Recloser at a Plant's Connection Point: Protection Design

How a recloser at a generator's point of connection is designed: visible disconnect, voltage and frequency protection, anti-islanding and reclosing.

By Shadai García, CEO and protection engineer at Tiza Group.

Short answer

A utility interconnection standard rarely names the recloser; it names functions: a visible disconnect, voltage and frequency protection, anti-islanding and coordination with the feeder's reclosing. A recloser at the point of connection can group those functions in one device, but the utility reviews the whole protection scheme and its settings, not the equipment alone.

Short answer

At a generator’s point of connection, the utility’s interconnection standard sets functions the design must provide: a visible, accessible disconnect, voltage and frequency protection, anti-islanding and coordination with the feeder’s reclosing. A recloser fits when its control can provide those functions and its operation leaves the plant separated from the grid. It is a design decision, not a requirement of the standard.

Recloser ratings are in recloser for a feeder: ratings and construction; anti-islanding design is in anti-islanding requirements compared.

Functions the point of connection must cover

FunctionDesign question
Visible disconnectRated voltage at least the line voltage, accessible, rated for the fault level
Voltage and frequency protectionWhich elements, which settings, and how they are demonstrated
Anti-islandingInverter-based: certified inside the inverter. Otherwise: voltage detection that blocks closing on a dead line, plus reverse-power detection
Directional and synchronizing functionsNeeded for rotating machines; the control must support them
Coordination with feeder reclosingThe plant clears before the first reclose

Clearing times used as reference

IEEE 1547-2003 gives the reference times that many interconnection standards adopt. With the grid voltage as a percentage of base:

Grid voltageClearing time
Below 50 %0.16 s
50 % to below 88 %2.00 s
Above 110 % and below 120 %1.00 s
120 % or more0.16 s

For frequency, above 30 kW: over 60.5 Hz, 0.16 s; between 57 and 59.8 Hz, an adjustable time from 0.16 s to 300 s; below 57 Hz, 0.16 s. The editions in force differ by utility and by year, so the utility’s current standard prevails.

Protection design at the point of connection
  1. Design: Single-line diagram and protection scheme. Voltage, frequency, grounding
  2. Design: Coordination study with the feeder reclosing. Clearing time against first reclose
  3. Utility: Is the study approved? Yes: continue; No: back to step 2.
  4. Design: Control settings and test plan. Per the approved study
  5. Design: Remote configuration and verification. Settings file and signals checked

Example with numbers (assumptions)

A 2 MW plant connected to a 13.2 kV feeder through a recloser.

  1. Plant current: I = 2 000 kVA ÷ (1.732 × 13.2 kV) = 2 000 ÷ 22.86 = 87.5 A at unity power factor.
  2. Fault on the feeder: the voltage drops to 40 % of base, so the plant must clear in 0.16 s.
  3. First feeder reclose at 1.0 s (assumed): margin = 1.0 − 0.16 = 0.84 s.
  4. Frequency at 59.5 Hz: above 30 kW, the delay is adjustable from 0.16 s to 300 s; the study sets the value.

Real reclose times come from the utility.

Design checklist

  • Functions required by the utility’s standard listed and assigned to a device.
  • Control capabilities checked against those functions.
  • Clearing times and the feeder’s reclose time in the same study.
  • Settings file prepared for the control.
  • Test plan with injection and a disconnection test.

We provide the design engineering and the remote configuration of the recloser control, from the coordination study to the settings file and the test plan: contact us with your network data and we will propose a scope. See remote relay configuration.

References

  • IEEE 1547-2003, Standard for Interconnecting Distributed Resources with Electric Power Systems: abnormal voltage and frequency response times.
  • IEEE C37.60 / IEC 62271-111, AC automatic circuit reclosers above 1 kV and up to 38 kV.
  • IEC 62116 and UL 1741, anti-islanding conformance of inverters.

Frequently asked questions

Does a utility require a recloser at the point of connection of a generator?

Usually it requires functions rather than a device: a visible, accessible disconnect, voltage and frequency protection with the settings delivered to the utility, anti-islanding, and coordination with the feeder's automatic reclosing. A recloser is one way to provide them; a breaker with a protection relay is another.

What clearing times does a plant have to meet?

IEEE 1547-2003 sets the reference most utilities still apply: 0.16 s when the grid voltage falls below 50 % of base, 2.00 s between 50 % and 88 %, 1.00 s between 110 % and 120 %, and 0.16 s at 120 % or more. Check the edition the utility currently requires.

Why does the reclose time of the feeder matter for the plant?

If the plant is still connected when the feeder recloses, the reclosure can happen out of synchronism. The plant must clear before the first reclose, and the margin between the two times is what the coordination study has to show.