Plant Recloser Coordination With Utility Relays: Margins

Design of a recloser at a plant's connection point: time margin against utility relays, overcurrent ceiling, reclosing coordination and test.

By Shadai García, CEO and protection engineer at Tiza Group.

Short answer

A recloser at a plant's connection point must be faster than the utility relays by a minimum time margin, so that internal plant faults are not cleared by the grid. The design fixes an overcurrent ceiling from the requested generation, coordinates with the feeder's reclosing and proves the disconnection in a witnessed test.

Short answer

A recloser at the connection point of a plant has two jobs: separate the plant from the grid when the grid fails, and clear plant faults before the grid protection does. The second job is a time margin: the plant device must be faster than the utility relays by a minimum set by the utility, or the utility will not accept the connection. The design also sets an overcurrent ceiling from the requested generation and proves coordination with the feeder’s reclosing.

Anti-islanding is in anti-islanding protection; the protection requirements for distributed generation, in requirements for distributed generation.

What the design fixes

ItemDesign rule
Margin against the utility relaysA minimum time between curves or trip delays, set by the utility
Overcurrent ceilingA percentage of the generation capacity requested, set by the utility
SelectivityInternal plant faults are cleared by the plant device, not by the grid
ReclosingThe plant is disconnected before the feeder recloses
Interrupting deviceRated for the maximum fault current, visible and accessible

If selectivity cannot be reached, the technical approval is not granted: the risk falls on the other customers of the feeder.

The connection test

The test usually follows an operating plan agreed in advance: date and hour, procedure, a responsible person, and a call to the control center, including whether reclosing is disabled. The sequence checks the open and close of each device, then interrupts the supply and verifies the plant stops within the defined times, and normalizes in reverse order. The control’s settings are recorded before and after.

Coordinating a plant recloser with the utility
  1. Plant designer: Single-line diagram and protection study. Curves, ceiling and reclosing
  2. Utility: Is selectivity confirmed? Yes: continue; No: back to step 1.
  3. Plant designer: Settings loaded in the control. Tested before energization
  4. Utility: Witnessed disconnection test. Supply interrupted, plant stops
  5. Utility: Plant connected

Example with numbers (assumptions)

A plant of 800 kVA at 13.2 kV.

  1. Rated current: I = 800 ÷ (1.732 × 13.2) = 800 ÷ 22.86 = 35.0 A.
  2. Overcurrent ceiling: 35.0 × 1.05 = 36.8 A.
  3. Margin: if the feeder relay trips in 0.50 s for a plant fault and the margin is 120 ms, the plant recloser must trip in 0.50 − 0.12 = 0.38 s or less.
  4. No margin: with 0.45 s the margin is 0.05 s, below 120 ms: the settings are recoordinated.

The real times come from the utility study.

Design checklist

  • Protection study with curves, ceiling and reclosing.
  • Margin against the utility relays met.
  • Interrupting device rated for the fault current.
  • Anti-islanding defined, with or without an inverter.
  • Settings loaded and recorded.
  • Test plan with the supply interruption.

We design the protection coordination for the recloser your project requires and configure its control remotely, whatever its make. See remote relay configuration.

References

  • IEEE 1547-2018, interconnection and interoperability of distributed energy resources.
  • IEEE C37.104-2022, Guide for automatic reclosing of circuit breakers for AC distribution and transmission lines.

Frequently asked questions

What time margin should a plant recloser keep against the utility relays?

The utility sets a minimum between timed curves or definite trip delays. The worked example uses 120 ms as an assumption. If the margin cannot be met, the connection is not technically viable until the settings are recoordinated.

How is the overcurrent ceiling of the plant protection set?

From the generation capacity requested. In the example it is 105 % of the rated current of the plant, so a plant of 800 kVA at 13.2 kV has a ceiling near 36.8 A.

What is checked in the connection test?

That the plant stops operating within the defined times when the utility supply is interrupted, that the feeder's automatic reclosing is coordinated with the plant response, and that the telemetry works if installed.