AS/NZS 61439 is the Australian and New Zealand adoption of the IEC 61439 series for low-voltage switchgear and controlgear assemblies. It replaced the older AS/NZS 3439 series, and Parts 1 and 2 have 2026 editions based on the IEC 2020 texts. For a switchboard in Australia the questions that matter are which part applies, whether the assembly manufacturer holds a design verification, which form of separation was agreed, and whether the rated fault withstand covers the prospective fault current at the board.
A switchboard installed in Australia is expected to follow AS/NZS 61439, the local adoption of the IEC 61439 series. The questions that decide a project are practical: which part applies, who holds the design verification, which form of separation was agreed and whether the board withstands the fault current at its location. For the international reading of the series, see IEC 61439-1: general rules for low-voltage assemblies. For the Australian framework around it, see the Australia electrical codes and grid connection guide.
Short answer: what does AS/NZS 61439 require of a switchboard?
AS/NZS 61439 requires that a low-voltage assembly, up to 1,000 V a.c. or 1,500 V d.c., be built to a design that has been verified, and that each unit built from it passes routine verification before it leaves the factory. Part 1 holds the general rules. Part 2 covers power switchgear and controlgear assemblies, and Part 3 covers distribution boards that ordinary persons operate. The series first appeared in 2016, replacing the AS/NZS 3439 series. The Wiring Rules, AS/NZS 3000, and the state electrical safety regulators decide where compliance is expected on an installation.
Edition
Standards Australia lists AS/NZS 61439.1:2026 and AS/NZS 61439.2:2026 as current. They were published in February 2026 as modified adoptions of IEC 61439-1:2020 and IEC 61439-2:2020, and they supersede the 2016 editions. New Zealand may still list the 2016 editions, and the state regulator may accept a transition period, so confirm the edition named in the contract.
The IEC method is covered in the guides on design verification of a switchboard, routine verification and the original manufacturer and the assembly manufacturer. The Australian view adds who the parties are, what the specifier must settle, and how to read the evidence.
The parties and where the evidence sits
The standard describes a chain. The original manufacturer designs and verifies the assembly system. The assembly manufacturer builds the actual board from that system, adds its own design changes and completes the routine verification. In Australia the assembly manufacturer is usually the switchboard builder, and it is the party that stands behind the finished board.
In practice, the switchboard builder compiles the design verification for the finished assembly, whatever equipment is inside the enclosure. A compliance letter from a component maker is not a substitute.
Design verification: three routes
Part 1 allows three routes to verify a design characteristic:
- Testing. The assembly or a representative arrangement is tested.
- Comparison with a tested reference design. A variant is shown to be equal or better than a design that has already passed tests, within the limits the standard sets.
- Assessment. Rules, calculations or design checks are applied where the standard allows them. Their scope is limited, and the standard restricts assessment for some characteristics.
The standard lists the characteristics to verify in an annex. They include temperature rise, short-circuit withstand, dielectric properties, protective circuit continuity, clearances and creepage, and mechanical operation. Ask the builder for the verification record for each characteristic and for the version of the reference design that the record refers to. When one component is substituted for another, the substitution must stay within the conditions in the standard.
Forms of separation
A form of separation describes how busbars, functional units and terminals are divided inside the enclosure. Forms 1 to 4 run from no internal separation to separation of every functional unit and its terminals. Higher forms keep a person working on one unit further from live parts of the others.
The form of separation is an electrical characteristic chosen by agreement between the specifier and the assembly manufacturer, and that the materials that make up the separation are still subject to verification. AS/NZS 3000 refers to the choice for larger boards, so check the clause that applies to the board’s current rating. Two consequences follow:
- Cost and size. Each step up needs more partitions and more space, so the form belongs in the first specification, not in the last review.
- Maintenance practice. If the owner expects to work on one outgoing unit while the board stays energised, the form must support that. See AS/NZS 4836 live work on low-voltage installations for the work-practice side.
Worked example: fault withstand against the prospective fault current
This example is illustrative. Assume a 1,000 kVA transformer at 415 V with 5% impedance and an infinite source on the primary.
- Full-load current at the secondary: 1,000 ÷ (√3 × 0.415) = 1,391 A.
- Prospective fault current at the main busbars: 1,391 ÷ 0.05 = 27.8 kA.
- The board’s rated short-time withstand current is 35 kA for 1 s. That is above 27.8 kA, so the first condition is met.
- As a screening check on thermal stress, 35² × 1 = 1,225 kA²s is available. With the incoming device clearing in 0.3 s, the fault gives 27.8² × 0.3 = 232 kA²s, well inside the rated value.
The conclusion is a screening result only. The verification record, the device characteristics and the peak current factor decide the real outcome, and the study that produced 27.8 kA should be kept with the board documents. For the study side, see the short-circuit test of a switchboard.
Figure: single-line view of a transformer, main switchboard and outgoing feeders, showing the prospective fault current and the rated short-time withstand at the main busbars.
Checklist for the engineer
- Confirm which part applies: Part 2 for power switchgear, Part 3 for boards operated by ordinary persons.
- Obtain the design verification record from the assembly manufacturer, not only a compliance letter.
- Compare the rated short-time withstand and short-circuit rating with the study at the board.
- State the form of separation in the specification and why.
- Check the verified temperature rise against the site ambient and the enclosure location. See temperature-rise limits.
- Ask for the routine verification record of the delivered unit.
- Check any change made after the original verification, such as a component swap, against the standard’s conditions.
- Check the state regulator for any local requirement on switchboard documentation.
Related guides
For the wiring side, see AS/NZS 3000 wiring rules explained and AS/NZS 3000 RCD requirements and overcurrent protection. For testing the finished board on site, see AS/NZS 3017 verification by inspection and testing. For the United States view of the same equipment, see NEC Article 408 switchboards and panelboards.
Who certifies
Electrical design and certification follow state rules. In Queensland, professional engineering services must be provided by, or under the direct supervision of, a Registered Professional Engineer of Queensland (RPEQ). Victoria has required registration for electrical engineers since 2023, and other states set their own rules. Tiza does not stamp, sign or certify any of this.
How Tiza can help
If your project needs an independent review of a switchboard design, Tiza reads the verification record, the fault study and the single-line diagram against the specification. Tiza delivers engineering ready for your RPEQ in Queensland, or the registered or chartered engineer your state requires, to review and certify. Contact us with the specification and the vendor documents.
Frequently asked questions
What is the difference between AS/NZS 61439 and IEC 61439?
AS/NZS 61439 is the joint Australian and New Zealand adoption of the IEC series. The technical structure is the same: general rules in Part 1 and product parts from Part 2. The Australian documents add the national front matter, and the Wiring Rules AS/NZS 3000 decide where an assembly must comply.
Who is responsible for design verification of a switchboard?
The assembly manufacturer, meaning the switchboard builder, holds the design verification for the assembly it completes. The verification can rest on tests, on comparison with a tested reference design, or on assessment where the standard allows it. The specifier should ask to see the evidence, not only a compliance letter.
Does the form of separation have to be written in the specification?
Yes. Forms 1 to 4 are chosen by agreement between the specifier and the assembly manufacturer, and they change cost and maintenance access. If the specification is silent, the builder chooses, and the result may not allow the live-work or isolation practice the owner expects.