LV Switchboard Standards: What Applies and When

Which standards govern a low-voltage switchboard: the IEC 61439 part for each type, the installation code, and the product rules that apply by country.

By Shadai García, CEO and protection engineer at Tiza Group.

Short answer

A low-voltage switchboard answers to three layers of standards: the product rules of the country, the installation code, and the construction standard that says how the assembly is designed, verified and declared. In most markets that construction standard is the IEC 61439 series, with one part for each type of assembly, plus separate standards for the enclosure, internal arcing and machines.

A switchboard is covered by several standards at once, and each one answers a different question.

Short answer

Think of switchboard standards in three layers. The product rules of the country decide whether the assembly can be sold and used. The installation code (NEC Article 408 in North America) decides how it is installed and protected. The construction standard, usually the IEC 61439 series, decides how it is designed, verified and declared. Which part of the series applies depends on the type of assembly and on who operates it.

The IEC 61439 series: one part per type

Part 1 holds the general rules and does not work alone. Each type of assembly has its own part, and that is the one to cite in a specification. Part 1 explains the split in detail.

PartAssemblyWhen it applies
IEC TR 61439-0Guidance on specifying assembliesWhen preparing the specification
IEC 61439-2Power switchgear and controlgear assemblies (main boards, MCCs, transfer)Most industrial and commercial switchboards
IEC 61439-3Distribution boards for operation by ordinary personsBoards accessible in homes and shops
IEC 61439-4Assemblies for construction sitesTemporary works
IEC 61439-5Public distribution networksNetwork cabinets
IEC 61439-6Busbar trunking systemsPrefabricated feeders
IEC 61439-7Marinas, camping sites and vehicle chargingCharging stations

In a contract, cite each part with its edition: the current edition of parts 1 and 2 is 2020.

Which part of IEC 61439 applies?
  • Is it the electrical equipment of a machine?
    • Yes: IEC 60204-1 applies to the machine, and the board that feeds it follows its own part of IEC 61439
    • No: Who operates it?
      • Trained staff: IEC 61439-2, power assemblies
      • General public: IEC 61439-3, boards for ordinary persons
      • Site, network or charging: Parts 4, 5, 6 or 7, as the case may be

Standards that add to the series

  • Enclosure: the IP code of IEC 60529 for solids and water, and the IK code of IEC 62262 for impact.
  • Internal arcing: IEC TS 61641 gives the test method; incident energy is calculated with IEEE 1584 inside an arc flash study.
  • Devices: the IEC 60947 series covers breakers, contactors and starters. Their individual tests do not replace verification of the assembly.
  • North America: UL 891 for switchboards, UL 845 for motor control centers and UL 508A for industrial control panels.
  • Colombia: the RETIE regulation treats the board as a product and asks for a product certificate, adapting IEC 61439-1 and -2 among other standards.

Worked example: a 1,000 kVA board

A 1,000 kVA, 480 V transformer with 5.75% impedance (an assumed value for the example) feeds a main board:

  • Rated current: 1,000 kVA / (√3 × 0.48 kV) = 1,203 A. The board is specified with a rated current InA of 1,250 A or more.
  • Prospective short-circuit current, infinite source: 1,203 / 0.0575 = 20.9 kA, a conservative maximum.
  • Declared withstand: Icw equal to or greater than 20.9 kA, for the duration set by the protection coordination.
  • Peak: between 20 and 50 kA, clause 9.3.3 of IEC 61439-1 uses n = 2.1, so the prospective peak is 20.9 × 2.1 = 43.9 kA. The board must declare an Ipk at least that high.

With those four figures the standard already has something to verify. How they are calculated in a real project is in switchboard design.

Checklist for reviewing an offer

  1. It names the IEC 61439 part for the assembly type, not just «IEC 61439».
  2. It declares InA, Icw, Ipk and rated voltages consistent with your study.
  3. It states the IP and IK rating of the enclosure.
  4. It includes design verification and the routine verification record.
  5. It names the original manufacturer behind the design.
  6. If internal arc protection is required, it cites the test and its level.

What not to do

  • Do not copy «complies with IEC 61439» into a specification without part and edition.
  • Do not treat an assembly as verified because its breakers have their own certificate.
  • Do not substitute a standard from another country for the product rules of the country of use.
  • Do not change the devices of a verified assembly unless someone takes on the verification of that change.

How we help

If you need to define which standards to require in your project, our engineering team prepares the specification and reviews the offers: see engineering design or contact us.

References

  • IEC 61439-1 and -2, edition 2020; IEC 61439-3 to -7 and IEC TR 61439-0, current edition.
  • IEC 60947-6-1, IEC 60529, IEC 62262, IEC TS 61641 and IEC 60204-1.
  • UL 891, UL 845 and UL 508A.
  • NFPA 70 (NEC), Article 408.
  • IEEE 1584, Guide for performing arc-flash hazard calculations.

Frequently asked questions

Which standard applies to a low-voltage switchboard?

For assemblies up to 1,000 V AC or 1,500 V DC, the IEC 61439 series, using the part that matches the type of assembly. In North America the equivalent products are covered by UL 891 for switchboards and UL 845 for motor control centers. The installation is governed by the local electrical code.

Is it enough for a manufacturer to state compliance with IEC 61439?

No. Compliance is declared against a specific part of the series, the one for that type of assembly, and it is backed by design verification and routine verification. Some countries also require a product certificate on top of that.

Does the installation code replace IEC 61439?

No. They cover different things. The installation code, such as NEC Article 408, governs how the assembly is installed and protected. IEC 61439 governs how the assembly leaving the factory is designed, tested and declared.