A utility design and construction standard (version 3, 2023) lists what a recloser control must do: phase, earth and high-impedance earth overcurrent, directional and non-directional, at least four reclosing sequences, over- and undervoltage, fault location, metering, GPS time-stamped events and RTU functions, with IEC 60870-5-104 over a radio modem to the control centre.
What the control must do
The utility’s standard lists the functions of the protection, metering and control unit of each recloser:
| Function required | What to verify |
|---|---|
| Overcurrent: phase, earth and high-impedance earth; directional and non-directional; instantaneous, definite-time and inverse-time | Each function available and enabled separately |
| Reclosing with at least 4 open-close sequences, instantaneous or timed independently | Four sequences accepted and the programmed one executed |
| Overvoltage and undervoltage | Both functions present and tripping |
| Fault location | Value delivered after an event |
| Metering: phase and line voltages, phase currents, power, energy | Values match an injected reference |
| Event log with GPS time stamp | Clock synchronised, events carry time |
| RTU functions | Signals reach the control centre |
| Input for tripping by external protection | An external contact opens the recloser |
Communications
- Protocol: IEC 60870-5-104.
- Medium: radio modem, with the radio equipment in a separate cabinet.
- Radio specification: provided by the utility.
- Integrator: Control with the required functions. Protection, reclosing, metering, log
- Utility: Radio modem specification. Before buying the modem
- Integrator: Function and signal tests. Injection and external trip contact
- Utility: Signals and time correct at the control centre? Yes: continue; No: back to step 3.
- Utility: Recloser under remote control
Worked example with assumed numbers
Assumptions, not from a real project: six new reclosers on one circuit, ten functional checks each (the eight functions in the table, the radio link and the IEC 60870-5-104 protocol).
- Total checks: 6 x 10 = 60.
- At 20 minutes per check: 60 x 20 = 1,200 min = 20 h.
- A radio link that does not come up first time repeats that unit’s communication checks: plan the test time before requesting energization.
The standard gives capabilities, not settings: curves, reclosing times and the signal list come from the coordination study and the utility. We design the protection coordination and configure the control remotely: see remote configuration of protective relays and controls.
References
- IEC 60870-5-104; IEC 61850 (GOOSE).
Frequently asked questions
What telecontrol protocol does the standard require?
IEC 60870-5-104, through a radio modem to the control centre. The radio equipment is installed in a separate cabinet and the utility provides the radio modem specification.
How many reclosing sequences must the control offer?
At least four open-close sequences, each programmable as instantaneous or timed independently. The standard fixes the capability; the actual times come from the coordination study.
Which events must be recorded?
Events with a GPS time stamp, plus metering of phase and line voltages, phase currents, power and energy, and fault location.