A utility construction norm, in its chapter on self-generation and distributed generation, asks generation plants for a protection coordination study, inverter anti-islanding within 2.0 s and, for large-scale self-generators, supervision from the utility's control centre with data every 5 minutes or faster plus three tests before operation. The norm does not impose a recloser on the plant; the connection point protection follows from the study.
Short answer
The chapter on self-generation and distributed generation of a utility construction norm covers plants that export to its network. It asks for a protection coordination study, datasheets that prove the protection functions required for the plant size, and an inverter anti-islanding response within 2.0 s of losing grid voltage. Large-scale self-generators also supply supervision data to the utility’s control centre and pass three tests before operating.
Supervision
The control centre must see the plant through RTUs or equivalent, agreed protocols, synchrophasor measurement if the agent asks for it, or intelligent electronic devices. Mandatory data:
| Data | Period |
|---|---|
| Active and reactive power | Agreed with the utility, 5 minutes or faster |
| Line-to-line voltage and phase current | Agreed with the utility, 5 minutes or faster |
| State of the frequency control function | Periodic or on change |
| Plant connection state: connected and operating, or not | Periodic or on change |
The period is never longer than 5 minutes; the two state signals may be sent on change. In emergencies the control centre may send active-power set-points.
- Developer: Design with coordination study. Calculation report and datasheets
- Utility: Design approved? Yes: continue; No: back to step 1.
- Developer: Build and own commissioning. Tests of the project itself
- Developer: Protection, supervision and synchronisation tests. Results sent to the utility
- Utility: Review of results. Within the set deadlines
- Utility: Operation. Maintenance notified one month ahead
Where a recloser fits
- Line length. The general chapter of the same norm requires a recloser or protection cell at the connection point on 34.5 kV lines longer than 1 km.
- Study result. If the coordination study shows a recloser gives the selectivity and disconnection the plant needs, it is designed in. The coordination and communication criteria are in recloser coordination and telecontrol criteria.
Worked example (assumptions)
A 3 MW solar plant at 13.2 kV.
- 3 MW is between 1 MW and 5 MW, so the large-scale supervision requirements apply.
- Data sent every 5 minutes gives 60 ÷ 5 = 12 reports per hour; every minute would give 60.
- If grid voltage is lost at t = 0, the inverter must stop energising before t = 2.0 s.
Power, voltage and period are assumptions; real values are agreed with the utility.
Checklist
- Plant category defined.
- Coordination study and datasheets for the protection functions.
- Anti-islanding tested at 2.0 s or less.
- Supervision channel chosen and the four signals defined.
- Reporting period agreed, 5 minutes or less.
- Protection, supervision and synchronisation test results sent.
How Tiza can help
We carry out the protection coordination study for the connection point and configure the relays and the recloser control remotely: see remote relay configuration. Contact us with the study and the utility’s requirements.
Related guides
- Industrial recloser protection: connection point criteria
- Recloser coordination and telecontrol criteria
- Recloser settings: reclosing and curves
Sources
- IEEE 1547-2018, interconnection and interoperability of distributed energy resources with electric power systems.
Frequently asked questions
Does the norm require a recloser at a solar plant's connection point?
Not for every plant. It requires a coordination study and datasheets proving the protection functions for the plant size. A recloser appears when the connecting line calls for it or when the study shows it gives the needed selectivity.
What data must a large-scale self-generator send?
Active and reactive power, line-to-line voltage and phase current, the state of the frequency control function and the plant connection state. The period is agreed with the utility and cannot exceed 5 minutes.
What tests come before operation?
Protection compliance tests, supervision system tests and grid synchronisation tests, with results sent to the utility.