ESB Networks Distribution Code and Microgeneration (NC6)

ESB Networks Distribution Code Version 8.0 and the NC6 microgeneration route: generator types, 6/11 kVA limits, I.S. EN 50549-1, plus a sizing example.

By Shadai García, CEO and protection engineer at Tiza Group.

ESB Networks LV networkWhsmart meterCustomer boardloads~=Inverter withintegratedinterface protectionPVbatteryPowerIntegrated protectioninverter current at 230 V per phase8 kVA, 3-phase: 11.6 A, under 16 A: micro12 kVA, 3-phase: 17.4 A, over 16 A: mini7 kVA, 1-phase: 30.4 A, over 25 A: minia small step in rating changes the route3-phase, 8 kVAlimit 16 A11.6 A3-phase, 12 kVAlimit 16 A17.4 Asingle phase, 7 kVAlimit 25 A30.4 Aillustrative; mini-generation up to 72 A per phaseMicroLV networkSmart meterBoardInverterIntegrated protection© tizagrp.comESB Networks LV networkWhsmart meterCustomer boardloads~=Inverter withintegratedinterface protectionPVbatteryPowerIntegrated protectioninverter current at 230 V per phase8 kVA, 3-phase: 11.6 A, under 16 A: micro12 kVA, 3-phase: 17.4 A, over 16 A: mini7 kVA, 1-phase: 30.4 A, over 25 A: minia small step in rating changes the route3-phase, 8 kVAlimit 16 A11.6 A3-phase, 12 kVAlimit 16 A17.4 Asingle phase, 7 kVAlimit 25 A30.4 Aillustrative; mini-generation up to 72 A per phaseMicroLV networkSmart meterBoardInverterIntegrated protection© tizagrp.com
Low-voltage single-line diagram of a microgeneration installation in Ireland: ESB Networks low-voltage network, smart meter, customer board with the loads, and an inverter with integrated interface protection fed by a PV array and a battery on its DC side; with the category check by inverter current per phase, 8 kVA three-phase at 11.6 A against the 16 A limit, 12 kVA three-phase at 17.4 A and 7 kVA single-phase at 30.4 A against the 25 A limit. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

The ESB Networks Distribution Code, Version 8.0 (February 2023, approved by the CRU), sets the rules for generators on the Irish distribution network and classifies them by registered capacity under the Requirements for Generators. Small installations on low voltage use a simpler route: microgeneration up to 25 A single phase or 16 A per phase three phase, notified on form NC6, and mini-generation up to 72 A per phase, which has its own conditions. The inverter capacity decides the category. Inverters must comply with I.S. EN 50549-1 with Irish protection settings.

Short answer: the ESB Networks Distribution Code and microgeneration

The ESB Networks Distribution Code is the rulebook for everyone connected to the Irish distribution network. The current version is Version 8.0 (February 2023), approved by the Commission for Regulation of Utilities (CRU). Small generation on low voltage follows a lighter route. Microgeneration is up to 25 A single phase (about 6 kVA) or 16 A per phase three phase (about 11 kVA). It is notified on form NC6 and must use inverters complying with I.S. EN 50549-1 with Irish settings.

For the national framework, see the Ireland and New Zealand grid codes guide. The Great Britain equivalent is in the UK Distribution Code and DNO connection offers.

What the Distribution Code contains

Version 8.0 is organised in parts. The general conditions (DGC) cover hierarchy, derogations and the Distribution Code Review Panel. The planning code (DPC) covers design standards and data. The connection conditions (DCC) hold the technical requirements, including DCC10 for generators in general and DCC11 for power park modules. The operating code (DOC) covers operations, and DOC12 describes the operational notification process that RfG mandates.

Version 8.0 incorporated modification proposals approved by the CRU in its letter of 22 February 2023. They include content for the demand connection code and operational notification for generators under the European Requirements for Generators (RfG).

Generator types. DCC10.1.6 classes RfG generation units by registered capacity in Table 6. Type A runs from 800 W up to 0.09 MW, Type B from 0.1 MW up to 4.9 MW, Type C from 5 MW up to 10 MW and Type D is above 10 MW. Anything connected at 110 kV or higher is Type D. The type decides which requirements apply, so confirm it before reading the technical clauses.

Frequency and rate of change. For power park modules, DCC11.3.1 requires continuous operation between 49.0 and 51.0 Hz. It also requires staying connected during a rate of change of frequency of up to plus or minus 1.0 Hz/s, measured as a rolling average over 500 ms. For generation units in general, DCC10.5.1(j) sets the same 1.0 Hz/s figure. How that interacts with loss of mains settings is covered in the ESB Networks protection guide.

The microgeneration route

ESB Networks publishes the conditions as a company standard, Conditions Governing the Connection and Operation of Micro-Generation (DTIS-230206-BRL, Version 6.1, status date 3 December 2021). In summary:

  • Scope. Installations in single customer premises, on the low voltage network, up to 25 A single phase or 16 A per phase three phase.
  • Inverter capacity decides. The inverter rating is used to set the category and the Maximum Export Capacity. A battery or several sources behind one inverter are therefore limited by that inverter.
  • Standard. I.S. EN 50549-1 replaced I.S. EN 50438, with the Irish interface protection settings in the conditions. A type test certificate goes with the application.
  • Notification. The NC6 form is submitted online or offline. ESB Networks describes the route as “inform and fit”, and no connection charge applies to installations in that range. The installation is done by a registered electrical contractor to the Safe Electric standards.
  • Smart meter. ESB Networks aims to fit one within four months of processing a valid NC6 form, where eligible.
  • Limits after 2023. Units rated above 25 A in the type test were accepted only until 31 May 2023, and only up to 28 A single phase. After that date they no longer qualify under NC6.

DOC12 of the Distribution Code states that, for microgeneration, the NC6 form is deemed an installation document in the operational notification process.

Above microgeneration: mini-generation

Inverter-connected installations above the micro limits, up to 72 A per phase (about 17 kVA single phase or 50 kVA three phase), are mini-generation. The ESB Networks standard for it (DOC-030221-GAP, Version 1.2, status date 30 June 2022) simplifies the process: type-tested equipment to I.S. EN 50549-1, no separate interface protection panel when the inverter protection is used, and witness testing on an audit basis. Export limiting schemes are available in that route. Larger or non-inverter generation falls under the conditions for connection at medium voltage (DTIS-250701-BDW).

Worked example: which category is the inverter?

These figures are illustrative. The category follows the inverter current at 230 V per phase.

  1. A three-phase hybrid inverter of 8 kVA. Current per phase = 8,000 ÷ (3 × 230) = 11.6 A. It is under 16 A, so it is microgeneration.
  2. A three-phase hybrid inverter of 12 kVA. Current per phase = 12,000 ÷ (3 × 230) = 17.4 A. It is over 16 A per phase, so it is mini-generation. The 72 A limit corresponds to about 49.7 kVA (3 × 72 × 230).
  3. A single-phase inverter of 7 kVA. Current = 7,000 ÷ 230 = 30.4 A. It is over 25 A, so it is mini-generation. The 25 A limit corresponds to 5.75 kVA.

The lesson is that a small step in inverter rating changes the process, the standard and the protection settings. Size the inverter and the battery with the category in mind, before ordering.

Checklist for the engineer

  • Quote the Distribution Code version (8.0, February 2023) and the conditions document and version used.
  • Work out the inverter current per phase and confirm the category.
  • Obtain the type test certificate for I.S. EN 50549-1 and check it shows the Irish settings.
  • Confirm that the generator type under DCC10.1.6 matches the registered capacity.
  • For mini-generation, confirm the export limiting arrangement, if any.
  • Keep the single line diagram and settings sheet with the design basis.

From the code to a design your engineer can sign

A small site still needs a consistent design: inverter choice, protection settings, cable sizing and the single line diagram. We prepare the engineering design and the settings plan for generation projects. Tiza does not sign, stamp or certify designs in Ireland. We deliver engineering ready for your Chartered Engineer (Engineers Ireland) to review and sign. The installation itself is done by a contractor registered with the Register of Electrical Contractors of Ireland (RECI). Contact us with the site data and the inverter model.

Related guides: UK G98 versus G99, Australia AS/NZS 4777, IEEE 1547, G99 and AS/NZS 4777 compared and the Ireland connection process.

Frequently asked questions

Which version of the ESB Networks Distribution Code applies?

Version 8.0, document DOC-270223-HQZ of February 2023, was approved by the Commission for Regulation of Utilities in a letter dated 22 February 2023. The ESB Networks website lists it as the current version, so quote the version number in each application.

What size is microgeneration in Ireland?

Up to 25 A single phase, about 6 kVA, or 16 A per phase three phase, about 11 kVA, in a demand installation on the low voltage network. The limit is applied to the inverter rating. Above it, up to 72 A per phase, the installation is mini-generation.

What standard must a microgeneration inverter meet?

I.S. EN 50549-1 with the specific Irish protection settings in the ESB Networks conditions document. A type test certificate showing compliance must go with the NC6 form.