The interrupting device of a distributed generation plant is usually chosen by size: below about 0.25 MW a breaker, or the inverter itself if certified; between 0.25 and 1 MW a breaker with trip units, a recloser or a power breaker. The design also has to block zero-sequence current toward the grid, set voltage and frequency protection and fix a reconnection delay.
Short answer
At a generation plant’s point of connection, the interrupting device is picked by installed power. For small plants, a breaker or the inverter’s own switching, when the inverter has a conformity certificate, is enough. In the band from about 0.25 MW to 1 MW, a breaker with trip units, a recloser or a power breaker are all acceptable, and their characteristics are agreed with the utility. Around the device the design has to set three things: the coupling transformer must not feed zero-sequence current to the grid, the voltage and frequency protection must have defined settings, and the reconnection must wait for a minimum time with all three phases energised.
Settings and curves are covered in recloser settings: reclosing, curves and sequence.
Device by plant size
- Is the installed power above 0.25 MW?
- No: Breaker, or the inverter's own switching with a conformity certificate
- Yes: Is it below 1 MW?
- Yes: Breaker with trip units, recloser or power breaker, agreed with the utility
- No: Define with the utility in the connection study
Where the device goes
The device belongs at the point of connection or at the same voltage level. When it is set back from that point, add a second interrupting device so a fault on the cable between the point and the main device is still cleared. That is the typical flaw of a recloser installed deep inside a plant: the connection cable is left unprotected.
Coupling transformer
Design the grid-side winding as a star with the neutral isolated from earth. A grounded star lets the plant feed zero-sequence current into ground faults on the grid, which reduces the sensitivity and directionality of the utility’s earth protection. The low-voltage side is the designer’s choice, driven by the inverters.
Example settings (assumptions)
For a 0.6 MW plant, with voltages measured at the point of connection:
| Function | Assumed setting |
|---|---|
| Undervoltage, stage 1 | 0.8 p.u., delay from the coordination study |
| Undervoltage, stage 2 | 0.6 p.u., delay from the coordination study |
| Overvoltage, stage 1 | 1.15 p.u., 2.5 s |
| Overvoltage, stage 2 | 1.25 p.u., 0.5 s |
| Under and over frequency | 57 Hz and 63 Hz, 0.2 s |
| Reconnection | 5 minutes minimum, voltage on all three phases |
The control also needs an auxiliary supply that keeps protection, control and the interrupting device working during the fault. For a recloser this is the charger and battery of its control cabinet.
Supervision
If the utility asks for remote supervision, the usual minimum is active and reactive power, line voltage, phase currents and the status of the connection. A recloser control with a communications protocol already produces those signals; what remains is to configure the points and test them end to end.
Design checklist
- Installed power and size band identified.
- Device at the point of connection, or an additional device up to it.
- Coupling transformer with an isolated star on the grid side.
- Voltage and frequency settings loaded with a test record.
- Reconnection timer and three-phase check tested.
- Auxiliary supply of the control proven.
We provide the design engineering and the remote configuration of the recloser control, from the coordination study to the settings file and the test plan: contact us with your network data and we will propose a scope. See remote relay configuration.
Related guides
- Recloser: what it is, how it works and tests
- Recloser-fuse and recloser-relay coordination
- Anti-islanding protection
- Requirements for distributed generation
References
- IEC 62271-111:2019 / IEEE C37.60-2018, automatic circuit reclosers for alternating current systems up to 38 kV.
- IEC 62109-1:2010 and UL 1741, inverter safety and conformity.
Frequently asked questions
Is a recloser required at the point of connection of a solar plant?
Not by name. A design rule by size usually lists the acceptable devices: a breaker or the inverter's own switching for small plants, and a breaker with trip units, a recloser or a power breaker for the next band. The characteristics are agreed with the utility.
Where should the interrupting device sit?
At the point of connection or at the same voltage level. If it sits further back, an additional device must clear faults on the section between the point of connection and the main device.
Why block zero-sequence current from the plant?
If the coupling transformer's grid-side winding is a grounded star, the plant feeds earth faults on the grid and desensitises the utility's ground protection. An ungrounded star on that winding keeps the plant out of the zero-sequence circuit.