EirGrid and SONI published the All-Island Grid Forming Strategy in February 2026. It sets three steps: voluntary requirements in the grid codes, technology trials, then mandatory requirements aligned with the European network codes. The EirGrid Grid Code, Version 18, does not yet contain grid forming requirements. The first proposal, MPID349 of 10 June 2026, covers HVDC interconnectors and describes the behaviour expected at the connection point: a voltage source behind an impedance, a response to phase and magnitude jumps, synthetic inertia and self-synchronisation.
Short answer: EirGrid grid forming
EirGrid grid forming is not yet a mandatory Grid Code requirement. EirGrid and SONI, the system operator for Northern Ireland, set the direction in the All-Island Grid Forming Strategy (February 2026). The current EirGrid Grid Code, Version 18 (issue date 27 October 2026), has no grid forming clauses. The first step is voluntary: modification proposal MPID349 (MPID is EirGrid’s modification proposal identifier) adds a non-mandatory grid forming capability for HVDC interconnector converter stations. Mandatory requirements follow later and are tied to the European network codes RfG 2.0 and HVDC 2.0.
For the wider framework see the Ireland and New Zealand grid codes guide. For the Great Britain approach, read the UK grid forming converter guide.
Why Ireland is moving to grid forming
The strategy gives the reason in system terms. All-island renewable generation capacity grows from about 10.2 GW in 2025 to about 18.6 GW in 2030, and the number of synchronous generators online falls. Less synchronous machinery means less inertia, less short-circuit current and less damping. A grid following inverter needs a stiff voltage to synchronise with, so on a weak system it can become part of the problem.
A grid forming converter behaves differently. Within its current limit, it holds an internal voltage phasor for the first fractions of a second and lets the network disturb the current, not the voltage. That is the behaviour a synchronous machine gives naturally.
The three steps in the strategy
- Voluntary requirements for HVDC and power park modules (PPMs) in the EirGrid and SONI grid codes, with test protocols. This is an early framework for new projects and trials, with no immediate obligation.
- Technology trials. An HVDC trial on the Celtic interconnector between Ireland and France, and a PPM trial through the Qualification Trial Process. The strategy expects both to begin in 2026.
- Mandatory requirements in the grid codes, informed by the trials and by system studies, in line with RfG 2.0 and HVDC 2.0.
Four principles run through all three steps. No converter oversizing is specified. The focus is on capability already in the controls. Requirements are performance-based and do not prescribe the control design. Mandatory rules do not apply retrospectively, except after significant modernisation.
How the strategy defines grid forming
There is no single international definition, and the strategy says so. It adopts a performance-based one. After a disturbance, the device must appear at its terminals as a source that injects current, within its limits, in a way that opposes the disturbance. This applies in the sub-transient and transient time frame. The strategy lists eleven performance areas, including voltage source behaviour, response to phase and magnitude jumps, synthetic inertia, weak grid operation and self-synchronisation, oscillation damping, fault current contribution and behaviour at current limits.
What MPID349 asks of an HVDC converter
MPID349 is dated 10 June 2026 and is written against Grid Code Version 16. It touches section PC.A6 (data), clause CC.7.5 and the definitions. Clause CC.7.5.13 applies only to converter stations that declare the capability, and the TSO can ask to enable or disable the grid forming mode remotely. Among its points:
- Thevenin source (CC.7.5.13.8.1). The converter behaves as a controllable voltage source behind an internal impedance, in normal operation and just after a disturbance.
- Effective impedance (CC.7.5.13.8.3). Between 0.2 and 0.5 per unit, a range the proposal still shows in brackets, with an X/R ratio of at least 10.
- Synchronising power and voltage stiffness (CC.7.5.13.8.4 and .8.5). The immediate response to a phase angle jump or a voltage magnitude jump is observed within 5 ms to 20 ms.
- Disturbances (CC.7.5.13.6). A phase angle jump of plus or minus 10 degrees, a magnitude jump of plus or minus 0.1 per unit, and a rate of change of frequency of 1 Hz/s for 1 s. All are within the converter’s current and energy limits.
- Self-synchronisation (CC.7.5.13.8.6), and synthetic inertia (CC.7.5.13.9) with an equivalent inertia constant of at least 3 MW/MVA, or a lower value the owner agrees with the TSO.
- Current limits (CC.7.5.13.10). If the response reaches the converter’s current limit, current limitation is allowed, but the station must stay stable and must not switch control mode.
These figures apply to HVDC converter stations in the proposal. They are not requirements for a solar or storage plant today. A developer can still use them as a reference when specifying inverters that may be asked for grid forming later.
Worked example: phase jump and current limit
The numbers below are illustrative. On its own base, a converter has an effective impedance X = 0.3 per unit and a current limit of 1.1 per unit. Its internal voltage E and the grid voltage V are both 1.0 per unit.
- Before the disturbance the angle between E and V is 10 degrees. Active power P = E × V × sin(δ) ÷ X = sin 10° ÷ 0.3 = 0.1736 ÷ 0.3 = 0.579 per unit.
- The grid voltage jumps by 10 degrees so the angle becomes 20 degrees. The unclipped power would be sin 20° ÷ 0.3 = 0.3420 ÷ 0.3 = 1.140 per unit, a change of 0.561 per unit.
- The converter current is the phasor difference divided by X: I = 2 × sin(δ ÷ 2) ÷ X. At 10 degrees, I = 2 × 0.0872 ÷ 0.3 = 0.581 per unit. At 20 degrees, I = 2 × 0.1736 ÷ 0.3 = 1.158 per unit.
- 1.158 exceeds the 1.1 per unit limit, so the response is cut at the limit. MPID349 accepts this, provided the station stays stable and keeps its control mode.
The lesson is that the same impedance that gives a strong response also drives current into the limit. Headroom, not control code alone, decides how much of a phase jump a plant can absorb. The strategy states that no oversizing is required, so the limit shapes the response.
Checklist for the engineer
- Quote the Grid Code version and issue date used (Version 18, 27 October 2026, at the time of writing) and check the EirGrid modifications page for the status of MPID349.
- Ask the inverter or converter supplier whether a grid forming mode exists, and which of the strategy’s eleven performance areas it demonstrates with test evidence.
- Collect the data MPID349 lists for HVDC: effective impedance and X/R, equivalent inertia constant, damping ratio and the frequency-dependent impedance from 5 Hz to 2500 Hz.
- Run a phase jump and a magnitude jump on the plant model and record the current against the converter limit.
- Check small-signal interaction at weak grid points with an electromagnetic transient model.
- Keep the design basis, model and studies in one package for the engineer of record.
From the strategy to a design your engineer can sign
A grid forming capability has to be specified, modelled and shown in studies before it reaches a connection offer. We prepare the engineering design and power-system studies behind that file: short-circuit levels, weak grid cases, protection coordination and equipment data. Tiza does not sign, stamp or certify designs in Ireland. We deliver engineering and studies ready for your Chartered Engineer (Engineers Ireland) to review and sign. Work on site is left to a contractor registered with the Register of Electrical Contractors of Ireland (RECI). Contact us with the project data and the operator’s requirements.
Related guides: Australia, AEMO model requirements for inverter plants, inverter contribution to short circuit, the Ireland connection process and ESB Networks protection requirements for generators.
Frequently asked questions
Does the EirGrid Grid Code require grid forming today?
No. Version 18 of the Grid Code, issued on 27 October 2026, has no grid forming section. The All-Island Grid Forming Strategy of February 2026 says voluntary requirements come first, then trials, then mandatory requirements aligned with the European network codes RfG 2.0 and HVDC 2.0.
What does MPID349 propose?
A non-mandatory grid forming capability for HVDC interconnector converter stations, submitted by EirGrid on 10 June 2026 against Grid Code Version 16. It adds data requirements to PC.A6 and a new clause CC.7.5.13 that defines the expected behaviour at the Grid Connection Point.
Will mandatory grid forming apply to existing plants?
The strategy says mandatory requirements will not apply retrospectively to existing connections unless they undergo significant modernisation. It also says the grid codes will not require converter oversizing or extra energy storage.