How LV electrical panel design works: input data, calculations, drawings, bill of materials and IEC 61439 verification, with a worked example of ratings.

By Shadai García, CEO and protection engineer at Tiza Group.

Short answer

Designing a panel means turning load and network data into documented decisions: voltage, rated current, short-circuit withstand, enclosure, devices, drawings and bill of materials. The result is verified against IEC 61439 before manufacture, and every decision must trace back to an input datum.

Panel design is a chain of decisions, each with a source datum. Knowing the whole chain tells you what is calculated, what is drawn and what is verified.

Short answer

Panel design starts from the network and load data, sets the rated characteristics of the assembly (voltage, current, short circuit, enclosure), selects the devices, produces the drawings and the bill of materials, and ends with the design verification required by IEC 61439. If an input changes, everything that depended on it must be reviewed.

Design route of a panel
  1. Client: Input data. Loads, network, site and requirements
  2. Designer: Current and short-circuit calculation. With the network study
  3. Designer: Selection of devices and enclosure. With the form of separation
  4. Designer: Temperature rise and short circuit verified? Yes: continue; No: back to step 3.
  5. Designer: Drawings and bill of materials. Single-line, control, front and terminals
  6. Client: Review and approval. Before manufacture

Input data

Annex C of IEC 61439-1 is a template that orders what the user gives the manufacturer; see data to specify a low-voltage switchboard. The inputs with most weight in design:

  • Network: voltage, frequency, earthing system and prospective short-circuit current, taken from a short-circuit study or from the transformer nameplate.
  • Loads: current, starting method and demand factor.
  • Site: indoor or outdoor, temperature, humidity, dust, corrosion and altitude. If it is outside the normal range, see panels in heat, altitude or aggressive environments.
  • Operation: who handles it, whether it needs remote control and how it will be extended.

What the design produces

DeliverableContentsWho uses it
Calculation reportCurrents, voltage drops, short circuit, selectivity, temperature riseReviewer and design verification
Single-line diagramPower scheme with devices and ratingsClient, network operator, contractor
Power and control drawingsWiring of each circuit and starterAssembler and commissioning
Front and layout drawingWhere each device goes in the enclosureManufacturer and maintenance
Terminal and wiring drawingOrigin and destination of each wireAssembly and testing
Bill of materialsEach device with reference and quantityPurchasing and traceability
Design verification recordHow each IEC 61439 requirement was verifiedAudit and client

The set is delivered as a traceable file: an auditor must be able to follow a device from the bill of materials to the drawing and the test.

Key decisions

Worked example: rated current of a main board

A 480 V main board fed by a 1,000 kVA transformer, with ten outgoing ways:

  • Four ways of 200 A and six of 100 A: the sum of rated currents is 4 × 200 + 6 × 100 = 1,400 A.
  • With a rated diversity factor of 0.7 (an assumed value for the example), the outgoing ways can be loaded at the same time up to 0.7 × 1,400 = 980 A.
  • Transformer current is 1,000 kVA / (√3 × 0.48 kV) = 1,203 A, and the incomer is protected at 1,250 A. The assumed load of 980 A sits below it, and the board is declared with an InA of 1,250 A.
  • The prospective short-circuit current, with 5.75% impedance (assumed) and ignoring the upstream network and motor contribution, is 1,203 / 0.0575 = 20.9 kA. The board is chosen with an Icw of 25 kA and the incomer with a breaking capacity of at least 25 kA. For 25 kA the factor n is 2.1 (clause 9.3.3 of IEC 61439-1), so Ipk must be at least 2.1 × 25 = 52.5 kA.

If the client later wants two more 200 A ways, the sum rises to 1,800 A and the assumed load to 1,260 A, which already exceeds the transformer: the extension forces a review of the source, not just the panel.

Design review checklist

  1. Every input datum is written down, with its source.
  2. InA, Icw, Ipk and voltages are consistent with the network.
  3. Selectivity and coordination were checked.
  4. A method for temperature-rise verification has been chosen.
  5. The enclosure has IP and IK ratings suited to the site.
  6. There is spare space and current for growth.
  7. Drawings agree with each other and with the bill of materials.
  8. The design verification is recorded.

What not to do

  • Do not design with the transformer rated current as if it were the short-circuit current.
  • Do not draw the single-line diagram before having the load list with starting methods.
  • Do not leave design verification until after manufacture: a failure then forces rework.
  • Do not change a device in the workshop without updating the drawing and the list.

How we help

Our engineering team prepares the calculation report, drawings and bill of materials of your panel, and the IEC 61439 verification package: see engineering design or contact us.

References

  • IEC 61439-1, edition 2020: rated characteristics (clause 5), design verification (clause 10), Annex C (user information).
  • IEC 61439-2, edition 2020: power switchgear and controlgear assemblies.
  • IEC TR 61439-0, Guidance to specifying assemblies, current edition.
  • IEC 60909, Short-circuit currents in three-phase AC systems.

Frequently asked questions

Which documents make up a panel design?

The calculation report, the single-line diagram, the power and control drawings, the front and equipment layout drawing, the terminal and wiring drawing, and the bill of materials. The IEC 61439 design verification record goes with them.

Who is responsible for the design of a panel?

It depends on who takes it on. IEC 61439 distinguishes the original manufacturer, who designs the system and verifies the design, from the assembly manufacturer, who builds it and performs routine verification. In a custom design both roles can fall to the same company.

What data does a designer need to start?

Voltage and earthing system, the prospective short-circuit current, the load list with starting method, the installation environment, altitude and temperature, and the requirements of the network operator or the client. Without that data the design rests on assumptions.