A plant may connect only when the grid voltage and frequency are inside a window and may transfer power only when voltage, frequency and angle differences are inside limits that depend on its size. The design sets these thresholds in the plant protection, with fault clearing in 150 ms and harmonic distortion within the limit.
Short answer
The protection at a plant’s connection point has three groups of settings: the window to connect (grid voltage and frequency inside a range, with a delay), the synchronization limits to transfer power (differences in voltage, frequency and angle, tighter for larger plants) and the fault clearing time. They come from the interconnection standard that the utility adopts and are loaded in the plant control, which can be a recloser control.
Anti-islanding is in anti-islanding protection; the protection requirements for distributed generation, in requirements for distributed generation.
What the design sets
- Entry window: voltage between 0.917 and 1.05 per unit and frequency between 59.5 and 60.1 Hz by default, with adjustable ranges, and a reconnection delay from 0 to 600 s (300 s by default).
- Synchronization: frequency, voltage and angle differences inside limits that depend on size: up to 500 kVA, 0.3 Hz, 10 % and 20°; from 500 to 1 500 kVA, 0.2 Hz, 5 % and 15°; above 1 500 kVA, 0.1 Hz, 3 % and 10°.
- Fault clearing: faults on the grid side and on the generator side are cleared in no more than 150 ms, with overvoltage and overcurrent protection as a minimum.
- Harmonics: total voltage distortion of the plant within 5 %.
- Plant designer: Protection study with the thresholds. Window, synchronism, clearing time
- Utility: Is the study approved? Yes: continue; No: back to step 1.
- Plant designer: Thresholds loaded in the control. Recloser or plant relay
- Utility: Tests by plant size. Larger plants, the full set
- Utility: Plant connected
Tests by size
The tests grow with the size: small plants get an inspection of the declared parameters and the protection scheme; mid-size plants add the protection and reconnection-time tests; the largest add the full set. The certificates of the inverter and of the metering are part of the file.
Example with numbers (assumptions)
A 1.2 MW plant at 13.2 kV with a recloser at the connection point.
- Band: 1 200 kVA falls in the 500 to 1 500 kVA band: 0.2 Hz, 5 % and 15°.
- Rated current: I = 1 200 ÷ (1.732 × 13.2) = 1 200 ÷ 22.86 = 52.5 A.
- Check: grid at 60.00 Hz and plant at 60.15 Hz: a difference of 0.15 Hz, which passes; at 0.25 Hz it would not.
- Voltage: grid 13.20 kV and plant 13.50 kV: a difference of 2.3 %, which passes.
- Clearing: an internal fault must clear in 150 ms or less.
Design checklist
- Entry window and reconnection delay set.
- Synchronization limits for the plant size.
- Fault clearing in 150 ms or less.
- Harmonic distortion within the limit.
- Test plan by plant size.
- Thresholds loaded and recorded in the control.
We design the protection coordination for the recloser your project requires and configure its control remotely, whatever its make. See remote relay configuration.
Related guides
- Anti-islanding protection
- Requirements for distributed generation
- Recloser settings: reclosing and curves
References
- IEEE 1547-2018, interconnection and interoperability of distributed energy resources, entry into service and synchronization.
- IEC 62271-111:2019 / IEEE C37.60-2018, automatic circuit reclosers for alternating current systems up to 38 kV.
Frequently asked questions
What window must the grid be in before the plant connects?
A default of 0.917 to 1.05 per unit in voltage and 59.5 to 60.1 Hz in frequency, with adjustable ranges, and a delay that can be set from 0 to 600 seconds (300 by default) before the plant reconnects.
How do the synchronization limits change with plant size?
They tighten: for plants up to 500 kVA, 0.3 Hz, 10 % and 20 degrees; from 500 to 1 500 kVA, 0.2 Hz, 5 % and 15 degrees; above 1 500 kVA, 0.1 Hz, 3 % and 10 degrees.
Does the recloser at the connection point set these limits?
Its control can hold the voltage, frequency and direction functions, and the synchronism check, but the thresholds come from the protection study. The device is chosen by the study, not by the catalog.