Tiza Group

Home / Guides / Equipment, switchboards and substations

Switchboards by Application: What Changes in the Design

What changes in an LV switchboard design by application: hospitals, buildings, pumping, mining, solar, EV charging and hazardous areas, with a guide.

By Shadai García, CEO and protection engineer at Tiza Group.

MT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.comMT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.com
LV switchboard and MCC: automatic transfer and forms of separation. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

A low-voltage switchboard is designed from its application: the use decides the continuity it must provide, the degree of protection, the type of loads, the backup source and the special rules that apply.

Short answer

Switchboards by application share the same product standard, IEC 61439, but the use decides four things: the continuity it must provide, the environment and degree of protection, the type of loads (motors, electronics, lighting) and the additional rules that apply to the place. With those four answers the specification is defined.

What is common to any switchboard design is in LV switchboard and MCC.

What changes with the use

UseWhat changes most in the switchboardWhere to go deeper
HospitalsDual source with transfer, backup within a set time, UPS for life support and IT system in operating roomsRETIE in hospital installations
BuildingsMany sub-panels, metering per unit, selectivity between levels and space in technical roomsAC station-service switchboard
Data centersRedundant supply, metering per circuit and maintenance without stopping the loadAutomatic source transfer
Water and pumpingMotor starting, drives, dry-run protection and standby unitsPumping with a drive
MiningDust, vibration and altitude; high mechanical protection and quick maintenanceMCC
Agro-industryHumidity, washdown and corrosion; irrigation and refrigeration motorsIP codes
Solar plantsDC and AC combined, protection and communicationsRETIE in PV installations
EV charging stationsResidual-current protection, surge protection and charger groundingProtection of a charging station
Oil, gas and hazardous areasEquipment certified for the zone and group, or the switchboard outside the areaHazardous areas under RETIE
Industry and manufacturingMix of motors, drives and automation; future growthSoft starter or drive

For the relevant codes by country, the references are the NEC (Article 517 for health care facilities, Articles 500 to 505 for hazardous locations, Article 625 for EV charging and Articles 690 and 705 for PV and interconnected sources) and the national equivalents.

A single switchboard rarely meets two different uses. A hospital switchboard incorporates transfer and insulation monitoring that a pumping switchboard does not need, and a pumping one carries starters and drives that a building switchboard may not have. That is why the specification names the use and not only the current.

How to choose the starting point

What drives the design of this switchboard?
  • Is there an explosive atmosphere from gases, vapors or dust?
    • Yes: Hazardous area: equipment certified for the zone, or the switchboard outside the area
    • No: Does the load require continuity of supply for safety of people or the process?
      • Yes: Dual source with transfer and backup; IT system if there are patients
      • No: Distribution switchboard or MCC according to the loads and environment

The answer does not replace the design: it defines the switchboard family. Details such as rated current and short-circuit rating come from the calculation and are written in data to specify an LV switchboard.

Worked example: three pumps, two running

A pumping station with three 55 kW motors at 440 V, two running and one standby. An efficiency of 0.93 and a power factor of 0.88 are assumed (example assumptions; use nameplate values).

  1. Current of each motor: I = P ÷ (√3 × V × η × cos φ) = 55,000 ÷ (1.732 × 440 × 0.93 × 0.88) = 55,000 ÷ 623.7 = 88 A.
  2. All three at once: 3 × 88 = 264 A.
  3. Normal operation, two pumps: 2 × 88 = 176 A.
  4. Outgoing circuit with a 100 A breaker: the rule in clause 5.4 of IEC 61439-1, RDF × rated current of the circuit ≥ assumed load, requires RDF ≥ 88 ÷ 100 = 0.88 on each outgoing circuit.

The difference between 264 A and 176 A is what changes the sizing of the busbars and the incomer. The specification must say that the third pump only replaces one, and must ask the manufacturer to confirm how the design verification handles that condition. If it is not declared, the switchboard is designed for the worst possible combination. See rated diversity factor (RDF).

What data the owner must give, by use

Without these data, the manufacturer fills the gaps with its own standard. The general template is in data to specify a switchboard; depending on the use, add:

UseData to add
HospitalsCritical areas, transfer time, life-support loads, earthing scheme
BuildingsNumber of units, metering scheme and technical rooms available
PumpingPower and number of pumps, how many run at once, type of starting
Mining and outdoorsAltitude, dust, temperature, vibration and access for maintenance
Hazardous areasClassification drawing with zone, group and temperature class
Solar and chargingDC voltages, number of inputs and utility requirements

At higher altitude, air loses cooling and insulating capacity; the guide on special service conditions of a switchboard explains how it is declared.

Application checklist

  • Use and environment described: indoor, outdoor, dust, humidity, altitude.
  • Continuity required: dual source, backup, transfer time.
  • Type of loads: motors, drives, sensitive electronics, lighting.
  • Special rules of the place: health care, hazardous area, solar, EV charging.
  • Suitable IP degree and impact resistance.
  • Simultaneous loads and diversity factor declared.
  • Room to grow and to maintain without stopping the process.

How we help

We provide the design engineering of switchboards for each application, from the single-line diagram and the ratings to the specification package: contact us with the use, the loads and the environment, and we will propose the design.

References

  • IEC 61439-1 and IEC 61439-2, low-voltage switchgear and controlgear assemblies; the rated diversity factor is covered in IEC 61439-1.
  • Ministerio de Minas y Energía, RETIE (Resolution 40117 of 2024, amended by Resolution 40284 of 2026), numerals 3.28.3.1 and 3.28.3.2.
  • NFPA 70, National Electrical Code, Articles 500 to 505, 517, 625, 690 and 705.

Frequently asked questions

Why does the application change the switchboard design?

Because the use defines what the switchboard must guarantee: continuity of supply, protection of people, working environment and type of loads. A hospital switchboard, a pumping switchboard and one for a hazardous area can start from the same product standard, IEC 61439, but the specification and the additional requirements are different.

Does a hospital switchboard need anything special?

Yes. Codes treat medical facilities as special installations: two independent sources with automatic transfer, an alternate source that picks up within a set time, UPS for life-support equipment and an isolated IT system with insulation monitoring in operating rooms and critical care. In Colombia the RETIE sets the alternate source at 10 s.

What is the rated diversity factor (RDF) and why does it matter in a specification?

It is the share of the rated current of each outgoing circuit that the assembly accepts in continuous duty when several circuits are loaded at the same time. The assembly manufacturer assigns it and the user states the assumed load of each outgoing circuit. If the specification does not say how the loads operate, the design cannot be matched to reality.

WhatsApp