Recloser for an Industrial Yard Substation

How a regional utility specifies a recloser on the MV side of a customer substation of 500 kVA or more: transformer trip input, reclosing disabled.

By Shadai García, CEO and protection engineer at Tiza Group.

Short answer

For customer yard substations of 500 kVA or more, a utility design and construction standard (version 3, 2023) asks for a recloser with the specifications of its overhead network and three changes: the control receives the transformer protection trip, reclosing is disabled and no control-centre communication port is required.

What changes against a feeder recloser

On the customer side the recloser has the same ratings as the utility’s feeder units (800 A, 16 kA, BIL 110 or 170 kV), with three differences:

  1. The control has an input to receive the trip of the transformer’s own protections.
  2. The reclosing function is disabled.
  3. No communication port to the utility control centre is required.

The transformer carries four relays that must be wired to that input: over-temperature, sudden pressure, Buchholz (63) and low oil level.

Customer yard substationMV protection in the standard
Below 500 kVA at 13.8 kVFused cutouts
500 kVA or moreRecloser with feeder specifications
MV protection of a customer yard substation
  1. Customer: Installed capacity. kVA and voltage
  2. Customer: Confirm 500 kVA or more. Below that, fused cutouts
  3. Customer: Recloser with feeder specification. Same ratings
  4. Customer: Transformer trip input. Four transformer relays wired
  5. Customer: Reclosing disabled. No control-centre port
  6. Utility: Substation design reviewed

Worked example with assumed numbers

Assumptions, not from a real project: a 13.8 kV plant with 630 kVA and 400 kVA transformers.

  • Installed capacity: 630 + 400 = 1,030 kVA, above 500 kVA: a recloser applies.
  • Primary rated current: 1,030 / (1.732 x 13.8) = 43 A, far below 800 A. The recloser is chosen by the utility’s specification and the fault level of the point, not by the load.
  • With a single 400 kVA transformer the standard describes fused cutouts.

Settings and coordination with upstream protection come from the protection study of the project. For the general design of a service-entrance recloser see recloser at an industrial service entrance: design.

Closing

We design the protection coordination of the recloser your project requires and configure its control remotely. See remote configuration of protective relays and controls.

References

  • IEC 62271-111 / IEEE C37.60, automatic circuit reclosers up to 38 kV.

Frequently asked questions

From what size is a recloser required in the customer substation?

From 500 kVA of installed capacity in yard substations, according to the standard's clause 8.4.7. For smaller yard substations at 13.8 kV the standard describes fused cutouts.

Why is reclosing disabled?

The standard states it without giving the reason. The usual technical reason is that the recloser protects a customer transformer, not a line with temporary faults: an internal transformer fault does not clear itself and re-energizing it makes it worse.

Which transformer protections are expected?

Over-temperature, sudden pressure, Buchholz (63) and low oil level relays. Their trip reaches the recloser control through a dedicated input.