Grid Codes and Connection in Ireland and New Zealand

Grid codes in Ireland (EirGrid, ESB Networks) and New Zealand (Electricity Code Parts 6 and 8, Transpower), with a reactive power example for a plant.

By Shadai García, CEO and protection engineer at Tiza Group.

=~Plant LVTransformerBreakerWhMeterNetworkInterfaceprotectionSystemoperatorCollectorP, QSite wiring codeGrid code at the connection pointPowerProtectionCommunicationsIrelandNew ZealandRegulatorapproves the codesElectricity AuthorityCode, Parts 6 and 8EirGridGrid CodeTranspowersystem operator, studiesESB NetworksDistribution CodeDistributorCode, Part 6Project siteI.S. 10101Project siteAS/NZS 3000, NZECP 34/3520 MW: 6.57 Mvar at pf 0.95, 9.69 at pf 0.90DocumentsGrid CodeDistribution CodePart 6Part 8Capability© tizagrp.com=~Plant LVTransformerBreakerWhMeterNetworkInterfaceprotectionSystemoperatorCollectorP, QSite wiring codeGrid code at the connection pointPowerProtectionCommunicationsIrelandNew ZealandRegulatorapproves the codesElectricity AuthorityCode, Parts 6 and 8EirGridGrid CodeTranspowersystem operator, studiesESB NetworksDistribution CodeDistributorCode, Part 6Project siteI.S. 10101Project siteAS/NZS 3000, NZECP 34/3520 MW: 6.57 Mvar at pf 0.95, 9.69 at pf 0.90DocumentsGrid CodeDistribution CodePart 6Part 8Capability© tizagrp.com
Ireland and New Zealand: regulator, system operator, distributor and project in each country, with the code that governs each link and a plant exporting P and Q at the point of connection. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Ireland and New Zealand are small island systems with their own grid codes. In Ireland the transmission operator EirGrid publishes the Grid Code and ESB Networks publishes the Distribution Code, both approved by the regulator. In New Zealand the Electricity Authority sets the rules in the Electricity Industry Participation Code, whose Part 6 covers distributed generation and Part 8 the technical requirements, and Transpower runs the grid.

Short answer: grid codes in Ireland and New Zealand

Grid codes in Ireland are published by the system operators and approved by the regulator. The EirGrid Grid Code sets technical requirements for generators and large users on the transmission system and for larger plants on the distribution system. The ESB Networks Distribution Code covers the distribution network. In New Zealand, the rules sit in the Electricity Industry Participation Code 2010, issued by the Electricity Authority. Part 6 covers connecting distributed generation, and Part 8 covers technical and quality requirements for the grid. Transpower is both owner of the high-voltage grid and the system operator.

Both are small island power systems. Ireland runs a high share of wind, and New Zealand relies mainly on hydro and geothermal, with wind and solar growing. Low inertia on a small system is why frequency response, fault ride-through and inverter behaviour get close attention in both codes.

The editions in force

  • EirGrid Grid Code: modifications are proposed and approved through a defined process, and each approval produces a new version. Quote the version number in every application.
  • ESB Networks Distribution Code: Version 8.0, approved by the Commission for Regulation of Utilities (CRU) in February 2023. Check the ESB Networks page for a later version before you apply.
  • Electricity Industry Participation Code 2010: a living document, republished with each amendment. Quote the version date of Part 6 or Part 8 that you used.

Ireland: how the documents fit

Two operators, two codes, one connection path.

  1. Grid Code (EirGrid). It sets the technical conditions for connection: reactive power, voltage control, frequency response, fault ride-through, protection and the testing needed to prove them.
  2. Distribution Code (ESB Networks). It applies to plants connected to the distribution network, including its protection and loss-of-mains requirements.
  3. Connection process. EirGrid and ESB Networks assess the application and issue an offer. The project then has to demonstrate compliance, including model validation and tests.
  4. Wiring on site. Installation work follows I.S. 10101, the Irish national rules for electrical installations.

EU network codes, such as the Requirements for Generators (RfG), also reach Ireland through the Grid Code.

New Zealand: how the documents fit

  1. Electricity Industry Participation Code, Part 6. It sets how distributed generation connects to a distribution network: the application process, timelines and information a distributor must provide.
  2. Electricity Industry Participation Code, Part 8. It covers the common quality rules, including the system operator’s obligations and the technical codes in its schedules.
  3. Transpower. It runs studies and connection agreements for the transmission grid.
  4. Installation wiring. The installation standard is AS/NZS 3000:2018 with its amendments.
  5. Safe distances and earthing. NZECP 34:2001 covers safe distances from overhead lines, and NZECP 35:1993 covers power systems earthing. Both are electrical codes of practice cited by the Electricity (Safety) Regulations 2010.

Inverters connected through the low-voltage network in New Zealand are also covered by AS/NZS 4777, the same family used in Australia. The cross-country guide on IEEE 1547 versus G99 versus AS/NZS 4777 compares it with the other regimes.

What the two countries share, and where they differ

Both countries have small power systems, so a loss of a large generator or a fault on a key line moves frequency and voltage quickly. Both codes therefore pay close attention to how generators and inverter-based plants behave during disturbances: how long they stay connected, how fast they support voltage, and how they respond to frequency changes.

They differ in structure. In Ireland, the two system operators write the technical requirements in their own codes, and the regulator approves them. A change therefore goes through a public modification process run by EirGrid or ESB Networks. In New Zealand, the Electricity Authority writes the rules in the Code itself and Transpower applies them as system operator. Each distributor adds its own connection requirements for the local network.

A designer working in one country should not assume the other’s terms. A plant category, a test or a study named in one country may have a different name, or no equivalent, in the other.

Worked example: reactive power at the connection point

Grid codes in both countries set a reactive-power capability for generators, expressed as a power factor range or as a share of rated active power. The exact figures belong to the code and to your connection offer. The numbers below are illustrative and only show the arithmetic.

A plant has a registered capacity of 20 MW at the connection point. Assume a requirement of 0.95 power factor, leading or lagging, at full active power. Then:

  • Apparent power S = P ÷ pf = 20 ÷ 0.95 = 21.05 MVA.
  • Reactive power Q = P × tan(arccos 0.95) = 20 × 0.3287 = 6.57 Mvar.

If the requirement were 0.90 instead, Q = 20 × tan(arccos 0.90) = 20 × 0.4843 = 9.69 Mvar, and S = 20 ÷ 0.90 = 22.22 MVA. The reactive capability needed at the connection point rises by about 47% for the same active power. The inverters, the transformer and the collector cables must carry that apparent power, and the losses between the inverter terminals and the connection point reduce what reaches it. That is why capability is checked at the point of connection, not at the inverter.

Checklist for the engineer

  • Identify the operator: EirGrid or ESB Networks in Ireland; Transpower or the local distributor in New Zealand.
  • Write the code version or version date used on the application.
  • Calculate the registered capacity and the required reactive capability at the connection point.
  • List the compliance tests and the model validation the operator will require.
  • Check frequency and voltage ride-through settings against the code.
  • Confirm that the on-site installation standard (I.S. 10101 or AS/NZS 3000) is identified in the design basis.
  • In New Zealand, check safe distances to overhead lines under NZECP 34 for construction and maintenance.
  • Keep the design package ready for the engineer of record or chartered engineer to review and sign off.

The Ireland and New Zealand series follows the same layers: the EirGrid Grid Code explained, wind and solar requirements in Ireland, the grid connection process of EirGrid and ESB Networks, ESB Networks protection requirements, the New Zealand technical codes, New Zealand distributed generation under Part 6 and New Zealand earthing under NZECP 35.

Background: frequency variation and DC component in the grid, ROCOF 81R, solar panels and power factor and capacitive reactive power.

From the codes to a design your engineer can sign off

An application to EirGrid, ESB Networks or Transpower is judged on its models, studies and settings. We prepare the power-system studies and the engineering design behind them: load flow and short-circuit inputs, reactive capability checks, protection and settings approach, and equipment data. Tiza does not stamp, sign or certify; we deliver engineering ready for your engineer of record or chartered engineer to review and sign off before you submit it. Contact us with the site data and the operator’s requirements.

Frequently asked questions

Who writes the grid code in Ireland?

EirGrid, as transmission system operator, publishes the Grid Code, and ESB Networks, as distribution system operator, publishes the Distribution Code. Changes in both are approved by the Commission for Regulation of Utilities (CRU).

Which rules cover connecting small generation in New Zealand?

Part 6 of the Electricity Industry Participation Code sets the process for connecting distributed generation to a distribution network, and each distributor adds its own technical requirements for the installation.

Is wiring covered by the same documents as grid connection?

No. Wiring inside the site follows the installation standard: I.S. 10101 in Ireland, and AS/NZS 3000 with the New Zealand electrical codes of practice in New Zealand. Grid connection follows the grid codes and the network operator's offer.