Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

S5.2.5.1 Reactive Power Capability in the NEM

S5.2.5.1 reactive power capability: the 0.395 factor, the mid-point voltage profile, temperature derating and negotiated levels for generators in the NEM.

By Shadai García, CEO and protection engineer at Tiza Group.

NSP busbreakerCT50/51relayCTVTMmeterplanttransformerLV busGGQ supplied to the networkQ absorbed from the network100 MWproduction systemPowerMeasure0.395 x 100 MW = 39.5 Mvarflat region 101% +/- 5%: 96 to 106%93%: 39.5 x 3 / 6 = 19.75 Mvar108%: 39.5 x 2 / 4 = 19.75 Mvar10% derating: 90 MW, 35.55 MvarMvarV %039.5-39.5flat region9096101106110supplyabsorb19.75 at 93%19.75 at 108%voltage at the connection point, % of nominalillustrative: limits 90% and 110%; PF 0.93CapabilityPmaxFlat regionLinear fallIdle plantRecord© tizagrp.comNSP busbreakerCT50/51relayCTVTMmeterplanttransformerLV busGGQ supplied to the networkQ absorbed from the network100 MWproduction systemPowerMeasure0.395 x 100 MW = 39.5 Mvarflat region 101% +/- 5%: 96 to 106%93%: 39.5 x 3 / 6 = 19.75 Mvar108%: 39.5 x 2 / 4 = 19.75 Mvar10% derating: 90 MW, 35.55 MvarMvarV %039.5-39.5flat region9096101106110supplyabsorb19.75 at 93%19.75 at 108%voltage at the connection point, % of nominalillustrative: limits 90% and 110%; PF 0.93CapabilityPmaxFlat regionLinear fallIdle plantRecord© tizagrp.com
Reactive power capability S5.2.5.1: a 100 MW production system at the connection point supplying and absorbing reactive power, and the supply and absorption limits against connection point voltage with a flat region of 96 to 106 percent, linear falls to zero at 90 and 110 percent, 39.5 Mvar, 19.75 Mvar at 93 and 108 percent. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Clause S5.2.5.1 of the National Electricity Rules sets how much reactive power a generating plant must be able to supply and absorb at its connection point. The automatic standard is 0.395 times the maximum active power, held across a voltage band set around a mid-point chosen by the network service provider, and reduced linearly toward the voltage limits. The minimum standard asks for no reactive capability but limits the voltage change when the plant is connected and idle.

S5.2.5.1 reactive power capability is the first technical clause in Schedule 5.2 of the National Electricity Rules (NER). It decides how much reactive power a generator, battery or other schedule 5.2 plant must be able to supply to the grid and absorb from it. The size of that capability drives the choice of inverters, transformer ratio and any extra compensation equipment. For the wider picture see the Australia electrical codes and grid connection guide and the guide to generator performance standards.

Short answer

Under the clause as amended from 21 August 2025:

  1. Automatic access standard: with all production units in service and at any level of active power, the plant must supply and absorb at least 0.395 times its maximum active power (Pmax) as reactive power at the connection point. This holds across a band of five percent of nominal voltage above and below a mid-point voltage. The network service provider (NSP) chooses that mid-point.
  2. Outside that band: the requirement falls linearly toward zero at the voltage limits set in clause S5.1a.4.
  3. Minimum access standard: no reactive power capability is required. The plant must not change the connection point voltage by more than 1%, or a higher agreed figure, when it is connected but idle.
  4. Negotiated standard: a level agreed with the NSP and the Australian Energy Market Operator (AEMO), set high enough to meet the system standards.

Reading the profile

The mid-point voltage is a value the NSP specifies for the plant’s connection point, between 95% and 105% of nominal voltage. Around it, the standard defines a flat region of 10% of nominal voltage in total.

  • Inside the flat region: supply and absorb at least 0.395 × Pmax.
  • Above the region, up to the upper voltage limit: absorb at least 0.395 × Pmax. The supply requirement falls linearly to zero at the limit.
  • Below the region, down to the lower voltage limit: supply at least 0.395 × Pmax. The absorption requirement falls linearly to zero at the limit.

The shape matches what the network needs. At high voltage, injecting more reactive power would push voltage higher still. At low voltage, absorbing more would push it lower. The clause therefore drops the capability that would work against the grid.

For an integrated resource system such as a battery, Pmax is the higher of its active power capability and its maximum demand under the automatic standard. It is reduced by any applicable temperature derating. Temperature derating is an amount by which capability may be cut when ambient temperature materially affects the plant.

Idle plant and compensation

Two paragraphs cover a plant that is energised but not producing. Under the automatic standard, it must not change the voltage at the connection point in steady state. This matters for long cables and for plant with large filter capacitance. Where the plant meets the requirement with reactive compensation, the clause requires a performance standard for the stability of that control, including a settling time for a voltage step.

When the plant cannot reach the standard

A negotiated standard must be set at a level consistent with the system standards before and after credible contingencies. If the plant falls short, the clause lists the remedies, and the applicant may use one or more:

  • pay compensation to the NSP for the reactive power it must provide from the network;
  • install extra equipment at the connection point or elsewhere, which then counts as part of the plant;
  • reach a commercial arrangement with a registered participant;
  • agree operating arrangements for the conditions where the gap occurs.

The performance standard must also record the agreed capability, the temperature limits and any extra capability above the required level.

Worked example: the profile for a 100 MW plant

The numbers are illustrative. A 100 MW production system, with a mid-point voltage of 101%. Assume the S5.1a.4 voltage limits are 90% and 110% of nominal.

  1. Full requirement: 0.395 × 100 MW = 39.5 Mvar.
  2. Flat region: 101% ± 5%, so 96% to 106% of nominal.
  3. At 93% voltage, supply stays at 39.5 Mvar. Absorption falls linearly from 39.5 Mvar at 96% to zero at 90%: 39.5 × (93 − 90) / (96 − 90) = 19.75 Mvar.
  4. At 108% voltage, absorption stays at 39.5 Mvar. Supply falls from 39.5 Mvar at 106% to zero at 110%: 39.5 × (110 − 108) / (110 − 106) = 19.75 Mvar.
  5. With a 10% temperature derating of Pmax at the design ambient, Pmax becomes 90 MW and the full requirement becomes 0.395 × 90 = 35.55 Mvar.

As a ratio, 0.395 corresponds to a power factor of cos(arctan 0.395), about 0.93.

Figure: reactive power supplied and absorbed against connection point voltage. The flat region sits around the mid-point voltage and the lines fall linearly to zero at the voltage limits.

Checklist for the engineer

  • Ask the NSP for the mid-point voltage and the voltage limits at the connection point.
  • Define Pmax with all units in service and apply the derating the plant will actually have.
  • Check inverter capability curves at the terminals, then add transformer and cable losses to find the capability at the connection point.
  • Check the reactive power the plant draws or produces when energised and idle.
  • If compensation equipment is needed, define its control stability and settling time.
  • Record the agreed values in the performance standard.

Related guides in this series: quality of electricity generated and response to voltage disturbances. Technical background: solar panels and power factor, capacitive reactive power, on-load tap changer and voltage regulation and transformer voltage drop under load.

Who reviews and certifies

Engineer registration is a state matter. In Queensland, professional engineering services must be provided by or under the direct supervision of an RPEQ.

How Tiza can help

Tiza prepares the power-system studies behind a reactive power proposal, such as load-flow and voltage studies, remotely and in English. Tiza does not stamp, sign or certify anything in Australia. The results are ready for review and certification by your RPEQ in Queensland, or by the registered engineer your state requires. Contact us with the plant data and the NSP’s connection requirements.

Frequently asked questions

What does 0.395 mean in clause S5.2.5.1?

It is the factor applied to the plant's maximum active power. At 100 MW, the automatic access standard requires at least 39.5 Mvar of reactive power supply and absorption in the main voltage band. As a ratio of reactive to active power, it corresponds to a power factor of about 0.93, calculated as cos(arctan 0.395).

Who sets the mid-point voltage?

The network service provider specifies it for the connection point, within 95% to 105% of nominal voltage. The full reactive power requirement applies in a band of five percent of nominal voltage above and below it.

Is there a minimum reactive power requirement?

The minimum access standard requires no reactive power capability. It does limit how much the plant may change the connection point voltage when it is connected but not otherwise in service. The usual limit is 1% unless a higher figure is agreed with the network service provider.

WhatsApp