Two design choices keep a feeder recloser operable: an auxiliary supply taken on the source side, so the control can be operated remotely when the unit is open, and a bypass chosen by the circuit current, with a visible break on each side. The control and its communications are specified with them.
Short answer
Two decisions keep a feeder recloser operable. The auxiliary supply is taken on the source side, so the control keeps power when the recloser opens and can still be operated remotely if the unit’s battery runs low. The bypass is chosen by the nominal current of the circuit, with a visible break on each side of the unit for work. The control and its communications are specified together with them.
How a recloser works is in recloser; settings, in recloser settings.
What the design fixes
| Item | Design rule |
|---|---|
| Auxiliary supply | Small transformer on the source side, fused on the primary and protected on the low side |
| Bypass, low current | Fused cutout with an arc-extinguishing chamber |
| Bypass, higher current | Disconnect switches rated for the circuit |
| Visible break | Disconnect switches at the input and the output of each phase, operated without load |
| Surge arresters | At the input and output of the recloser |
| Control and ground | The control cable is kept apart from the ground conductor, so a fault current does not induce voltage in it |
The limit between the two bypass types is set by the utility. Below it, a cutout is enough; above it, the switches must carry the full circuit current.
- Design engineer: Circuit current, voltage and site. Trunk or branch
- Design engineer: Visible break and bypass. By current: cutout or switches
- Design engineer: Auxiliary supply on the source side. Fused, protected on the low side
- Design engineer: Control and communications. Protocols, settings groups, records
- Utility: Is the design approved? Yes: continue; No: back to step 2.
- Utility: Control set and tested before energization
Example with numbers (assumptions)
A 13.2 kV branch with 2.2 MVA installed and a bypass limit of 100 A.
- Current: I = 2 200 ÷ (1.732 × 13.2) = 2 200 ÷ 22.86 = 96 A: a cutout is enough.
- With 20 % growth: 96 × 1.2 = 115 A: above the limit, so the design uses disconnect switches from the start.
- Auxiliary supply: a small transformer on the source side, fused on the primary.
- Control: communications to the control center and the settings groups defined before ordering.
The real currents and fault levels come from the utility.
Design checklist
- Circuit current, with growth, against the bypass limit.
- Visible break on each side of the recloser.
- Auxiliary supply on the source side, protected.
- Arresters on both sides.
- Control cable apart from the ground conductor.
- Communications and settings defined for the control.
We design the protection coordination for the recloser your project requires and configure its control remotely, whatever its make. See remote relay configuration.
Related guides
- Recloser: what it is, how it works and tests
- Recloser settings: reclosing and curves
- Recloser-fuse coordination
References
- IEC 62271-111:2019 / IEEE C37.60-2018, automatic circuit reclosers for alternating current systems up to 38 kV.
- IEEE C37.104-2022, Guide for automatic reclosing of circuit breakers for AC distribution and transmission lines.
Frequently asked questions
Why is the auxiliary supply taken on the source side?
So the control keeps its supply when the recloser opens, and remote operation stays available when the battery of the unit is depleted. If it were taken on the load side, an opening would leave the control without power.
How is the bypass chosen?
By the nominal current of the circuit: a fused cutout for low-current branches, and disconnect switches rated for the circuit for higher currents. The limit between the two is set by the utility; the example uses 100 A as an assumption.
What does the controller need to be set remotely?
Communications to the control center, the settings groups, the reclosing sequence and the event record. These are defined with the design and loaded before energization.