Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

S5.2.5.7 Partial Load Rejection for Synchronous Units

S5.2.5.7 partial load rejection: the 30% and 5% load drops a synchronous NEM generator must ride through, the size threshold and the minimum-load rule.

By Shadai García, CEO and protection engineer at Tiza Group.

network busbreakerCT50/51relaystep-uptransformerGG50 MW50 MWspeed and frequency riseload50/51relayload blockswitched offPowerMeasure / trip2 x 50 = 100 MW, above 25 MWminimum level 2 x 0.40 x 50 = 40 MWA: 0.70 x 70 = 49 MW, above 40B: 0.70 x 50 = 35 MW, below 40MW40minimum 40 MW70load49-30%66.5-5%A: loaded 70 MW50load35-30%47.5-5%B: loaded 50 MWB at -5%: 47.5 MW, minimum standard appliesCheckRelevant systemLoad lossMinimum levelCaseRecord© tizagrp.comnetwork busbreakerCT50/51relaystep-uptransformerGG50 MW50 MWspeed and frequency riseload50/51relayload blockswitched offPowerMeasure / trip2 x 50 = 100 MW, above 25 MWminimum level 2 x 0.40 x 50 = 40 MWA: 0.70 x 70 = 49 MW, above 40B: 0.70 x 50 = 35 MW, below 40MW40minimum 40 MW70load49-30%66.5-5%A: loaded 70 MW50load35-30%47.5-5%B: loaded 50 MWB at -5%: 47.5 MW, minimum standard appliesCheckRelevant systemLoad lossMinimum levelCaseRecord© tizagrp.com
Partial load rejection S5.2.5.7: two 50 MW synchronous units with a step-up transformer and connection point breaker with CT and relay on a network bus, with a block of network load switched off, and the loading before and after a 30 percent and 5 percent load reduction against the combined minimum operating level of 40 MW for a plant loaded at 70 MW and at 50 MW. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Clause S5.2.5.7 of the National Electricity Rules requires larger synchronous generating units to stay connected when part of the system load disappears. The automatic standard is a 30% load reduction, or the equivalent effect of part of the system separating, within 10 seconds. The minimum standard is 5%. The units must be loaded above their combined minimum operating level. The clause applies only to the synchronous part of a plant, and only above a size threshold.

S5.2.5.7 partial load rejection is the clause in Schedule 5.2 of the National Electricity Rules (NER) that protects the grid from losing synchronous generation when part of the load suddenly disappears. If a large block of load trips, or part of the network separates, the remaining generators speed up, and the system frequency rises. A generator that trips on that event removes still more supply from the part of the grid that remains. The clause sets how big a load loss a synchronous plant must ride through. For the wider framework see the Australia electrical codes and grid connection guide and the guide to generator performance standards. The Australian Energy Market Operator (AEMO) and the network service provider (NSP) assess the proposal.

Short answer

  1. Who: a relevant system. That is synchronous production units, or the synchronous part of a production system. Their combined nameplate must be at or above the lower of 30 MW and 5% of the maximum credible contingency size.
  2. Automatic access standard: stay in continuous uninterrupted operation during and after a 30% load reduction in under 10 seconds. A part of the system separating, with the same effect, counts as well.
  3. Minimum access standard: the same, for a 5% reduction.
  4. Condition: the combined loading of the operating synchronous units remains above their combined minimum operating level.
  5. Recording: the agreed performance is recorded in the performance standard.

What the clause allows

During the event, the plant may change active power and reactive power as far as needed to oppose a voltage or frequency change. A unit that raises its output to support a falling frequency, or lowers it to support a rising one, is not in breach.

The clause is limited to synchronous machines. Since the 21 August 2025 amendment, its heading carries the words “for synchronous production units”, and the clause applies only to them. A plant with both synchronous and inverter-based units follows S5.2.5.7 for its synchronous units only.

Why the minimum-load condition matters

A synchronous unit cannot run below its minimum stable output. If the load rejection pushes the combined loading below the combined minimum operating level, the clause does not require the units to stay on. The plant’s performance standard should therefore document the minimum operating level used in the assessment. The point is where the governor and the turbine controls can hold the machine, and where a unit would need to shut down.

Governor and speed control behaviour decides how a machine handles the first seconds after the event. The excitation system matters too, since the voltage rises as load falls. See generator excitation and AVR, the inertia constant H and synchronous generator models and transformer overfluxing and load rejection, which covers the step-up transformer side of the same event.

What the assessor looks at

The NSP and AEMO ask for simulation of the load rejection with the plant model, using the unit controls as built. The results should show active power, speed or frequency, terminal voltage and the excitation response. They also ask which protection could act during the event, such as over-speed, over-voltage and over-frequency elements, and at what setting.

Worked example: does the 30% case apply?

The numbers are illustrative. A plant has two synchronous units of 50 MW each. The minimum stable output of each unit is 40% of its rating. Assume the plant output falls in proportion to the load reduction.

  1. Relevant system: 2 × 50 = 100 MW combined nameplate. In a region with a maximum credible contingency of 500 MW, 5% is 25 MW. The lower of 30 MW and 25 MW is 25 MW. The plant is above it, so S5.2.5.7 applies.
  2. Combined minimum operating level: 2 × 0.40 × 50 = 40 MW.
  3. Case A, plant loaded at 70 MW: a 30% reduction takes the loading to 0.70 × 70 = 49 MW. That is above 40 MW, so the automatic standard requires the plant to stay online. A 5% reduction gives 66.5 MW, also above 40 MW.
  4. Case B, plant loaded at 50 MW: a 30% reduction takes the loading to 35 MW. That is below 40 MW, so the minimum-load condition is not met and the 30% requirement does not apply. A 5% reduction gives 47.5 MW, above 40 MW, so the minimum standard still applies.

The example shows why the loading condition at the time of the event, and the minimum operating level, belong in the performance standard.

Figure: single-line diagram of two synchronous units, the step-up transformer and the connection point, with a block of network load that is switched off.

Checklist for the engineer

  • Confirm the size threshold with the region’s frequency operating standard.
  • Collect the minimum stable output of each synchronous unit and the combined minimum operating level.
  • Model a 30% and a 5% load reduction in under 10 seconds, and an island case that has the same effect.
  • Check the governor, the speed limits, the over-speed trip and the voltage controller settings.
  • Check the step-up transformer for overfluxing when the voltage and frequency change together.
  • Record the agreed result in the performance standard.

Related guides in this series: frequency disturbance ride-through and reactive power capability. Technical background: generator faults and how they are detected and protection of the generator excitation system.

Who reviews and certifies

Engineer registration is a state matter. In Queensland, professional engineering services must be provided by or under the direct supervision of an RPEQ.

How Tiza can help

Tiza prepares the power-system studies and dynamic simulations behind a load rejection proposal, remotely and in English. Tiza does not stamp, sign or certify anything in Australia. The results are ready for review and certification by your RPEQ in Queensland, or by the registered engineer your state requires. Contact us with the unit data and the network requirements.

Frequently asked questions

Which plants does S5.2.5.7 apply to?

Only to synchronous production units, and to a production system only for its synchronous part. It also applies only to a relevant system, meaning synchronous units with a combined nameplate rating at or above the lower of 30 MW and 5% of the maximum credible contingency size in the region's frequency operating standard.

Does an inverter-based solar or battery plant have to meet S5.2.5.7?

No. Since the Improving the NEM access standards, Package 1 rule took effect on 21 August 2025, the clause heading refers to synchronous production units and the clause applies only to them. Inverter-based plant is covered by the frequency and ride-through clauses.

What does 30% load reduction mean for the plant?

It is a reduction in power system load of 30%, or an equivalent effect from part of the power system separating, in less than 10 seconds. The generator must stay in operation during and after it, as long as the combined loading of the operating synchronous units stays above their combined minimum operating level.

WhatsApp