AS/NZS 4777.2:2020 requires inverters to include autonomous power quality response modes, mainly volt-watt and volt-var. Volt-watt reduces active power as voltage rises, and volt-var changes reactive power with voltage. The installer chooses a regional setting at commissioning, and the DNSP can specify the settings it requires. The modes limit voltage rise at the point of connection without a communications link.
When many rooftop inverters feed the same low-voltage line, the voltage at midday can climb past the network limit. The inverters themselves are one of the tools to contain it, through the AS/NZS 4777.2 response modes, volt-watt and volt-var, and the regional settings chosen at commissioning. For the installation side and the DNSP context, read the AS/NZS 4777 inverter grid connection guide; for the whole framework, the Australia electrical codes and grid connection guide.
Short answer: what do the AS/NZS 4777.2 response modes do?
AS/NZS 4777.2:2020, with Amendment 2:2024, sets the requirements for inverters connected to the grid. Among them are autonomous power quality response modes, which the inverter applies by itself based on the voltage at its terminals. Volt-watt reduces active power when the voltage rises. Volt-var absorbs reactive power when the voltage rises and supplies it when the voltage falls. Both are enabled by default, so voltage rise is limited without a communication link. Other modes, such as fixed power factor and fixed reactive power, are available when the network operator requires them.
Edition
The edition Standards Australia lists as current is AS/NZS 4777.2:2020 with Amendment 2:2024. The parameters used in a real project come from the standard, the inverter’s technical documentation and the DNSP.
How the modes work
Volt-watt. Below a starting voltage, the inverter delivers all the power available. Above it, the maximum output falls along a defined curve. It is a protective mode: it gives up energy to keep the local voltage within limits.
Volt-var. The inverter adjusts reactive power along a curve. At high voltage it absorbs reactive power, which lowers the voltage; at low voltage it supplies it. Reactive power uses part of the inverter’s current capacity, so it competes with active power.
Order of priority. When both modes act, the standard defines how the inverter shares its apparent power capacity between them. The inverter’s compliance documentation lists the behaviour.
Figure: volt-watt and volt-var curves, with voltage on the horizontal axis and inverter power on the vertical axis.
Regional settings
At commissioning, the installer selects the region setting for the site. The standard provides three Australian regions, A, B and C, for power systems of different size, from the large interconnected grid to isolated systems, and one for New Zealand. Each setting groups the protection limits and the response mode parameters suited to that kind of network. The DNSP states which one applies, and in some cases requires different values. Check the current DNSP document before commissioning; an inverter commissioned with the wrong region can be non-compliant even if it works.
Other requirements in Part 2
The standard also specifies the inverter’s protection functions and its behaviour during disturbances. It covers how the inverter detects loss of the grid, its limits on harmonic and DC injection, and the declarations the manufacturer must provide. Anti-islanding is covered in neutral voltage displacement and anti-islanding.
Worked example: volt-watt curtailment
These values are illustrative. The curve is assumed for the example and is not a region setting from the standard. Assume a 5 kW single-phase inverter with this volt-watt curve: full power up to 245 V, then a straight line down to 20% of rated power at 255 V.
- At 245 V or below, output is 100%: 5.0 kW.
- At 255 V, output is 20%: 1.0 kW.
- At 250 V, halfway along the slope, the fraction is 1 − 0.8 × (250 − 245) / (255 − 245) = 0.60. Output is 0.60 × 5 = 3.0 kW.
- If the line voltage at the connection is 250 V at midday, the inverter gives up 2.0 kW of its potential output.
The example shows the trade-off: a weak line causes curtailment, and every curtailed kilowatt-hour is energy the owner does not sell. A better cable or a transformer tap change at the source raises the voltage margin and reduces curtailment.
Voltage rise and the choice of mode
Volt-watt works on active power, the quantity that drives most of the voltage rise on a resistive low-voltage line. Volt-var works on reactive power, which has more effect on lines with a higher reactance. In most low-voltage feeders the resistance dominates, so absorbing reactive power helps but curtailing active power helps more. Upgrading the customer’s own cable, or a tap change agreed with the DNSP, reduces curtailment. The comparison needs the line data, the inverter capacity and the voltage limits of the network.
What the engineer checks
- Which settings the DNSP requires and whether the inverter supports them.
- The line voltage at the connection with and without export, so curtailment can be estimated.
- The effect of reactive power on the inverter’s current and on the line voltage.
- Whether several inverters on the same feeder behave consistently.
- That the commissioning record states the region and the settings.
Checklist for the engineer
- Confirm that the inverter is certified to AS/NZS 4777.2:2020 and that the edition is accepted by the DNSP.
- Obtain the DNSP’s current technical requirements and the region setting it specifies.
- Estimate voltage rise and potential curtailment for the proposed capacity.
- Check the inverter’s apparent power capacity for the reactive power demanded.
- Define how settings are recorded and who may change them.
- Plan the commissioning tests for the response modes.
- Keep the manufacturer’s compliance documentation with the project records.
Legal frame
In Queensland, professional engineering services must be provided by or under the direct supervision of a Registered Professional Engineer of Queensland (RPEQ). Other states and territories set their own rules for engineering responsibility.
How Tiza can help
If your project needs voltage rise and curtailment calculations and a settings schedule checked against the DNSP requirements, Tiza prepares the engineering design and power system studies remotely and in English. Tiza does not stamp, sign or certify; we deliver the calculations ready for your RPEQ in Queensland, or your chartered engineer elsewhere, to review and certify. Contact us with the inverter model, the line data and the DNSP requirements.
Frequently asked questions
What are the AS/NZS 4777.2 power quality response modes?
They are behaviours the inverter performs on its own according to the voltage at its terminals. The main ones are volt-watt, which reduces output power at high voltage, and volt-var, which absorbs or supplies reactive power with voltage. Other modes, such as fixed power factor, are available when the network operator requires them.
What is a regional setting?
A pre-set group of grid protection and response parameters that the installer selects at commissioning. The standard defines three Australian regions, A, B and C, for power systems of different size, and one for New Zealand. The network operator confirms which one applies to a connection.
Can the settings be changed after installation?
Settings may be changed within the limits the standard and the network operator allow, normally by an authorised person using the inverter's tools. Changes should be recorded, and the network operator should be informed when the connection agreement depends on them.