Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

AS/NZS 3017: Verifying an Electrical Installation

AS/NZS 3017 test and verify guide: how inspection and testing prove an installation meets AS/NZS 3000, with an earth fault loop example and checklist.

By Shadai García, CEO and protection engineer at Tiza Group.

switchboardsupplyMCB 20 A type Csocketoutletearth barMEN linkneutral barPE conductorearth fault at the socketcurrent returns through PE and the MEN linkbreaker trips: circuit deadactive / neutralearth (PE)20 A type C: assumed to trip at 10 × 20 = 200 Alimit: 230 V ÷ 200 A = 1.15 Ω1.15 Ωmeasured at the far end: 0.86 Ω0.86 ÷ 1.15 = 75 % of the limit:the breaker trips instantly with marginscreening figure only: apply the standard'sown limits and temperature correctionFault loopActiveFaultEarth (PE)MEN linkSource© tizagrp.comswitchboardsupplyMCB 20 A type Csocketoutletearth barMEN linkneutral barPE conductorearth fault at the socketcurrent returns through PE and the MEN linkbreaker trips: circuit deadactive / neutralearth (PE)20 A type C: assumed to trip at 10 × 20 = 200 Alimit: 230 V ÷ 200 A = 1.15 Ω1.15 Ωmeasured at the far end: 0.86 Ω0.86 ÷ 1.15 = 75 % of the limit:the breaker trips instantly with marginscreening figure only: apply the standard'sown limits and temperature correctionFault loopActiveFaultEarth (PE)MEN linkSource© tizagrp.com
AS/NZS 3017 earth fault loop: the path from the active conductor through the fault, the earth conductor and the MEN link back to the source, with 0.86 Ω measured against 1.15 Ω. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

AS/NZS 3017:2022, titled Electrical installations: verification by inspection and testing, sets out the inspection and test methods that show a low-voltage installation meets the safety requirements of AS/NZS 3000 for fire prevention and protection against electric shock. It supersedes the 2007 edition. The tests prove what the design assumed: continuity, insulation, earth fault loop impedance, polarity and the operation of protective devices.

An installation that looks right can still be wrong inside. AS/NZS 3017 is the standard that turns the Wiring Rules into a set of inspections and tests, so that the claim “this installation complies with AS/NZS 3000” has evidence behind it. The verification works in two parts, and its records stay on file. For the Australian framework around it, see the Australia electrical codes and grid connection guide.

Short answer: what does AS/NZS 3017 verify?

AS/NZS 3017:2022 covers the inspection and test methods that show a low-voltage installation meets the safety requirements for fire prevention and protection against electric shock. In practice the verifier inspects that the installation matches the design and the regulations, then tests continuity of protective conductors, insulation resistance, polarity, earth fault loop impedance and the operation of residual current devices. Each result is compared with the requirement in AS/NZS 3000, and the record is kept.

Edition and scope

The current edition is AS/NZS 3017:2022, published in December 2022. It is the fourth edition and supersedes the 2007 edition, which was titled “Verification guidelines”. A separate standard, AS/NZS 3019, deals with periodic verification of installations already in service. State electrical safety regulators decide which editions apply and what must be lodged after the work.

Inspection first, then testing

Verification has two parts that work together.

Inspection. The verifier checks that the work matches the design and the rules before any instrument is used. Typical items are conductor sizes and colours, protective devices fitted as designed, correct connection of earthing and bonding, labelling, and the physical condition and fixing of equipment.

Testing. Instruments measure what the eye cannot see. The usual tests are:

  • Continuity of the earthing and bonding conductors, which proves the protective path is complete.
  • Insulation resistance, which shows that conductors are not leaking to earth or to each other.
  • Polarity, which proves that devices are in the correct conductor.
  • Earth fault loop impedance, which shows that a fault will draw enough current for the protective device to operate in the required time.
  • Operation of residual current devices, which proves they trip at their rated sensitivity and within their time.

The order is part of the method. Tests that rely on a sound installation, such as live measurements, are done after the dead tests that prove it is safe to energise. See AS/NZS 3000 RCD requirements and overcurrent protection for the devices being tested and AS/NZS 3000 main earthing and MEN systems for the earthing that the continuity test proves.

Where it connects to commissioning

For a solar or storage project, verification of the installation is one part of the commissioning evidence. It sits beside the inverter and protection tests that the network operator asks for. The Spanish-language guides on commissioning of switchboards and on insulation resistance in photovoltaic generators show the same ideas from another angle. For the United States view of commissioning tests, see IEEE 1547 commissioning tests and verification.

Worked example: does the earth fault loop allow the breaker to trip?

This example is illustrative and uses simple assumptions. A final circuit is protected by a 20 A type C miniature circuit breaker. For the instantaneous trip we assume a conservative upper limit of 10 times the rating, so the breaker is certain to trip magnetically at 200 A.

  1. The nominal phase-to-earth voltage is 230 V.
  2. The loop impedance that lets 200 A flow in a bolted earth fault is 230 ÷ 200 = 1.15 Ω.
  3. The verifier measures 0.86 Ω at the far end of the circuit.
  4. The measured value is 0.86 ÷ 1.15 = 75% of the limit, so the breaker would trip instantly with margin.

Two cautions apply in a real verification. The standard gives its own maximum values and its own correction for the temperature at which the cable was measured. A measurement taken on a cold circuit understates the impedance at operating temperature. Apply the standard’s values, not the screening figure in this example.

Figure: single-line view of a final circuit from the switchboard to a socket outlet, with the earth fault loop path marked through the protective conductor and the supply.

Checklist for the engineer

  • Quote AS/NZS 3017:2022 and the edition of AS/NZS 3000 that applies.
  • Check the design documents for the circuit data the verifier needs.
  • Plan the test sequence: dead tests first, live tests after.
  • Record each measurement with the instrument, the date and the person.
  • Compare each result with the limit in AS/NZS 3000 and note pass or fail.
  • Re-test any circuit that failed, and record the correction.
  • File the records with the as-built drawings, and keep them for the life of the installation.
  • Check what the state regulator requires to be lodged after the work.

For the switchboard that is being tested, see AS/NZS 61439 switchboards in Australia. For safe working while testing, see AS/NZS 4836 live work on low-voltage installations. For the design side, see AS/NZS 3000 wiring rules explained and AS/NZS 3008 cable selection and voltage drop.

Who certifies

The licensed electrician is responsible for the verification results under the state rules. Engineering design review is separate: in Queensland, professional engineering services must be provided by, or under the direct supervision of, an RPEQ, and other states set their own rules. Tiza does not stamp, sign or certify.

How Tiza can help

If your project needs the verification and commissioning test plan prepared, Tiza provides engineering design in English: the test sequence, the record sheets and the limits worked out against your design. Tiza delivers engineering ready for your RPEQ in Queensland, or the registered or chartered engineer your state requires, to review and certify. Contact us with the single-line diagram and the circuit schedule.

Frequently asked questions

What is the difference between AS/NZS 3000 and AS/NZS 3017?

AS/NZS 3000 sets what an installation must achieve, including the requirements to be verified. AS/NZS 3017 explains how to inspect and test the installation to show that it does. The designer works from the first; the person verifying works from both.

Does verification have to be done before energising?

Verification combines inspection and testing, and some tests are done with the installation de-energised while others need it energised. The sequence matters: tests that could be affected by a fault in the installation are done before power is applied. Follow the sequence in the standard and the instructions of the state regulator.

Who signs the test results?

The licensed electrician who carried out or supervised the verification is responsible for the results and the records. The state electrical safety regulator sets what certificate or notice must be lodged. Engineering sign-off on the design is a separate step that the engineer of record handles.

WhatsApp