EirGrid Fault Ride Through for Wind and Solar Plants

EirGrid fault ride through for wind and solar farms under clause PPM1.4: voltage dips, active power recovery, reactive current and a worked timing example.

By Shadai García, CEO and protection engineer at Tiza Group.

Connection pointCTgrid-connectedtransformercollector bussolar unitsVTPlant controlleractive power firstset-pointsvoltage dip at the HV terminalsreactive currentthen power backPowerControlPPM1.4.1: marks of the voltage-time figurerecovery target 0.90 x min(40, 36) = 32.4 MWcase A: cleared in 120 ms, within 140 ms90 % at 190 ms, plus 500 ms: 690 mscase B: cleared in 400 ms, 1 s allowance90 % at 450 ms, plus 1 s: 1450 msreactive range 36 x 0.3287 = 11.83 MvarU (% of nominal)90151506253000 msmarks only, envelope not redrawnillustrative timeline, ms after fault inceptionAfault 120 ms190 ms: U 90 %690 ms: 32.4 MWBfault 400 ms450 ms: U 90 %1450 ms: 32.4 MWRide-throughHV voltageDipActive power firstReactive currentRecovery© tizagrp.comConnection pointCTgrid-connectedtransformercollector bussolar unitsVTPlant controlleractive power firstset-pointsvoltage dip at the HV terminalsreactive currentthen power backPowerControlPPM1.4.1: marks of the voltage-time figurerecovery target 0.90 x min(40, 36) = 32.4 MWcase A: cleared in 120 ms, within 140 ms90 % at 190 ms, plus 500 ms: 690 mscase B: cleared in 400 ms, 1 s allowance90 % at 450 ms, plus 1 s: 1450 msreactive range 36 x 0.3287 = 11.83 MvarU (% of nominal)90151506253000 msmarks only, envelope not redrawnillustrative timeline, ms after fault inceptionAfault 120 ms190 ms: U 90 %690 ms: 32.4 MWBfault 400 ms450 ms: U 90 %1450 ms: 32.4 MWRide-throughHV voltageDipActive power firstReactive currentRecovery© tizagrp.com
Single-line diagram of a solar plant during a voltage dip at the high-voltage terminals of the grid-connected transformer: CT and voltage transformer feeding the plant controller, which gives priority to active power and sends reactive current set-points to the inverters; with the marks of the PPM1.4.1 voltage-time figure (15 % and 90 % of nominal, 150, 625 and 3000 ms) and the worked example timeline of a 36 MW set-point with 40 MW available: recovery target 32.4 MW, 690 ms after inception for a fault cleared in 120 ms and 1450 ms for a fault cleared in 400 ms. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Clause PPM1.4 of the EirGrid Grid Code (Version 18) requires a wind or solar plant to stay connected and stable through voltage dips, give priority to active power, inject reactive current at least in proportion to the dip, and recover at least 90 % of available power within 500 ms of voltage returning to 90 % when the fault clears within 140 ms. EirGrid specifies the pre-fault and post-fault conditions, including minimum short-circuit capacity, for each site.

Short answer: EirGrid fault ride through for wind and solar

EirGrid fault ride through for wind and solar plants is set in clause PPM1.4 of the EirGrid Grid Code (Version 18, issued 27 October 2026). A plant must stay connected and stable during voltage dips on any or all phases, as long as the voltage at the high-voltage terminals of the grid-connected transformer stays above the envelope in the code figure. During the dip it must give priority to active power, inject reactive current, and then recover active power quickly after the fault clears. Reactive power capability in steady state is a related but separate requirement in PPM1.6.

The general map is in the EirGrid Grid Code guide. The steady-state reactive rules are in the wind and solar requirements guide. The context for both countries is in the Ireland and New Zealand overview.

What the clause asks, in plain terms

Clause PPM1.4.1 draws a voltage-against-time envelope for the high-voltage terminals of the grid-connected transformer. The figure marks voltage levels of 15 % and 90 % of nominal and the time points 150 ms, 625 ms and 3000 ms. Read the exact envelope from the code figure in the version named in your connection agreement; do not rebuild it from memory.

Clause PPM1.4.2 adds the functions that go with ride through:

  • During the dip. Provide active power in proportion to the retained voltage and provide reactive current to the transmission system.
  • After the fault. Recover at least 90 % of the lesser of maximum available active power and the active power set-point, as quickly as the technology allows. The deadline is 500 ms after voltage recovers to 90 % of nominal for faults cleared within 140 ms, and 1 second for longer faults.
  • Priority. Active power takes priority during and after faults. The reactive current aims to restore voltage and should be at least proportional to the dip, within the plant rating. Its rise time is no greater than 100 ms and its settling time no greater than 300 ms.
  • Any control mode. The transient reactive response is required whatever reactive control mode was active before the dip.
  • Return to the previous mode. The plant reverts to its pre-fault reactive control mode and set-point within 500 ms of the voltage returning to its normal range.
  • Source of the reactive current. It can come from the individual units, from additional dynamic devices such as statcoms or static var compensators on site, or from both.

EirGrid may ask a plant to reduce its dynamic reactive response if it causes over-voltages on the transmission system. The plant then agrees the change with EirGrid and confirms its implementation within 120 days of the formal request.

The conditions behind the test

EirGrid does not leave the study conditions open. Under PPM1.4.2(f) it specifies, case by case and on request, the pre-fault and post-fault conditions for the capability. They include the minimum short-circuit capacity at the connection point in MVA before and after the fault, and the pre-fault active power, reactive power and voltage at the connection point. EirGrid also makes the specified conditions public. A weak connection point gives a very different converter response from a strong one, so the study result is only as valid as these inputs. Ask for them early, as they feed both the plant model and the controller tuning.

The EirGrid fault ride through study template and assessment documents on the EirGrid site structure how these studies are presented. Check the current template version on the EirGrid website before preparing a study.

Worked example: when must the power be back?

The values are illustrative. A solar plant has an active power set-point of 36 MW and an available power of 40 MW.

  1. The recovery target is 90 % of the lesser of the two: 0.90 × min(40, 36) = 0.90 × 36 = 32.4 MW.
  2. Case A: a fault is cleared in 120 ms, which is within 140 ms. The terminal voltage returns to 90 % of nominal at 190 ms after fault inception. The plant must reach 32.4 MW within 500 ms of that moment, which is by 690 ms after fault inception.
  3. Case B: a slower fault is cleared in 400 ms. It is longer than 140 ms, so the 1 second allowance applies. If voltage returns to 90 % at 450 ms after inception, the deadline is 1450 ms.
  4. Reactive range check: at 36 MW and 0.95 power factor, the reactive range at the connection point is 36 × 0.3287 = 11.83 Mvar. That is the room the reactive current can use, within the plant current rating and with active power first.

The point of the example is the deadline arithmetic. In the model and in the test, the clock starts when voltage crosses 90 %, not when the fault clears. The target also follows the set-point when it is below available power.

How this compares with other regimes

Great Britain’s equivalent requirements for power park modules are in the GB fault ride through guide and, for smaller plants, the G99 guide. The US picture is in the ERCOT ride-through guide, and the Australian rules are in the S5.2.5.4 guide. The three-country ride-through comparison lines up the numbers. Irish values apply to Irish projects only.

Checklist for the engineer

  • Read the envelope and the clause text in the Grid Code version of your connection agreement.
  • Request the pre-fault and post-fault conditions, including minimum short-circuit capacity.
  • Check the active power recovery against the 140 ms and the longer-fault deadlines, with the set-point and the available power.
  • Confirm the reactive current rise time and settling time of the converters and the plant controller.
  • Confirm the return to the pre-fault reactive mode within 500 ms.
  • Decide the source of dynamic reactive current: units only, or units with a statcom.
  • Run the plant model against the envelope for single-phase and three-phase dips.
  • Keep the study ready for your chartered engineer to review and sign.

From the clause to a study your engineer can sign

The ride-through result depends on the model, the connection conditions and the controller settings. Tiza prepares power-system studies for generation projects, with the assumptions listed against the clause numbers. Tiza does not stamp, sign or certify. The studies are delivered ready for your chartered engineer, registered with Engineers Ireland, to review and sign before anything is sent to EirGrid. Contact us with the plant data and the connection documents.

Frequently asked questions

How fast must a plant recover active power after a fault?

Clause PPM1.4.2(b) asks for at least 90 % of the lesser of available active power and the active power set-point, as quickly as the technology allows and within 500 ms of voltage recovering to 90 % of nominal, for faults cleared within 140 ms. For longer faults the time allowed is 1 second.

Which has priority during a dip, active or reactive current?

Clause PPM1.4.2(c) gives priority to the active power response. The reactive current response is supplied within the plant rating and should be at least proportional to the voltage dip, with a rise time no greater than 100 ms and a settling time no greater than 300 ms.

Who decides the fault conditions used to prove ride through?

EirGrid specifies the pre-fault and post-fault conditions case by case and makes them public. They include the minimum short-circuit capacity at the connection point, the pre-fault active and reactive power operating point and the voltage.