Tiza Group

Home / Guides / Protection, control and communications

Recloser Control Functions and IEC 60870-5-104 Link

The protection, reclosing, metering, GPS log and RTU functions a utility requires from a recloser control, and its IEC 60870-5-104 radio link.

By Shadai García, CEO and protection engineer at Tiza Group.

Short answer

A utility design and construction standard (version 3, 2023) lists what a recloser control must do: phase, earth and high-impedance earth overcurrent, directional and non-directional, at least four reclosing sequences, over- and undervoltage, fault location, metering, GPS time-stamped events and RTU functions, with IEC 60870-5-104 over a radio modem to the control centre.

What the control must do

The utility’s standard lists the functions of the protection, metering and control unit of each recloser:

Function requiredWhat to verify
Overcurrent: phase, earth and high-impedance earth; directional and non-directional; instantaneous, definite-time and inverse-timeEach function available and enabled separately
Reclosing with at least 4 open-close sequences, instantaneous or timed independentlyFour sequences accepted and the programmed one executed
Overvoltage and undervoltageBoth functions present and tripping
Fault locationValue delivered after an event
Metering: phase and line voltages, phase currents, power, energyValues match an injected reference
Event log with GPS time stampClock synchronised, events carry time
RTU functionsSignals reach the control centre
Input for tripping by external protectionAn external contact opens the recloser

Communications

  • Protocol: IEC 60870-5-104.
  • Medium: radio modem, with the radio equipment in a separate cabinet.
  • Radio specification: provided by the utility.
From the recloser control to the utility control centre
  1. Integrator: Control with the required functions. Protection, reclosing, metering, log
  2. Utility: Radio modem specification. Before buying the modem
  3. Integrator: Function and signal tests. Injection and external trip contact
  4. Utility: Signals and time correct at the control centre? Yes: continue; No: back to step 3.
  5. Utility: Recloser under remote control

Worked example with assumed numbers

Assumptions, not from a real project: six new reclosers on one circuit, ten functional checks each (the eight functions in the table, the radio link and the IEC 60870-5-104 protocol).

  • Total checks: 6 x 10 = 60.
  • At 20 minutes per check: 60 x 20 = 1,200 min = 20 h.
  • A radio link that does not come up first time repeats that unit’s communication checks: plan the test time before requesting energization.

The standard gives capabilities, not settings: curves, reclosing times and the signal list come from the coordination study and the utility. We design the protection coordination and configure the control remotely: see remote configuration of protective relays and controls.

References

  • IEC 60870-5-104; IEC 61850 (GOOSE).

Frequently asked questions

What telecontrol protocol does the standard require?

IEC 60870-5-104, through a radio modem to the control centre. The radio equipment is installed in a separate cabinet and the utility provides the radio modem specification.

How many reclosing sequences must the control offer?

At least four open-close sequences, each programmable as instantaneous or timed independently. The standard fixes the capability; the actual times come from the coordination study.

Which events must be recorded?

Events with a GPS time stamp, plus metering of phase and line voltages, phase currents, power and energy, and fault location.

WhatsApp