Clause S5.2.5.4 of the National Electricity Rules sets how long a generating plant must stay connected when voltage at its connection point goes above 110% or below 90% of nominal. The automatic standard covers up to 130% for 0.02 seconds and down to 70% for 2 seconds, with defined time bands between. The minimum standard is less demanding. Voltage-time settings in inverters and relays must sit outside these bands, and the performance standard records the agreed values.
S5.2.5.4 response to voltage disturbances is the clause in Schedule 5.2 of the National Electricity Rules (NER) that sets how long a generating plant must stay connected during abnormal voltage. It covers over-voltage up to 130% of nominal and under-voltage down to 70%. The values drive the settings of inverter protection and plant relays. See also the Australia electrical codes and grid connection guide and the guide to generator performance standards.
Short answer
The clause works with time bands. Voltage is the root mean square value at the connection point, phase to phase or phase to ground. The timer starts at T(ov), the moment voltage first goes above 110% of nominal, or T(uv), the moment it first goes below 90%.
- Automatic access standard: the plant, each operating production unit and any synchronous condenser stay in continuous uninterrupted operation through the bands in the table below.
- Minimum access standard: shorter times for the high bands, and a lower under-voltage time at 80% to 90%.
- Negotiated standard: assessed by the network service provider (NSP) and AEMO against the expected performance of existing networks and plant.
The time bands
| Voltage band (of nominal) | Automatic standard | Minimum standard |
|---|---|---|
| Marginally above 130% | 0.02 s | none |
| Above 125% to 130% | 0.2 s | none |
| Above 120% to 125% | 2 s | none |
| Above 115% to 120% | 20 s | 0.1 s |
| Above 110% to 115% | 20 min | 0.9 s |
| 90% to 110% | continuous | continuous, with a voltage-to-frequency condition |
| Below 90% down to 80% | 10 s | 5 s |
| Below 80% down to 70% | 2 s | 2 s |
The table summarises the automatic and minimum access standards of clause S5.2.5.4, as amended from 21 August 2025.
General requirements
For voltage variations within 90% to 110%, active power output must not reduce and reactive power capability must be kept in line with the performance standard for S5.2.5.1. Several allowances apply. On-load tap changers, switching and overload capability may help. Transient responses are ignored. Reductions caused by energy source availability and losses are permitted. For variations greater than 10% inside the 90% to 110% range, reasonable temporary changes are allowed if tap changing or agreed operating arrangements correct them.
Sometimes the nominal voltage at the connection point is below 66 kV and no automatic tap-changing transformer sits between the plant and that point. In that case the NSP and AEMO may agree to measure at the closest point of 66 kV or above.
The performance standard must record any operating arrangements needed so the plant meets its agreed levels under abnormal network or plant conditions.
Relay and controller settings
Every voltage-based trip in the plant has to be compared with the table. That includes inverter protection, plant controller logic, auxiliary supply and the settings of relays in the plant substation. Clause S5.2.5.8 covers the protection design and is the place where the ride-through and the protection must agree. A trip that acts sooner than the table allows, with no agreed exception, fails the clause.
For the effect on motors and auxiliary loads during a sag, see large motor starting and voltage dip. To read what the plant actually did during a sag, use the oscillography record.
Worked example: checking three settings
The numbers are illustrative. A plant has these settings at its connection point.
- Under-voltage: trip when voltage stays below 85% for 1.0 second. The automatic standard requires ride-through for voltage below 90% down to 80% for 10 seconds. The minimum standard requires 5 seconds. A trip at 85% after 1.0 second acts before both times, so it meets neither level.
- Over-voltage: trip when voltage stays above 118% for 5 seconds. The automatic standard requires 20 seconds for the band above 115% to 120%, so the setting is too short. The minimum standard requires only 0.1 seconds for that band, so the same setting passes the minimum but not the automatic level.
- Voltage-to-frequency ratio: voltage 112% of nominal and frequency 48.5 Hz, which is 97% of 50 Hz. The ratio is 1.12 / 0.97 = 1.155. That is above 1.15, so it may last no more than 2 minutes. At 49.0 Hz (98%), the ratio is 1.12 / 0.98 = 1.143, which is below 1.15 and so is not limited by that condition.
Figure: voltage against time on a logarithmic time axis, with the automatic and minimum ride-through envelopes from 70% to 130% of nominal voltage.
Checklist for the engineer
- Take the table values from the version of clause S5.2.5.4 that applies to your enquiry.
- List every voltage trip and delay in the plant, from the inverter to the connection point relay.
- Check that each trip is slower than the table, or is covered by an agreed negotiated standard.
- Check that the plant keeps active power and reactive capability inside the 90% to 110% range.
- Confirm the measurement point and the voltage transformer (VT) or inverter measurement accuracy.
- Prepare the model and the test plan that show the voltage response at commissioning.
Related guides
Related guides in this series: frequency disturbance ride-through and disturbance ride-through. Technical background: loss of potential alarm and VT fuse failure and on-load tap changer and voltage regulation.
Who reviews and certifies
Engineer registration is a state matter. In Queensland, professional engineering services must be provided by or under the direct supervision of an RPEQ.
How Tiza can help
Tiza provides remote relay configuration in English: the voltage protection settings plan, checked against the agreed performance standard. Tiza does not stamp, sign or certify anything in Australia. The deliverables are ready for review and certification by your RPEQ in Queensland, or by the registered engineer your state requires. Contact us with the agreed standard and the plant protection data.
Frequently asked questions
What is the lowest voltage a NEM generator must ride through?
Under the automatic access standard, the plant must stay in continuous uninterrupted operation for voltage below 80% down to and including 70% of nominal for at least 2 seconds after the voltage first falls below 90%. The minimum standard has the same 2 second requirement for that range.
How long must a plant ride through 115% to 120% voltage?
Under the automatic standard, at least 20 seconds after the voltage first rises above 110%. Under the minimum standard, at least 0.1 seconds for that range.
What does the minimum standard say about voltage and frequency together?
For 90% to 110% voltage, the plant must run continuously as long as the ratio of voltage to frequency, both as percentages of nominal, does not exceed 1.15 for more than 2 minutes or 1.10 for more than 10 minutes.