A grid-forming converter behaves as a voltage source that sets its own voltage and phase, instead of following the grid like a standard inverter. The GB Grid Code added a minimum specification for this capability through modification GC0137, implemented in February 2022. It is a technical specification and not a mandatory requirement. Definitions, technical conditions and compliance evidence sit in separate parts of the code.
Short answer: what grid-forming means in the GB Grid Code
A grid-forming converter acts as a voltage source behind an impedance. It sets its own voltage and phase, where a standard grid-following inverter reads the grid and injects current. The GB Grid Code added a minimum specification for GB Grid Forming (GBGF) capability through modification GC0137. Ofgem published its decision on 31 January 2022, and the specification was implemented on 14 February 2022. It is a technical specification for plant that offers the capability and not a mandatory requirement for all plant. It defines the types of response, not a minimum size. The current text is Grid Code Issue 6, Revision 46, dated 8 October 2026. For the wider code see the Grid Code overview.
Why it matters to a developer
A system with more converters and fewer rotating machines has less inertia and a weaker voltage reference. A converter that forms its own voltage helps hold the frequency and the voltage during disturbances, in the first moments before any control loop reacts. NESO has published guidance notes that explain the specification and describe the grid-forming capability. Treat them as interim guidance that the code may update, and confirm which issue applies to your project.
Where the requirements sit in the code
The GC0137 decision spreads the specification across three parts of the code:
| Part of the Grid Code | What GC0137 puts there |
|---|---|
| Glossary and Definitions | Definitions of the grid-forming capability and its terms |
| European Connection Conditions (ECC) | The minimum technical requirements, including monitoring |
| European Compliance Processes (ECP) | The simulation and testing a plant must pass to show compliance |
The plants it covers are converter-based ones such as power park modules and high-voltage direct current (HVDC) converter stations. The specification states that a grid-forming plant must also comply with the rest of the code, so the ECC, ECP and the operating codes still apply to it.
The core model is a synchronous internal voltage source behind an impedance. The code defines the response the plant must give to voltage and phase disturbances in terms of that model. NESO’s definitions also include terms such as damping and active phase jump power, which the design has to address in simulation. A follow-up modification has been proposed to focus the wording on the converter’s output performance instead of one impedance method. Check the Grid Code modification tracker for its status.
Worked example: response to a phase jump
All values are illustrative and assumed. The phase jump size is an assumption, not a figure from the code.
Model: the converter behaves as a voltage source E behind a total reactance X to the grid voltage V. Work in per unit on the converter base.
- Internal voltage E = 1.00 per unit. Grid voltage V = 1.00 per unit.
- Converter virtual reactance 0.20, transformer 0.10, grid equivalent 0.15 per unit. Total X = 0.20 + 0.10 + 0.15 = 0.45 per unit.
The active power exchanged between two voltage sources is P = (E × V ÷ X) × sin δ, where δ is the angle between them.
- Before the disturbance δ = 0, so P = 0 for this case.
- The grid suffers a 10 degree phase jump. sin 10° = 0.1736.
- P = (1.00 × 1.00 ÷ 0.45) × 0.1736 = 0.386 per unit.
- On a 40 MW converter, that is 0.386 × 40 = 15.4 MW delivered or absorbed within the first moments, with no measurement delay, because the angle itself drives the power.
- Check the current. The converter voltage is near 1 per unit, so current ≈ 2 × sin(5°) ÷ 0.45 = 0.39 per unit, well below an assumed limit of 1.1 per unit. The converter can follow this response without hitting its limit.
A grid-following inverter would see the same jump through its phase-lock loop and respond later. The grid-forming plant responds at once. Now take a 40 degree jump. Then sin 40° = 0.643 and P = 1.43 per unit. That exceeds the assumed current limit of 1.1 per unit, so the converter would need to limit its output. The design must show how it behaves there. This is the case the simulations in the compliance process exercise.
Design issues to settle early
- Current limit. A converter cannot supply much more than its rated current, so its response to a large disturbance is capped. Show the cap and what the controls do next.
- Energy source. The response needs energy behind it. A battery system can supply it. A solar plant needs a headroom or storage strategy. See battery storage system parts and functions.
- Protection. Interface and plant protection must not trip the converter inside its required response. See interface protection for generation.
- Models. The compliance process asks for models that reproduce the converter’s behaviour, including electromagnetic transient models where required.
For how inverters behave in a fault, see inverter fault current in solar plants. For inertia in general see inertia constant H and synchronous generator models.
Checklist for the engineer
- Record the Grid Code issue and revision, and read the grid-forming parts of the ECC and ECP in that revision.
- Decide whether the project offers the capability or the connection offer asks for it.
- Model the converter as a voltage source behind an impedance and check phase-jump and voltage responses.
- Show the current-limit behaviour for large disturbances.
- Identify the energy source that supports the response.
- Review protection settings against the required response.
- Check the modification tracker for follow-up changes to the specification.
- Route the design to your chartered engineer for review before submission.
Related guides
The reactive side of the same plant is in reactive capability for power park modules. The UK series starts at the UK codes overview.
From the specification to a design your chartered engineer can sign off
We prepare the engineering design and the power-system studies behind a grid-forming submission: converter model inputs, the response studies, the protection concept and the evidence list. The package is ready for your chartered engineer to review and sign off before it goes to the network operator. Tiza does not sign or certify designs in the UK. Contact us with the site data and the connection offer.
Frequently asked questions
What is GC0137?
It is the Grid Code modification that set the minimum specification for grid-forming capability in GB. Ofgem published its decision on 31 January 2022, and the change was implemented on 14 February 2022.
Is grid-forming capability mandatory in GB?
The specification introduced by GC0137 is not a mandatory requirement for every plant. It defines what a plant must meet when it offers grid-forming capability. Check the connection offer and the current Grid Code for any obligation that applies to your project.
What is the difference between a grid-forming and a grid-following inverter?
A grid-following inverter measures the grid voltage and injects current to match it. A grid-forming inverter acts as a voltage source behind an impedance, so it holds its own voltage and phase and shares the response to a disturbance with the grid.