AS/NZS 5033 PV Array Wiring Rules Explained

AS/NZS 5033 PV array wiring rules explained: what the 2021 edition covers, where it meets AS/NZS 4777.1 at the inverter, with a string voltage example.

By Shadai García, CEO and protection engineer at Tiza Group.

string 1string 2string 3string 414 modules per stringcombinerDC isolationAS/NZS 5033AS/NZS 4777.1input terminals=~inverterAC sidestring of 14 modules, coldest cell 0 °Cmodule: 41.5 × 1.0675 = 44.30 Vstring: 14 × 44.30 = 620.2 Vfour strings: reverse current 34.5 Aabove the 20 A module limit: protectfewer strings: 23.0 A, then 11.5 Astring voltage at 0 °C, V620.2 V1000 V inverterat −5 °C: 628.1 Vfault in one string: the others feed it4 strings: 3 × 11.5 = 34.5 A20 A assumed limit3 strings: 2 × 11.5 = 23.0 A2 strings: 11.5 Aillustrative values; the standard fixes method and marginsArrayModulesFusesCombinerIsolationInverter© tizagrp.comstring 1string 2string 3string 414 modules per stringcombinerDC isolationAS/NZS 5033AS/NZS 4777.1input terminals=~inverterAC sidestring of 14 modules, coldest cell 0 °Cmodule: 41.5 × 1.0675 = 44.30 Vstring: 14 × 44.30 = 620.2 Vfour strings: reverse current 34.5 Aabove the 20 A module limit: protectfewer strings: 23.0 A, then 11.5 Astring voltage at 0 °C, V620.2 V1000 V inverterat −5 °C: 628.1 Vfault in one string: the others feed it4 strings: 3 × 11.5 = 34.5 A20 A assumed limit3 strings: 2 × 11.5 = 23.0 A2 strings: 11.5 Aillustrative values; the standard fixes method and marginsArrayModulesFusesCombinerIsolationInverter© tizagrp.com
Single-line diagram of a PV array under AS/NZS 5033: four strings of 14 modules, each with its string fuse, joined in a combiner, then DC isolation up to the inverter input terminals where AS/NZS 5033 ends and AS/NZS 4777.1 begins, with the worked example: string voltage 620.2 V at 0 °C against a 1000 V inverter limit, and a fault in one string fed by the others with 34.5 A for four strings, 23.0 A for three and 11.5 A for two against an assumed 20 A module limit. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

AS/NZS 5033:2021 sets the installation and safety requirements for photovoltaic arrays in Australia, from the modules to the inverter input terminals. The 2021 edition changed how DC isolation is arranged compared with earlier editions. It sits next to AS/NZS 3000 and 4777.1, and a cold-temperature string voltage and reverse current example shows the first checks.

AS/NZS 5033 is the standard that decides how a photovoltaic array is wired, protected and isolated in Australia and New Zealand. It sits between the modules and the inverter, so it is the document an installer, an inspector and a designer all have open at the same time. For the whole framework see the Australia electrical codes and grid connection guide.

Short answer: what are the AS/NZS 5033 PV array wiring rules?

AS/NZS 5033 sets the installation and safety requirements for photovoltaic arrays. It covers the voltage and current the array can reach, array wiring, DC protection and isolation, earthing and bonding, and the labelling of DC equipment. Its scope ends at the inverter input terminals. From there, AS/NZS 4777.1 governs the inverter energy system, and AS/NZS 3000 governs the AC wiring.

Editions

AS/NZS 5033:2021 is the current edition. It replaced the 2014 edition and its amendment. State regulators adopt editions on their own dates and may allow a transition period, so confirm what applies where the project sits. A design that was based on the 2014 edition needs a recheck, particularly for the DC isolation arrangements, which changed in the 2021 edition. If a newer edition appears in the Standards Australia catalogue, that edition prevails.

Where the standard sits

Each standard needs the others to be read together. The array voltage chosen under AS/NZS 5033 limits the inverter you can select, and the inverter’s isolation point is shared between the two standards.

The design points that matter first

  1. Maximum array voltage. It is set by the cold-weather open-circuit voltage of a string, and it decides the cable and equipment ratings. The method is explained in PV string sizing at minimum temperature.
  2. Fault current in the array. Parallel strings can feed a fault in one string. This decides whether string protection is needed.
  3. DC isolation. The array must be isolatable, and the 2021 edition changed where and how this isolation is arranged compared with earlier editions. For many rooftop systems the rooftop DC isolator is no longer mandatory, and a disconnection point brings its own rules for cable routes, labels and records.
  4. Earthing and bonding. Frames and metalwork are bonded, and the array wiring is protected against lightning-induced and fault voltages. See grounding of a solar plant and its stations.
  5. Wiring system. Cable type, routes and protection against damage on the roof or in the field. See PV conductor sizing and raceways.
  6. Labelling. DC equipment and cables carry labels so that an emergency responder can see where DC circuits run.

Fuses and DC disconnects are explained in gPV fuses and DC disconnects in solar systems, and the combiner is covered in string combiner box parts and functions.

Figure: single-line diagram of a PV array with strings, a combiner, DC isolation and the inverter input terminals, with the boundary between AS/NZS 5033 and AS/NZS 4777.1.

Worked example: string voltage and string fault current

These values are illustrative. Always use the real data sheet values.

A module has an open-circuit voltage of 41.5 V at 25 °C, a short-circuit current of 11.5 A and a voltage temperature coefficient of −0.27 % per °C. A string has 14 modules. The site’s lowest expected cell temperature is 0 °C. The inverter accepts up to 1000 V DC.

  1. Temperature difference: 25 − 0 = 25 °C below the reference.
  2. Voltage factor: 1 + 0.0027 × 25 = 1.0675.
  3. Module voltage at 0 °C: 41.5 × 1.0675 = 44.30 V.
  4. String voltage: 14 × 44.30 = 620.2 V, well below 1000 V. At −5 °C the string would be 628.1 V.
  5. A design could add modules while staying under the inverter limit, but the more important check is the maximum voltage for the cables, isolators and fuses selected.

Now the string current. With four strings in parallel, a fault in one string can receive the current of the other three:

  1. Reverse current: 3 × 11.5 A = 34.5 A.
  2. If the module data sheet allows a maximum reverse current of 20 A, 34.5 A exceeds it, so string protection is needed. With three strings the figure would be 2 × 11.5 = 23.0 A, still above 20 A. With two strings it would be 11.5 A, below the limit.

The standard defines the exact method and any margins, so the example shows the order of the checks, not the final values.

Checklist for the engineer

  • Confirm the edition required by the state regulator and the network operator.
  • Calculate maximum string voltage with the cold temperature of the site.
  • Check string reverse current against the module rating and decide on protection.
  • Define the DC isolation arrangement and match it to the inverter selected.
  • Check earthing and bonding of frames and the array wiring.
  • Prepare the labelling schedule and the array layout.
  • Coordinate the inverter terminals with AS/NZS 4777.1 and the AC side with AS/NZS 3000.

Small arrays are installed by licensed installers under state electrical safety rules. Larger systems carry an engineering design: in Queensland, professional engineering services must be provided by or under the direct supervision of an RPEQ, and Victoria has required registration for electrical engineers since 2023. Other states and territories set their own rules. Tiza delivers engineering and studies ready for your RPEQ in Queensland, or the registered or chartered engineer your state requires, to review and certify. Tiza does not stamp, sign or certify.

How Tiza can help

If your project needs the engineering design for a PV array, Tiza prepares the string sizing, the DC protection concept and the single-line diagrams remotely and in English. Contact us with the module data, the layout and the connection requirements.

Frequently asked questions

What does AS/NZS 5033 cover?

It covers the installation and safety of photovoltaic arrays: modules, array wiring, DC protection and isolation, earthing and bonding, and the labelling of the DC side. Its scope ends at the inverter input terminals, where AS/NZS 4777.1 takes over for inverter energy systems.

Which edition of AS/NZS 5033 is current?

AS/NZS 5033:2021 is the current edition, and it replaced the 2014 edition with its amendment. State regulators set their own adoption dates, so confirm the edition that is mandatory where the project sits.

Does an array design need an engineer's certification?

Small rooftop arrays are installed and recorded by licensed installers. Larger or complex arrays usually carry an engineering design, which the responsible engineer reviews and certifies: an RPEQ in Queensland or a registered or chartered engineer elsewhere. Tiza prepares the design but does not certify.