0 to 51.0 HzUnlimited
51.0 to 51.5 Hz90 minutes
51.5 to 52.0 Hz60 minutes

The plant must also stay connected for a rate of change of frequency (RoCoF) of up to 1 Hz per second, measured over a rolling 500 ms. During voltage dips the fault ride-through clause takes precedence over this limit. The code states that this is a capability and does not require RoCoF protection or set a setting for anti-islanding or loss-of-mains relays. Those settings are a matter for the connection agreement.

How the response works

Clause PPM1.5.3 builds the response around a power-frequency curve with points A to E for plants other than energy storage. Frequency points F_B and F_C bound the deadband and sit between 49.5 and 50 Hz and between 50 and 50.5 Hz. Outside them the plant changes its active power by a governor droop, with a default of 4 %. Droop is calculated against registered capacity, and the frequency deviation is measured from nominal frequency, not from the deadband edge. EirGrid specifies two curves for each plant at least 120 Business Days before the Operational Date, and the plant must switch between them within one minute of a signal.

Other rules in the clause:

  • In active power control mode the plant always operates in Frequency Sensitive Mode, with a deadband of plus or minus 15 mHz unless EirGrid agrees otherwise.
  • The plant provides at least 60 % of its expected additional response within 5 seconds and 100 % within 15 seconds.
  • Response is delivered by changing the output of all available units in proportion, not by switching units on and off where that can be avoided.
  • No delays beyond those inherent in the design, such as averaging filters, are allowed in the frequency measurement.
  • Limited Frequency Sensitive Mode applies on instruction. In over-frequency it starts at 50.2 Hz and in under-frequency at 49.5 Hz. The plant moves between modes within one minute of the signal.

Energy storage power stations follow a separate five-mode characteristic with settable trigger frequencies, trajectories and maximum responses, and they must respond from any operating point, including zero output.

Ramp rates

Three ramp rates apply, in priority order: the frequency response ramp rate, the active power set-point ramp rate and the resource-following ramp rate. EirGrid specifies the last two as a percentage of registered capacity per minute. For a storage plant the capacity-limited ramp rate sits first. Under PPM1.5.2 the plant starts to implement an active power set-point from EirGrid within 10 seconds of receiving it.

Worked example: droop on a 50 MW plant

The values are illustrative. A solar plant has a registered capacity of 50 MW and a droop of 4 %.

  1. The frequency falls to 49.5 Hz. The deviation from 50 Hz is 0.5 Hz, which is 0.5 ÷ 50 = 1 % of nominal.
  2. The power change is the deviation divided by the droop, applied to registered capacity: (1 % ÷ 4 %) × 50 MW = 12.5 MW.
  3. Timing: at least 60 % of 12.5 MW = 7.5 MW within 5 seconds, and the full 12.5 MW within 15 seconds.
  4. Case A, over-frequency: the plant produces 40 MW available. At 50.5 Hz the reduction is also 12.5 MW, so output falls to 27.5 MW.
  5. Case B, under-frequency: the plant is curtailed to 30 MW while 40 MW is available. The droop asks for 12.5 MW, but only 10 MW of headroom exists, so the response is limited to 10 MW and output rises to 40 MW.

A plant running at its maximum available power cannot raise output in under-frequency. That is a commercial and operating decision about headroom, not a controller fault, and it should be settled with EirGrid before the plant relies on it.

DS3 system services are a separate layer

EirGrid also procures system services such as fast frequency response, primary, secondary and tertiary operating reserve under its DS3 programme (Delivering a Secure, Sustainable Electricity System). These are contracted services with their own market rules, qualification and testing pages on the EirGrid website. They sit on top of the Grid Code capability. Check the current rules for each service before designing a plant to qualify.

How this compares with other regimes

For Great Britain’s limited frequency sensitive mode and ride-through, see the G99 guide. Australia’s frequency control and disturbance rules are in the S5.2.5.11 guide and the S5.2.5.3 guide, and the US approach for inverter plants is in the IEEE 2800 guide.

Checklist for the engineer

  • Confirm the Grid Code version and the frequency table in force.
  • Check that the inverters and the plant controller ride through the frequency bands and 1 Hz per second.
  • Request the two power-frequency curves and the droop and deadband settings from EirGrid.
  • Program the modes: frequency sensitive, limited under-frequency and limited over-frequency.
  • Verify the 60 % in 5 seconds and 100 % in 15 seconds response in the model.
  • Plan the headroom for under-frequency response, in curtailed and unconstrained operation.
  • Check the ramp rates and the 10-second set-point implementation.
  • Keep the design and settings ready for your chartered engineer to review and sign.

From the clause to plant settings your engineer can sign

Frequency response depends on controller settings that have to match the code, the model and the commissioning test. Tiza configures plant controllers and inverters remotely and prepares settings documents with each value traced to its clause. Tiza does not stamp, sign or certify. The settings package is delivered ready for your chartered engineer, registered with Engineers Ireland, to review and sign. Contact us with the plant and controller details.

Frequently asked questions

What default droop does the EirGrid Grid Code use for wind and solar plants?

The default governor droop is 4 %, applied to registered capacity, with a deadband of no more than plus or minus 15 mHz. EirGrid can set a different value within the range the code allows, and the plant must be able to reselect it repeatedly when asked.

How quickly must a plant deliver its frequency response?

Clause PPM1.5.3.3 asks for at least 60 % of the expected additional active power within 5 seconds and 100 % within 15 seconds of the start of the frequency excursion outside the deadband.

Is frequency response in the Grid Code the same as the DS3 system services?

No. The Grid Code sets the technical capability every plant must have. System services under the DS3 programme, such as fast frequency response and operating reserves, are procured separately and have their own qualification and testing.