NZECP 34:2001, the New Zealand Electrical Code of Practice for Electrical Safe Distances, is issued by WorkSafe under the Electricity Act 1992. It sets minimum distances to protect people, property, vehicles and mobile plant near electric lines. The Electricity (Safety) Regulations 2010 require work near lines to keep to it, and a building consent does not replace it. Where a job must get closer, the line owner issues a close approach consent.
Short answer: NZECP 34 electrical safe distances
NZECP 34:2001 is the New Zealand Electrical Code of Practice for Electrical Safe Distances. It is issued under the Electricity Act 1992, published by WorkSafe, and it replaced the 1993 edition. Its minimum distances protect people, property, vehicles and mobile plant near electric lines. Under the Electricity (Safety) Regulations 2010, a person who carries out construction, building or excavation on or near an electric line must keep the distances the code sets.
WorkSafe lists the 2001 edition as current. The code is free to read on the WorkSafe website. Read the distances in the code itself, because they depend on the line voltage and on what is approaching the line.
Figure: overhead line, crane boom and required clearance envelope on a solar site.
The code is one of several documents beside the Wiring Rules. The AS/NZS 3000 guide for New Zealand shows how the codes of practice fit with the regulations, and the guide on NZECP 35 earthing covers the companion code for earthing. The grid codes guide gives the wider picture.
What the code covers
NZECP 34 sets minimum safe electrical distances for overhead lines and for other works linked to supplying electricity from generating stations to end users. It deals with people and tools working near lines, scaffolding, mobile plant, digging near poles and towers, and construction near poles and towers. Mobile plant has its own section.
Three points matter to a project team:
- It binds the person doing the work. The contractor with a crane or an excavator near a line carries the duty, but the designer decides where the plant, the laydown area and the access roads will be.
- It is separate from consents. A building consent or a resource consent does not mean the work complies.
- It is checked at inspection. WorkSafe says the inspection of high-voltage installation work must verify compliance with NZECP 34 as well as several regulations.
Close approach consent
Where work cannot keep the distances, the owner of the line may allow it under a close approach consent. The terms come from the line owner. One distributor describes the arrangement like this:
- Consent is required to work within 4 m of overhead lines, to excavate within 5 m of a power pole or 12 m of a tower or pylon, or to work closer than the code allows.
- It is written permission with site information, the details of the works and special working conditions.
- It is valid for 28 days or less and is issued to the site supervisor, who must brief everyone on site, including subcontractors and plant operators.
- Where conditions for a consent apply, no works start until it is issued.
Other line owners have their own forms, thresholds and durations. Ask the owner of each line that crosses or borders the site, including Transpower where a transmission line is involved.
Where it bites on a solar or storage site
- Cranes and telehandlers unloading transformers, containers and battery enclosures under or beside a line.
- Piling and trenching close to poles and towers.
- Laydown areas, access roads and fences laid out inside a line corridor.
- The connection works themselves, where a new line or cable meets an existing line.
- Construction scaffolds and temporary structures near conductors.
Put the line positions and the clearance envelope on the construction drawings, not only in the safety plan. Our guides on solar park engineering and design, lockout and tagout in solar plants and the overhead-to-underground transition cover related site planning.
Worked example: crane boom against a line
All numbers are illustrative. Take a crane with its pivot 1.8 m above the ground and a 16 m boom. An overhead conductor is 11 m above the ground and 8 m horizontally from the pivot. Assume the required minimum distance for this job is 4.0 m; the real value comes from the code’s tables for the line voltage and the type of plant.
- Place the pivot at (0, 1.8) and the conductor at (8, 11). The vector from pivot to conductor is (8, 9.2).
- At a boom angle of 70° from horizontal, the boom direction is (cos 70°, sin 70°) = (0.342, 0.940).
- The closest point on the boom lies at distance 8 × 0.342 + 9.2 × 0.940 = 11.38 m along the boom, which is inside its 16 m length.
- The perpendicular distance from conductor to boom is the square root of (8² + 9.2² − 11.38²) = 4.37 m.
At 70° the boom clears the assumed 4.0 m by 0.37 m. At 65° the same calculation gives 3.36 m, which is below 4.0 m. The distance equals 4.0 m at about 68.1°, so the boom must stay steeper than that, or the crane must move, or a consent is needed. This simplified view ignores slewing and boom deflection, so a real lift plan keeps a margin.
Checklist for the engineer
- Record the NZECP 34 edition used.
- Mark every overhead line, pole and tower within the site and its approaches on the drawings.
- Read the code’s distances for each line voltage and each type of plant.
- Place laydown areas, roads and fences outside the clearance envelope where possible.
- Ask each line owner for its close approach requirements before construction starts.
- Include the distances in the construction safety plan and the crane lift plans.
- Do not treat a building or resource consent as proof of compliance.
- Check the distances again at inspection of high-voltage work.
From the code to a layout ready for your engineer
Site layout near lines is part of the design, and design in New Zealand is reviewed and signed by a Chartered Professional Engineer (CPEng, registered with Engineering New Zealand). Tiza does not sign or certify designs in New Zealand. We deliver engineering design with the line corridors, clearance envelopes and construction constraints drawn, ready for your CPEng to review and sign. Contact us with the site plan and the line owners involved.
Frequently asked questions
What is NZECP 34?
It is the New Zealand Electrical Code of Practice for Electrical Safe Distances, edition 2001. It is issued under the Electricity Act 1992 and published by WorkSafe. Its minimum distances protect persons, property, vehicles and mobile plant from electrical hazards near overhead lines and other works.
Does a building consent mean I comply with NZECP 34?
No. Line owners state that an approved resource consent or building consent does not mean compliance with NZECP 34. Keeping the distances is a separate duty for whoever carries out the work.
What is a close approach consent?
It is written permission from the line owner to work closer to its equipment than the code allows. It records the site, the works and the special working conditions. Line owners limit how long it lasts and issue it to the site supervisor.