Part 8 of the Electricity Industry Participation Code sets the common quality rules for the New Zealand grid. Subpart 1 covers the system operator, Subpart 2 the performance obligations and technical standards of asset owners, and Subpart 7, added in July 2026, the commissioning, testing and information standard. For a generator, clauses 8.17 to 8.25D on frequency, voltage and fault ride-through carry the main duties.
Short answer: what Code Part 8 covers
Code Part 8 is the Common quality part of the Electricity Industry Participation Code 2010. It sets how the system operator, Transpower, keeps the grid secure, and what generators, grid owners and large consumers must do so their assets support that goal. It is the part that matters for technical requirements in New Zealand. Part 6, covered in the distributed generation guide, deals with how a small generator connects to a local network.
The clauses cited are those of Part 8 on the Electricity Authority website, with the latest amendment dated 30 October 2026. The Code is amended often, so confirm the version date before you rely on any clause. The Ireland and New Zealand grid codes guide places Part 8 beside the other documents.
How Part 8 is organised
| Subpart | Clauses | Subject |
|---|---|---|
| 1 | 8.2 to 8.15 | Performance obligations of the system operator |
| 2 | 8.16 to 8.38 | Asset owner performance obligations and technical standards |
| 3 | 8.39 to 8.54 | Arrangements for ancillary services |
| 4 | 8.54A to 8.54BA | Interruptible load and emergency reserve |
| 5 | 8.54C to 8.54TF | Revoked |
| 6 | 8.54U to 8.70 | Allocating costs |
| 7 | 8.71 to 8.76 | Connected asset commissioning, testing and information standard |
The schedules include Schedule 8.1 (equivalence arrangements and dispensations), Schedule 8.2 (alternative ancillary service arrangements) and Schedule 8.3, the technical codes. The guide on the Transpower technical code explains Schedule 8.3.
Subpart 2: the duties that bind a generator
Subpart 2 is where a project team spends most of its time.
- 8.17, frequency contribution. Generators, while synchronised, must help keep frequency inside the normal band. This does not apply to units at excluded generating stations.
- 8.19, under-frequency events. Generators must stay synchronised and hold output through a defined frequency range, with time limits that shorten as frequency falls. South Island and HVDC provisions are separate.
- 8.22, voltage ranges. Assets must operate inside set voltage bands.
- 8.23, voltage support. Grid-connected generating stations must export and import reactive power in stated shares of maximum continuous MW output.
- 8.23A, embedded generation. Since 1 July 2026, some embedded stations must export and import at least 33% of maximum continuous MW output as reactive power, measured at the point of connection. The clause covers stations of 10 MW or more under clause 5(2A) of Technical Code A, unless agreed otherwise with the distributor.
- 8.25A to 8.25D, fault ride-through. Assets must remain stable and connected during specified grid faults. See ride-through and IBR requirements.
- 8.25(5) to (7), embedded output information. The system operator can ask for intended output information from embedded stations over 10 MW.
The 10 MW line
Clause 8.21 excludes stations under 10 MW from the frequency duties in 8.17 and 8.19 and from 8.25D, and from the Technical Code A frequency provisions. An amendment in force from 1 July 2026 moved the line down to 10 MW from 30 MW. Clause 8.21(3) to (5) adds transitional cases. A station can stay excluded if it cannot comply without modification and its asset capability statement records this. The owner of a generating unit of 1 MW or more must still notify the system operator of its planned connection.
A design team therefore asks two questions at the start. Is the station above or below 10 MW? And is it connected to the grid or embedded in a distribution network? The answers select clause 8.23 or 8.23A and the frequency duties. For 8.23A, a third question matters: does the station connect at the nominal voltage of the closest busbar where the grid owner supplies the local network?
Subpart 7: the commissioning standard
The connected asset commissioning, testing and information standard became a system operation document on 1 July 2026. Clause 8.74 lists what it covers: commissioning and decommissioning information, asset capability statements, connection studies, periodic testing, operational communications, high-speed monitors and time frames. Clause 8.75 sets transitional rules for assets connected before and after 1 July 2026.
Compliance and dispensations
Owners must comply at all times and show it on request (clause 8.28). The system operator monitors compliance (clause 8.27) and may decline to dispatch a non-compliant asset after warning the owner. Clauses 8.29 to 8.37 allow an equivalence arrangement or a dispensation. The system operator cannot grant a dispensation for automatic under-frequency load shedding.
Worked example: an embedded solar plant above the line
The numbers are illustrative. A 12 MW solar plant connects to a distribution network at the voltage of the closest grid supply busbar.
- 12 MW is above 10 MW, so the exclusion in clause 8.21 does not apply, assuming no transitional case.
- Clause 8.23A asks for at least 33% of maximum continuous output in each direction: Q = 0.33 × 12 = 3.96 Mvar, exported and imported.
- Apparent power at the limit: S = √(12² + 3.96²) = √159.7 = 12.64 MVA.
The inverters must therefore be rated for about 12.64 MVA at the connection point, and a little more to cover losses. A 9.5 MW plant on the same feeder would fall under the exclusion in clause 8.21 for the clauses it lists. It would still follow Part 6 and the distributor’s requirements.
Checklist for the engineer
- Note the Part 8 version date and amendment history for the clauses you rely on.
- Decide whether the station is grid-connected or embedded and whether it is above 10 MW.
- Map each duty in clauses 8.17 to 8.25D to a design requirement.
- Gather the asset capability data the commissioning standard asks for.
- Agree any variation with the distributor or the system operator in writing.
- Plan modelling and study inputs early. See grid connection and Transpower studies.
Compare with other regimes
Australia puts these duties into generator performance standards agreed for each plant. The United Kingdom splits them by plant size in the G99 type A to D structure. Ireland uses the EirGrid Grid Code. In New Zealand, one national Code applies to a single national grid.
Review before submission
A missed clause, a wrong threshold or an inconsistent capability statement is cheaper to fix in design than after the system operator or distributor finds it. Tiza does not sign or certify designs in New Zealand. We deliver engineering design and studies with each Part 8 duty mapped to a design requirement, ready for your Chartered Professional Engineer (CPEng) to review and sign. Contact us with the site data and the Code version.
Frequently asked questions
What is Part 8 of the Electricity Industry Participation Code about?
Part 8 is titled Common quality. It sets what the system operator must do to keep the grid secure and what asset owners must do so the assets support it. Its schedules include the technical codes.
Does Part 8 apply to small distributed generation?
Mostly not. Clause 8.21 excludes generating stations under 10 MW from several obligations, including clauses 8.17, 8.19 and 8.25D, unless the Authority directs otherwise under clause 8.38. Part 6 governs how they connect to a distributor.
Where do I find the current version of Part 8?
On the Electricity Authority's Code page, which publishes each dated version with history notes. Part 8 changed on 1 July 2026 and again on 1 August, 1 September, 1 October and 30 October 2026, so always quote the date you used.