Industrial Recloser Protection: Connection Point Criteria

When a utility norm requires a recloser or protection cell at an industrial connection point, and what the design must provide for remote control.

By Shadai García, CEO and protection engineer at Tiza Group.

Short answer

A utility construction norm for medium- and low-voltage networks calls for a recloser or protection cell at the connection point of industrial plants above 1,000 kVA at 13.2 or 34.5 kV, and on every 34.5 kV line longer than 1 km regardless of load. Any recloser must come with a GPRS or fibre link so the control centre can measure and operate it remotely. For the protection designer this fixes the device, the communications and the settings that must be agreed with the utility.

Short answer

A utility’s construction norm for medium- and low-voltage networks, in its overcurrent protection section, sets the device at the connection point by installed capacity and voltage. Above 1,000 kVA at 13.2 or 34.5 kV the table calls for a “recloser or protection cell”. On 34.5 kV lines longer than 1 km it is required regardless of the approved load.

General protection design for reclosers is in recloser protection settings.

What the norm sets

ConditionDevice at the connection point
Above 1,000 kVA, 13.2 or 34.5 kVRecloser or protection cell
34.5 kV line longer than 1 km, any loadRecloser or protection cell
Inside the customer substationDepends on the configuration: type K fuse for a yard substation, bayonet and HH fuses for pad-mounted, load-break switch with trip coil and HH fuse for indoor dry-type

The norm also says a recloser is normally not used on underground circuits, because faults there are usually permanent.

Does the connection point need a recloser or cell?
  • Is the installed capacity above 1,000 kVA at 13.2 or 34.5 kV?
    • Yes: Recloser or protection cell at the connection point
    • No: Is the line 34.5 kV and longer than 1 km?
      • Yes: Recloser or protection cell at the connection point
      • No: Device set by the table for that capacity

What the designer has to deliver

  1. Short-circuit study at the connection point; the recloser’s interrupting rating must exceed the maximum fault current.
  2. Coordination study with the utility’s relays and fuses; the settings are agreed with the utility. The coordination criteria are in recloser coordination and telecontrol criteria.
  3. Communications: GPRS or fibre, with coverage verified at the site, and a control that supports the protocol and signal list the utility defines.

Worked example (assumptions)

A 1,200 kVA plant at 13.2 kV, yard substation.

  1. 1,200 kVA is above 1,000 kVA, so the table requires a recloser or cell at the connection point.
  2. Rated current: I = 1,200 ÷ (√3 × 13.2) = 1,200 ÷ 22.86 = 52.5 A.
  3. A second plant of 500 kVA at 34.5 kV on a 1.4 km line is below 1,000 kVA but above 1 km, so the length rule applies.

The values are assumptions to show the criterion.

Checklist

  • Capacity and voltage checked against the protection table.
  • Line length measured from the utility’s network to the connection point.
  • Short-circuit current at the site below the recloser’s interrupting rating.
  • Communication link planned and tested.
  • Settings agreed with the utility before commissioning.

How Tiza can help

We design the protection coordination of the recloser your project requires and configure its control remotely: see remote recloser configuration. Contact us with the study and the utility’s requirements.

Sources

  • IEC 62271-111 / IEEE C37.60, automatic circuit reclosers up to 38 kV.

Frequently asked questions

Above what load does the norm require a recloser at the connection point?

Above 1,000 kVA installed capacity at 13.2 or 34.5 kV, the protection table lists a recloser or protection cell at the connection point. For 34.5 kV lines longer than 1 km it is required whatever the load.

What must the recloser include?

A communications link, GPRS or fibre optic, that allows remote measurement and control from the utility's control centre. The norm sets this for any recloser installed on the utility's network.

Recloser or protection cell: who decides?

The norm allows both. The choice follows from the short-circuit study, the location and what the utility approves with the design.