Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

AS/NZS 3000 in New Zealand: Wiring Rules and ECPs

AS/NZS 3000 in New Zealand: how the Electricity (Safety) Regulations cite the 2018 edition, the 13 November 2026 changeover and related codes of practice.

By Shadai García, CEO and protection engineer at Tiza Group.

Electricity Act 1992section 36Electricity (Safety)Regulations 2010reg 14, 59-61, 62, 65-66reg 59Schedule 2: AS/NZS 3000:2018Amd 1-3, NZ modificationsWorkSafe codesNZECP 34safe distancesNZECP 35power systems earthingCited by / issued underA 10 Sep 2025: old editionB 20 Jan 2026: finish by 12 NovC 16 Nov 2026: 2018 edition13 Nov 202512 Nov 2026AB window 296 daysCSep 2025Mar 2026Jul 2026Nov 2026illustrative datesLayerActRegulationsSchedule 2Codes of practiceCertificate© tizagrp.comElectricity Act 1992section 36Electricity (Safety)Regulations 2010reg 14, 59-61, 62, 65-66reg 59Schedule 2: AS/NZS 3000:2018Amd 1-3, NZ modificationsWorkSafe codesNZECP 34safe distancesNZECP 35power systems earthingCited by / issued underA 10 Sep 2025: old editionB 20 Jan 2026: finish by 12 NovC 16 Nov 2026: 2018 edition13 Nov 202512 Nov 2026AB window 296 daysCSep 2025Mar 2026Jul 2026Nov 2026illustrative datesLayerActRegulationsSchedule 2Codes of practiceCertificate© tizagrp.com
Legal layers behind AS/NZS 3000 in New Zealand: the Electricity Act 1992 section 36, the Electricity (Safety) Regulations 2010 with regulations 14, 59 to 61, 62, 65 and 66, Schedule 2 citing AS/NZS 3000:2018 with Amendments 1 to 3 and New Zealand modifications, and the NZECP 34 and NZECP 35 codes of practice beside them, with a timeline of three example projects starting 10 September 2025, 20 January 2026 and 16 November 2026 and a 296 day window for the second. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

In New Zealand, AS/NZS 3000 binds through the Electricity (Safety) Regulations 2010. Since the 2025 amendment, Schedule 2 cites AS/NZS 3000:2018 with Amendments 1, 2 and 3, with New Zealand modifications. Construction that begins after 12 November 2026 must follow the new edition, while earlier work can finish under the 2007 edition. WorkSafe's electrical codes of practice, such as NZECP 34 and NZECP 35, apply beside the standard.

Short answer: AS/NZS 3000 in New Zealand

AS/NZS 3000 is the Australian/New Zealand Wiring Rules. In New Zealand it has legal force through the Electricity (Safety) Regulations 2010. Regulation 59 requires low and extra-low voltage installations to comply with it as cited, and Schedule 2 of the regulations names the cited edition.

The Electricity (Safety) Amendment Regulations 2025 took effect on 13 November 2025. Since then the cited edition is AS/NZS 3000:2018 including Amendments 1, 2 and 3, replacing AS/NZS 3000:2007 with Amendments 1 and 2. The citation carries New Zealand modifications, so the Australian text on its own is not enough.

Figure: how the Act, the regulations, the cited standard and the codes of practice stack in New Zealand.

How the pieces fit

  • Electricity Act 1992. The base law. Under section 36 it allows WorkSafe to issue electrical codes of practice.
  • Electricity (Safety) Regulations 2010. The duties: safe design, certification, inspection and the standards that installations must meet. Regulation 59 is the hook for AS/NZS 3000; regulations 60 and 61 deal with Part 2 of the standard and specific rules for Part 1.
  • Cited standards. AS/NZS 3000 is the main one. The 2025 amendment also updated other citations. AS/NZS 4777.1 is cited for the specific purpose of low-voltage mains parallel generation systems connected to the national grid.
  • Codes of practice. Documents such as NZECP 34 and NZECP 35 sit beside the standard. The guides on safe distances and power systems earthing cover them.

High-voltage installations are treated differently. The regulations require a certified design for them, and WorkSafe points to NZECP 35 for earthing. The earthing guide above explains where that code enters.

The changeover to the 2018 edition

WorkSafe’s guidance sets out the transition. The dates matter more than the clause changes for most projects.

  • From 13 November 2025, a designer or installer may choose the 2018 edition for new installations and for alterations.
  • Where construction began before 13 November 2025, the 2007 edition can be used to completion, with no time limit.
  • Where work under the 2007 edition began after that date, it must be completed by 12 November 2026. If it is unfinished, a certificate of compliance covers the work done, and the rest follows the new edition.
  • All new installations where construction begins after 12 November 2026 must comply with the 2018 edition.
  • Repair and maintenance of existing installations may continue under the old edition, but any alteration or addition within it follows the new one.
  • Construction includes the design phase, so work can follow the old edition if a quote or tender was already under way.

Existing installations do not have to be upgraded, provided they are not unsafe. Only the parts changed follow the new edition.

What the New Zealand citation changes

The Government changed some clauses of AS/NZS 3000:2018 in its citation. WorkSafe lists the changes. They include an added sentence in clause 1.5.6.3 on RCD selection for DC fault currents and waveform distortion. They also replace clause 2.6.2.2.3(b) on RCD types and delete clauses 2.3.2.1.2(b) and (c). Read the list in the amendment regulations before you design to the Australian edition, because the same clause number can have a different outcome in each country.

The standard is shared with Australia. For its structure and its overcurrent, RCD and earthing rules, read the Australian guides on the Wiring Rules, overcurrent and RCD protection and main earthing and MEN systems. The country comparison places the standard beside the NEC and BS 7671.

Worked example: which edition applies to three projects

The dates are illustrative.

ProjectConstruction startRule
A10 September 2025Began before 13 November 2025: the 2007 edition can be used to completion.
B20 January 2026Old edition allowed, but it must be completed by 12 November 2026.
C16 November 2026After 12 November 2026: the 2018 edition with Amendments 1 to 3 applies.

For project B, the window from 20 January to 12 November 2026 is 296 days. If the work will not finish in that window, plan for a certificate of compliance for the part done and design the rest to the new edition from the start. The simplest approach is to design to the 2018 edition from day one, because it is allowed throughout and avoids a split job.

Certification and inspection

WorkSafe’s guidance on the regulations adds duties that the standard does not describe:

  • Installers provide a certificate of compliance for the work they do.
  • Installations considered high risk are subject to third-party inspection, and some installations need periodic assessment, such as a warrant of electrical fitness.
  • A certificate of verification is required to reconnect an installation that has been disconnected for more than six months.
  • High-voltage work must be inspected by a person authorised by their registration and practising licence who did not carry out, supervise or certify that work.

Plan these steps into the project schedule. They affect who can sign each stage, and a certificate of compliance can also mark the point where the changeover date splits a job.

Checklist for the engineer

  • Record the edition and amendments in the design basis and on the drawings.
  • Check the start of construction against the transition dates.
  • Read the New Zealand modifications to the clauses you rely on.
  • Identify which parts of the project are low voltage and which are high voltage.
  • List the codes of practice that apply to the site, such as NZECP 34 and NZECP 35.
  • Confirm who certifies and who inspects each part of the work.
  • For generation, read the distributor’s connection standard for the inverter standards it expects.

Who does what in New Zealand

Design responsibility rests with the designer under regulation 14. Electrical work is done by licensed electrical workers registered with the Electrical Workers Registration Board (EWRB). Engineering design is reviewed and signed by a Chartered Professional Engineer (CPEng, registered with Engineering New Zealand).

From the Wiring Rules to a design ready for your engineer

Tiza does not sign or certify designs in New Zealand. We deliver engineering design that states the edition used, the modifications applied and the calculations. It is ready for your CPEng to review and sign, and for licensed electrical workers to build. Contact us with the scope of the installation and the date construction will start.

Frequently asked questions

Which edition of AS/NZS 3000 applies in New Zealand now?

AS/NZS 3000:2018 including Amendments 1, 2 and 3, as cited in Schedule 2 of the Electricity (Safety) Regulations 2010 with New Zealand modifications. New installations where construction begins after 12 November 2026 must comply with it.

Can work started under the 2007 edition continue?

WorkSafe says work begun before 13 November 2025 under the old edition can continue to completion. Work started after that date under the old edition must be finished by 12 November 2026, and the rest then follows the new edition.

Is AS/NZS 3000 the only document that applies?

No. WorkSafe issues electrical codes of practice under the Electricity Act 1992, such as NZECP 34 on safe distances and NZECP 35 on power systems earthing, and the regulations add duties on design, certification and inspection.

WhatsApp