Main Low-Voltage Switchboard: What It Is and What It Holds

The main low-voltage switchboard receives power from the transformer and distributes it. What it holds and how its incomer and fault ratings are sized.

By Shadai García, CEO and protection engineer at Tiza Group.

MT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.comMT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.com
LV switchboard and MCC: automatic transfer and forms of separation. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

The main low-voltage switchboard (MDB) receives power from the transformer or the service entrance and feeds sub-distribution boards, motor control centers and large loads. Its incomer, busbars and short-circuit withstand are set by the transformer current and the fault level at its busbars.

The main low-voltage switchboard (MDB) is the first board of an installation. It receives power from the distribution transformer or the service entrance and distributes it to sub-distribution boards, motor control centers and large loads. Everything downstream depends on its breakers, busbars and short-circuit withstand.

Short answer

A main low-voltage switchboard is the assembly of breakers and busbars where an installation’s power enters and from which the main circuits leave. It is designed from three inputs: the transformer current, the short-circuit current available at its busbars, and the site conditions (altitude, temperature, environment). IEC 61439-1 and IEC 61439-2 are the base standards. What all board types share is in the guide on types of electrical switchboards.

What sets it apart

Under IEC 61439, a main switchboard is a power switchgear and controlgear assembly (IEC 61439-2), operated by skilled or instructed persons, unlike the distribution boards for ordinary persons of IEC 61439-3. It is the main board because it holds the main protection of the installation and, where the earthing scheme uses one, the main bonding between neutral and earth, which is made only there.

What it contains

  • Incoming breaker, air or molded-case. Its breaking capacity and short-time withstand current (Icw) must cover a fault on the busbars. See low-voltage circuit breakers.
  • Main and distribution busbars on insulators, rated no lower than the projected load current or the maximum setting of the protection.
  • Outgoing breakers to sub-distribution boards, motor control centers, transfer and power factor correction.
  • Metering and signals: network analyzer, current transformers, trip alarms.
  • Surge protection where the design calls for it.
  • Earth bar connected to the grounding system.
  • Spare ways: room and busbar capacity to expand without replacing the board.

Ratings fixed at design

ItemWhere it is definedWhat it decides
Rated current of the assembly (InA)IEC 61439-1, 5.3.1Busbar and incomer size
Short-circuit ratings (Icw, Ipk, Icc)IEC 61439-1, 5.3.4 to 5.3.6Strength of busbars, supports and breakers
Rated diversity factor (RDF)IEC 61439-1, 5.4Simultaneous load the outgoing circuits accept
Form of internal separationIEC 61439-2, 8.101What can be worked on with the rest energized
IP and IK degreeIEC 61439-1, 8.2Where it can be installed
Service conditionsIEC 61439-1, 7.1 and 7.2Altitude and temperature correction

Related guides: rated current, Icw, Ipk and Icc and service conditions.

Worked example

An industrial building is fed by a 1,000 kVA transformer at 440 V. The transformer impedance is 5% (assumed for the example; read it from the nameplate).

  1. Rated current: 1,000 kVA / (√3 × 0.44 kV) = 1,312 A.
  2. Short-circuit current at the busbars, with an infinite source upstream: 1,312 A / 0.05 = 26.2 kA. With the real network it is somewhat lower.
  3. Peak value: Table 7 of IEC 61439-1 (clause 9.3.3) gives n = 2.1 between 20 and 50 kA, so Ipk = 26.2 × 2.1 = 55.1 kA.
  4. Incomer: the next available rating above 1,312 A, for example 1,600 A, with an Icw of at least 26.2 kA. The busbars must be declared for at least that Icw and Ipk.

At a site around 2,600 m above sea level, the 2,000 m limit of IEC 61439-1 is exceeded. Specify the correction of rated current and clearances in writing.

Specification checklist

  1. Transformer power, voltage and impedance, and whether there is a standby generator.
  2. Short-circuit current at the busbars, with its calculation source.
  3. Number and rating of outgoing ways, plus spare capacity.
  4. Altitude, temperature and environment of the electrical room.
  5. Form of separation and type of units (fixed or withdrawable).
  6. Whether transfer, metering or power factor correction sit in the same board.

What to avoid

  • Do not choose the incomer from the transformer current alone: short-circuit capacity matters as much as the rating.
  • Do not distribute circuits without checking selectivity between the incomer and the outgoing breakers. See selectivity in low voltage.
  • Do not leave the room without working clearance: the board must be openable and maintainable.

How we help

We prepare the engineering design of main low-voltage switchboards: single-line diagram, short-circuit and rating calculations, specification and drawings. See engineering design and studies or contact us.

References

  • IEC 61439-1:2020, general rules, clauses 5.3, 5.4, 7.1, 7.2 and 9.3.3.
  • IEC 61439-2:2020, power switchgear and controlgear assemblies, clause 8.101.
  • IEC 60947-2:2024, circuit-breakers.

Frequently asked questions

What is the difference between a main switchboard and a sub-distribution board?

The main switchboard is the first level: it receives from the transformer or the service entrance and feeds everything else. A sub-distribution board is fed from another board and serves a floor, a zone or a process, with a lower fault level.

Which standard covers a main low-voltage switchboard?

IEC 61439-1 and IEC 61439-2, which cover power switchgear and controlgear assemblies up to 1,000 V AC. The circuit breakers inside it are built to IEC 60947-2.

Why does altitude matter when specifying a main switchboard?

IEC 61439-1 treats altitudes up to 2,000 m as normal service. Above that, special service conditions apply and the rated currents and clearances need correction, which is common in high-altitude cities.