Tiza Group

Home / Guides / Protection, control and communications

Recloser Installation: Design Checklist and Key Decisions

Design checklist for a recloser installation on a distribution line: site, structure, bypass, arresters, grounding, control cabinet, supply and testing.

By Shadai García, CEO and protection engineer at Tiza Group.

Short answer

Designing a recloser installation means settling five things: the site and structure, the mounting with its bypass and arresters, the grounding, the control cabinet with its auxiliary supply and the communications. The control and the operating levels are tested before energization, and the utility usually requires drawings and its own approval.

Short answer

Recloser installation design comes down to five items: the site and structure, the mounting with its bypass and arresters, the grounding, the control cabinet with its supply, and the communications. Then come commissioning tests and energization. The equipment standard is IEEE C37.60 / IEC 62271-111, for reclosers above 1 kV and up to 38 kV.

What a recloser is and how it works is in recloser; settings are in recloser settings.

Before selecting or installing

A recloser is chosen for the network it goes into, not from a catalog. The minimum data are:

  • Maximum system voltage: the equipment must have an equal or higher rated voltage.
  • Load current, with the expected growth.
  • Short-circuit current at the point, which the equipment must be able to interrupt.
  • Role in the network: feeder head, trunk, lateral or point of connection of a plant.
  • Altitude and environment, which may require insulation correction.
  • Settings from the coordination study, with the neighboring fuse or recloser. See recloser-fuse coordination.

If the point is on a third-party network, the utility reviews drawings and design. See drawing and design requirements for the utility and grid operators in Colombia.

Where it goes, by function

The location defines the design. The usual points of a distribution network are:

  • Feeder head, at the substation exit.
  • Trunk, to split a long circuit into sections.
  • Lateral tap, with a fuse downstream.
  • Point of connection of a solar plant or distributed generation.
  • Tie point between circuits, normally open.

At a plant’s point of connection, voltage, frequency and anti-islanding functions come in besides overcurrent, and the utility sets them in its requirements. Each location changes the current, the short-circuit level and the reclosing sequence set by the coordination study.

Design route

From selection to energization of a recloser
  1. Design engineer: Network data and coordination study. Short-circuit, load and settings
  2. Design engineer: Design and drawings. Structure, bypass, grounding, control
  3. Utility: Is the design approved? Yes: continue; No: back to step 2.
  4. Design engineer: Installation specification. Pole, tank, arresters, grounding, control cable
  5. Design engineer: Control and operating-level test plan. With no power on the tank
  6. Utility: Energization. With the unit closed and phase reading checked
  7. Design engineer: Report and handover. Settings, results and signals

What the design covers, part by part

PartWhat the design must settle
Structure or poleMechanical strength for the weight of the tank and cabinet, height and access
Disconnects and bypassAbility to remove the unit without interrupting the circuit
Surge arrestersProtection of the tank against overvoltages, on each side
GroundingTank, cabinet and arresters with their ground resistance
Control cableTank-to-cabinet connection, protected and with its connectors
Control cabinetProtection, control, battery, charger and local interface
Auxiliary supplyOwn supply from the line or from a voltage transformer, and battery
CommunicationsLink to the control center, with the utility’s protocol

Worked example: is the rated current enough?

A recloser at the head of a 13.2 kV circuit feeding 12 MVA.

  1. Load current: I = S ÷ (√3 × V) = 12,000 kVA ÷ (1.732 × 13.2 kV) = 12,000 ÷ 22.86 = 525 A.
  2. With 15 % growth: 525 × 1.15 = 604 A.
  3. Rated current of 630 A: the margin is (630 − 604) ÷ 630 = 4 %. That is tight.

Conclusion: move to the next rated current offered in the data sheet, or split the circuit with a second recloser on the trunk. Then check the interrupting rating: with an 8.5 kA fault current at the site and a 12.5 kA unit, the margin is 12.5 ÷ 8.5 = 1.47. The interrupting rating must exceed the maximum expected fault, with the margin the design sets.

Catalog values change by equipment and voltage: always take them from the data sheet of the unit to be used.

Tests before energization

The tank tests are done by personnel competent in medium-voltage switching; the control tests are done with no power on the line, with the control cable disconnected and a tank simulator. One check that avoids surprises is the phase reading: with a healthy line there should be no appreciable negative-sequence voltage. Detail on what is tested is in recloser commissioning tests and in primary and secondary injection.

Design checklist

  • Network data confirmed: voltage, load, short-circuit, altitude.
  • Settings from the coordination study received and backed up.
  • Drawings approved by the utility, where applicable.
  • Bypass with disconnect switches and a written operating procedure.
  • Arresters and grounding measured and recorded.
  • Auxiliary supply and battery tested.
  • Operating levels tested: pole, local and remote.
  • Signals verified point by point with the control center.
  • Report with settings, results and energization date.

How we help

We provide the design engineering of recloser installations, from the network data and the coordination study to the drawings, the test plan and the remote configuration of the control: contact us with your network data and we will propose a scope. See also remote configuration of reclosers.

References

  • IEEE C37.60 / IEC 62271-111, AC automatic circuit reclosers above 1 kV and up to 38 kV, 2012 edition. The current edition is IEC 62271-111:2019.
  • IEEE C37.104, Guide for automatic reclosing of circuit breakers for AC distribution and transmission lines.
  • Ministerio de Minas y Energía, RETIE (Resolution 40117 of 2024, amended by Resolution 40284 of 2026): grounding, safety distances and distribution networks.

Frequently asked questions

What must be defined before a recloser installation is designed?

The load current and the short-circuit current at the site, the maximum system voltage, the role in the network (feeder head, trunk, lateral or point of connection), the insulation level and altitude, and the settings from the coordination study. With those data the equipment is selected and the design closed.

What is the bypass of a recloser for?

It lets the recloser be taken out of service for maintenance or replacement without leaving the circuit de-energized. It is made with disconnect switches on each side of the unit and a bypass switch, and operated with the procedure and interlocking set by the utility.

Is utility approval needed?

In practice yes, when the recloser sits on the utility's network or connects a plant to it: the utility reviews drawings, protection and settings, and often attends energization. Each utility publishes its requirements; check them before the equipment is purchased.

WhatsApp