Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

S5.2.5.5 Disturbance Ride-Through and Multiple Faults

S5.2.5.5 disturbance ride-through in the NER: faults a NEM generator must survive, the multiple-fault series and reactive current response in S5.2.5.5A.

By Shadai García, CEO and protection engineer at Tiza Group.

NSP busACT50/51relayfeeder faultfeeder ABVT=~DCinverterplant27 / 59no tripvoltage dip on the busPowerMeasure / triptime below 0.90 pu: 1,320 msintegral: 0.5045 pu secondautomatic 1,800 ms, 1 pu s: insideminimum 1,000 ms, 0.5 pu s: outsidepufive minutes0.900.501.000.20 pu0.32 s0.45 pu0.28 s0.60 pu0.45 s0.85 pu0.15 s0.80 pu0.12 sdips drawn as rectangles; not to scale in timeRide-throughFaultSeriesCountIntegralCheck© tizagrp.comNSP busACT50/51relayfeeder faultfeeder ABVT=~DCinverterplant27 / 59no tripvoltage dip on the busPowerMeasure / triptime below 0.90 pu: 1,320 msintegral: 0.5045 pu secondautomatic 1,800 ms, 1 pu s: insideminimum 1,000 ms, 0.5 pu s: outsidepufive minutes0.900.501.000.20 pu0.32 s0.45 pu0.28 s0.60 pu0.45 s0.85 pu0.15 s0.80 pu0.12 sdips drawn as rectangles; not to scale in timeRide-throughFaultSeriesCountIntegralCheck© tizagrp.com
Disturbance ride-through S5.2.5.5: a network feeder fault cleared by its own breaker and relay while an inverter plant on the same bus stays connected, and the connection point voltage over five faults in five minutes of 0.20 pu for 0.32 s, 0.45 for 0.28, 0.60 for 0.45, 0.85 for 0.15 and 0.80 for 0.12 with the 90 percent and 50 percent lines, 1,320 ms below 0.90 pu and a voltage-time integral of 0.5045 pu second. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Clause S5.2.5.5 of the National Electricity Rules, now titled disturbance ride-through capability, requires a generating plant to stay connected through credible contingency events and a defined series of faults. The automatic standard allows up to 15 disturbances in five minutes. The minimum standard allows up to 6. Limits on cumulative time and the voltage-time integral below 90% bound the series. Clause S5.2.5.5A adds the reactive current response during the disturbance.

S5.2.5.5 disturbance ride-through is the clause in Schedule 5.2 of the National Electricity Rules (NER) that asks a generating plant to stay online while the network clears faults. In the National Electricity Market (NEM), a single fault can drag the voltage down at many plants at once. If all of them trip, the event gets worse. The clause covers single faults, a series of faults in a short window, and how long the voltage may stay low. Before 21 August 2025 its title was “Response to disturbances following contingency events”. Since then a similar title, “Responses to disturbances following contingency events”, heads the new clause S5.2.5.5A. The wider framework is in the Australia electrical codes and grid connection guide, and the three levels of standard are explained in the guide to generator performance standards. The Australian Energy Market Operator (AEMO) assesses the agreed level with the network service provider.

Short answer

  1. Single events: the plant, each operating production unit and any synchronous condenser stay in continuous uninterrupted operation for a credible contingency event, or for a fault cleared by the relevant protection.
  2. Series of events: up to 15 disturbances in five minutes under the automatic standard, and up to 6 under the minimum standard.
  3. Limits: the series must not island the plant, and the time and depth of low voltage are capped.
  4. Reactive current: clause S5.2.5.5A sets the response during the disturbance.
  5. Negotiated standard: accepted if the plant, at the proposed level, would not cause other plant to trip that would otherwise have stayed on.

Single faults

Under the automatic standard, the plant must ride through:

  • a credible contingency event;
  • a three-phase fault in a transmission system cleared by all relevant primary protection;
  • an unbalanced fault in a transmission system (two-phase-to-ground, phase-to-phase or phase-to-ground), cleared in the longest breaker fail time. With no breaker fail protection, the clearing time is the greater of 430 milliseconds (or the time in Table S5.1a.2) and the longest primary time;
  • a three-phase or unbalanced fault in a distribution network, cleared in the longest breaker fail time, or the greater of 430 milliseconds and the longest primary clearing time.

Under the minimum standard, the plant must ride through a credible contingency event and a single-phase-to-ground, phase-to-phase or two-phase-to-ground fault cleared by primary protection. An exception applies if AEMO and the network service provider (NSP) agree that the total impact on the power system would not exceed 100 MW. They may agree a greater limit they consider reasonable.

The series of faults

ItemAutomatic standardMinimum standard
Disturbances in any five minutesup to 15up to 6
Of which voltage below 50%up to 6up to 3
Three-phase faultsup to 2 where three-phase reclose is permitted, else 1none
Cleared by breaker failup to 1not applicable
Gap between disturbancesmay be zeromore than 200 ms, and no more than 3 within 30 s
Cumulative time below 90% in five minutesnot more than 1,800 msnot more than 1,000 ms
Voltage-time integral below 90% in five minutesnot more than 1 pu secondnot more than 0.5 pu second

The table summarises the automatic standard in S5.2.5.5(d) and the minimum standard of the same clause. The minimum series also needs 30 minutes with no disturbance afterwards. A fault that is re-established after an automatic reclose counts as a separate disturbance. A disturbance ends when voltage returns to 90% to 110% and stays there for at least 20 milliseconds.

Reactive current response, clause S5.2.5.5A

For asynchronous plant such as inverter-based plant, the automatic standard asks for reactive current to support the voltage during the fault. The plant must supply positive-sequence capacitive reactive current of at least 4% of the maximum continuous current for each 1% fall in voltage below the starting level. For a voltage rise it must absorb at least 6% for each 1% rise. It must also provide negative-sequence current to oppose unbalance. The response starts within 10 milliseconds once the voltage passes the starting level, which is 85% for under-voltage and 115% for over-voltage unless agreed otherwise. For a voltage step, the rise time of the reactive current is no more than 40 milliseconds. Active power must return to at least 95% of its pre-fault level within 100 milliseconds after the disturbance ends.

Synchronous plant has its own paragraphs in the same clause.

Worked example: five disturbances in five minutes

The numbers are illustrative. An inverter plant sees five disturbances in a five-minute window. Each has a residual voltage and a duration:

EventResidual voltageDuration
10.20 pu0.32 s
20.45 pu0.28 s
30.60 pu0.45 s
40.85 pu0.15 s
50.80 pu0.12 s
  1. Cumulative time below 0.90 pu: 0.32 + 0.28 + 0.45 + 0.15 + 0.12 = 1.32 s, or 1,320 ms.
  2. Voltage-time integral: each dip is its depth below 0.90 pu times its duration. The sum is 0.224 + 0.126 + 0.135 + 0.0075 + 0.012 = 0.5045 pu second. This treats each dip as a rectangle, which slightly overstates a real sloped profile.
  3. Automatic standard: 1,320 ms is below 1,800 ms, and 0.5045 is below 1 pu second. The series is inside the envelope the plant must ride through.
  4. Minimum standard: 1,320 ms is above 1,000 ms, and 0.5045 is above 0.5 pu second. This series is outside the envelope, so the minimum standard does not require ride-through for it.

Figure: connection point voltage against time for a series of five faults in five minutes, with the 90% line and the 50% line marked.

Checklist for the engineer

  • Get the clearing times for the network, including breaker fail times, from the NSP.
  • Set up the model to test single faults, unbalanced faults and the series with zero gap.
  • Check that the inverter or turbine controller counts and restarts correctly through repeated faults.
  • Check the reactive current gains, start points and rise time against S5.2.5.5A.
  • Check that auxiliary supplies, trackers and communications also ride through the series.
  • Record any plant limitation that is agreed in a negotiated standard.

For reading the real behaviour afterwards, see line faults and how to read an event and the oscillography record. Recloser behaviour matters too: see recloser settings, reclosing and curves.

Related guides in this series: response to voltage disturbances and frequency disturbance ride-through. Technical background: power system fault analysis and network topology changes and protection settings.

Who reviews and certifies

Engineer registration is a state matter. In Queensland, professional engineering services must be provided by or under the direct supervision of an RPEQ.

How Tiza can help

Tiza prepares the power-system studies and the dynamic assessment that support a ride-through proposal, remotely and in English. Tiza does not stamp, sign or certify anything in Australia. The results are ready for review and certification by your RPEQ in Queensland, or by the registered engineer your state requires. Contact us with the plant model and the NSP’s requirements.

Frequently asked questions

Why is the clause now called disturbance ride-through capability?

The Improving the NEM access standards, Package 1 rule, in force from 21 August 2025, changed the heading of S5.2.5.5 and moved the reactive current response into a new clause, S5.2.5.5A. The earlier title, now in the plural, heads S5.2.5.5A: responses to disturbances following contingency events. Older documents still use it for S5.2.5.5.

How many faults in a row must a plant ride through?

Under the automatic standard, up to 15 disturbances within any five minute period, with up to 6 of them taking voltage below 50%. Under the minimum standard, up to 6 disturbances, with up to 3 below 50%, with a 30 minute gap with no disturbances after the series.

Does the plant have to ride through a fault that disconnects it from the grid?

No. The requirement applies to events that do not disconnect the plant from the power system by removing network elements from service. Series that cause islanding, or that exceed the cumulative time and voltage-time limits, are also outside it.

WhatsApp