AS/NZS 4836:2023 is the Australian and New Zealand standard for safe working on or near low-voltage and extra-low voltage electrical installations and equipment. It replaced the 2011 edition. It sets a minimum set of procedures for the hazards of electric shock, electrocution, arc flash and arc blast. The practical rule behind it is simple: isolate and test first, work live only where de-energising cannot reasonably be done, and design the installation so that safe isolation is possible.
Anyone who plans or does maintenance on an Australian low-voltage installation meets AS/NZS 4836 sooner or later. It is the standard for safe working on or near low-voltage and extra-low voltage electrical installations and equipment, and it sits behind the work method statements used on site. The wider framework of Australian codes is in the Australia electrical codes and grid connection guide.
Short answer: what does AS/NZS 4836 require?
AS/NZS 4836 sets a minimum set of procedures, safety requirements and recommendations to manage the hazards of electric shock, electrocution, arc flash and arc blast when working on or near low-voltage and extra-low voltage installations. In practice it asks for four things: a risk assessment before the task, isolation and proving dead as the normal method, controls for the exceptional case of live work, and competent people with suitable tools and personal protective equipment (PPE).
Edition and how it is applied
The current edition is AS/NZS 4836:2023, the third edition. It replaced AS/NZS 4836:2011. Regulators decide how the standard is used in each place. For example, the NSW Resources Regulator published a position paper in August 2024 on electrical work on or near energised equipment at mining operations. It cites AS/NZS 4836:2023 and states that convenience or business interruption does not justify live work. The Western Australian regulator publishes safe working guidelines for electrical workers. Read the one for the state in question.
The method in plain terms
Isolate first. The normal and expected way to work is to disconnect the supply, secure the isolation so that nobody can reconnect it, and prove the equipment dead with a tester that has itself been proved. A board with several sources needs every one of them considered: the incoming supply, a generator, a battery inverter, solar and any backfeed through control wiring.
Live work is the exception. Where de-energising creates a larger hazard or cannot reasonably be done, live work needs its own risk assessment, a written procedure, trained people and suitable barriers and PPE. The assessment starts with the question of whether the work can be done dead instead.
Arc hazards are part of the picture. The standard treats arc flash and arc blast as hazards in their own right, with PPE and safe work zones tied to them. This links to arc flash studies and the PPE categories for arc flash. See also arc flash and electrical safety regimes compared for the international view.
Competence matters. People must be trained for the task and the voltage, and the person in charge must be clearly identified.
What the designer controls
Safe working is partly decided on the drawing board. A designer who plans for isolation makes live work unnecessary:
- Fit isolation points that are accessible, lockable and clearly labelled, one for each source that can energise the board.
- Choose a form of separation that allows work on one outgoing unit with the others still live. See AS/NZS 61439 switchboards in Australia.
- Give the protection settings a maintenance mode that cuts the clearing time during work, where the system allows it.
- Provide test points and earthing points so that proving dead and applying earths does not need the panel to be opened further.
- Label the available fault level and the arc hazard so that the work planner can see it.
For a solar plant, the same ideas appear in lockout and tagout in solar plants.
Worked example: why clearing time matters
This example is illustrative. A switchboard outgoing is protected by a device that clears a fault in 0.5 s at normal settings. A maintenance-mode setting clears the same fault in 0.1 s. The arcing current is the same in both cases.
- For a given arcing current, the energy released in an arc grows in proportion to the duration.
- The ratio of durations is 0.5 ÷ 0.1 = 5.
- So the arc energy at the work position is about five times lower in maintenance mode, as a first estimate.
The exact figure comes from the arc flash study, because the arcing current and the arc behaviour also change with the configuration. The example shows why a design that can shorten the clearing time during work is worth specifying, and why the work plan should state which setting is active.
Figure: single-line view of a switchboard with the incoming supply, a generator, a battery inverter and a solar inverter, each with its own labelled isolation point, feeding one outgoing circuit being worked on.
Checklist for the engineer
- Identify every source that can energise the equipment, including generators, inverters, batteries and backfeeds.
- Provide a lockable and labelled isolation point for each source.
- Provide a way to prove dead and to apply earths.
- Record the available fault level and the arc hazard at the work position.
- Specify the form of separation that allows the intended work practice.
- State the maintenance-mode setting, if the protection has one, and how it is activated and restored.
- Write down when live work is justified and who may authorise it.
- Check the state regulator’s guidance and adopt the edition it expects.
Related guides
For the installation rules that sit beside this standard, see AS/NZS 3000 wiring rules explained and AS/NZS 3000 RCD requirements and overcurrent protection. For testing an installation before it is energised, see AS/NZS 3017 verification by inspection and testing. For the United States arc flash labelling rule, see NEC 110.16 arc flash labeling.
Who certifies
The safe working procedure is the employer’s responsibility under the state work health and safety law. For design and studies, engineering registration is a state matter: in Queensland, professional engineering services must be provided by, or under the direct supervision of, an RPEQ, and other states set their own rules. Tiza does not stamp, sign or certify.
How Tiza can help
If your project needs the arc flash study, the fault levels and the protection settings that support a safe work plan, Tiza prepares them remotely in English as engineering design and power-system studies. Tiza delivers engineering ready for your RPEQ in Queensland, or the registered or chartered engineer your state requires, to review and certify. Contact us with the single-line diagram and the protection data.
Frequently asked questions
Does AS/NZS 4836 allow live work?
The standard gives procedures for working on or near energised equipment, but it does not make live work the default. State work health and safety regulators expect de-energising wherever it can reasonably be done, and they treat live work as an exception that needs a documented risk assessment. Check the regulator for the state where the work happens.
Is AS/NZS 4836 only for electricians?
It applies to anyone working on or near low-voltage and extra-low voltage installations and equipment, which includes electrical workers, supervisors and the people who plan the work. Designers also have a role, because the installation has to allow safe isolation and testing.
What does the 2023 edition add compared with 2011?
The 2023 edition gives more weight to arc faults, with PPE and safe work zones tied to the arc hazard. The exact requirements are in the 2023 text.