Canada has no single ride-through rule for inverter-based resources. Ontario sets performance categories in the IESO Market Rules without a voltage-time table. Alberta publishes voltage and frequency tables in AESO ISO rules 503.5 and 503.6. Hydro-Québec publishes its own curves in its transmission requirements. One disturbance can give three different minimum ride-through times, so each province has to be read separately.
Short answer: ride-through rules by province
IBR ride-through in Canada is set province by province. IBR means inverter-based resource: a solar, wind or battery plant connected through inverters. Ontario writes performance categories into the IESO Market Rules. Alberta publishes voltage-time and frequency-time tables in ISO rules 503.5 and 503.6. Québec publishes curves in the Hydro-Québec transmission requirements. The comparison below covers transmission-connected plants and links each rule to its source. For the national picture, see the overview of Canadian electrical codes and grid connection.
Ontario: performance categories in the Market Rules
Appendix 4.2 of the Market Rules covers generation and electricity storage connected to the IESO-controlled grid. The current text sits in the Renewed Market Rules, Chapter 4 Appendices, Issue 2.0 of December 3, 2025. It applies to facilities whose connection assessment was finalised after September 21, 2020. Confirm the current issue before design.
The voltage ride-through category is written as a duty, not as a curve. A unit has to ride through routine switching events and design-criteria contingencies, assuming standard fault detection and rated breaker interrupting times. For inverter-based units, momentary cessation or a reduction of output current during disturbances is not permitted without IESO approval.
The frequency category does have numbers. Plants operate continuously between 59.4 and 60.6 Hz. Above that band, the required region is bounded by a line from 61.8 Hz at 8 s to 60.6 Hz at 600 s on a log-linear scale. Below it, a line from 57.0 Hz at 3.3 s to 59.0 Hz at 300 s.
Generators embedded in a distributor or connected wholesale customer must meet at least the frequency and voltage ride-through categories of Appendix 4.2.
Alberta: ISO rules 503.5 and 503.6
Voltage. ISO rule 503.5, effective April 1, 2024, applies to transmission-connected units above 9.0 MW, to aggregated facilities without storage, and to storage with a range above 5 MW. The 1.0 p.u. reference is the phase-to-phase voltage on the high-voltage side of the step-up transformer.
| High voltage | Duration | Low voltage | Duration |
|---|---|---|---|
| 1.10 p.u. or more | 1.00 s | Below 0.90 p.u. | 3.00 s |
| 1.15 p.u. or more | 0.50 s | Below 0.75 p.u. | 2.00 s |
| 1.175 p.u. or more | 0.20 s | Below 0.65 p.u. | 0.30 s |
| 1.20 p.u. or more | Instantaneous trip | Below 0.45 p.u. | 4 to 9 cycles |
The rule also states that voltage may remain at 0.0 p.u. for at least the normal clearing time of a three-phase fault at that location. Three faults are excepted. They are a fault that forces out a radial line, a fault on the plant side, and a fault that operates a transfer trip or anti-islanding scheme.
Frequency. ISO rule 503.6, amended July 10, 2026, sets Appendix 1 times during which the plant must not trip. Otherwise it needs firm arrangements to trip an equal amount of load. Trip is instantaneous at 61.7 Hz or more and at 57.0 Hz or less. Between 60.6 and 61.6 Hz the time is 180 s, and from 61.6 Hz it is 30 s.
Québec: curves in the transmission requirements
Hydro-Québec’s Technical Requirements for the Connection of Generating Stations to the Hydro-Québec Transmission System (Decision D-2022-088, effective July 15, 2022) gives inverter plants their own chapter. Low voltage below 0.25 p.u. has a minimum time of 3.4 × V + 0.15 s. Frequency above 60.6 Hz requires 11 minutes, and 1.5 minutes above 61.5 Hz. Details are in Hydro-Québec technical requirements for generators.
The NERC layer
NERC PRC-029-1 adds ride-through performance for inverter-based resources where a province enforces it. Ontario lists an effective date of October 1, 2026. For Alberta, check the AESO list of Alberta reliability standards; ISO rule 503.5 already sets ride-through for transmission-connected plants. For Québec, check the Régie de l’énergie list of adopted standards. See NERC reliability standards in Canada and, for the US version, NERC PRC-029.
Worked example (illustrative)
One disturbance, three provinces. All values come from the tables above.
- Voltage sag to 0.20 p.u. at the high-voltage side. Québec: 3.4 × 0.20 + 0.15 = 0.83 s. Alberta: the band below 0.45 p.u. allows 4 to 9 cycles, which is 4 ÷ 60 = 0.067 s to 9 ÷ 60 = 0.150 s. Ontario: no voltage-time value in the rule, so the duty “design-criteria contingencies” applies.
- Frequency rise to 60.9 Hz. Québec: 11 minutes, which is 660 s. Alberta: 180 s. Ontario: interpolate on the line from (8 s, 61.8 Hz) to (600 s, 60.6 Hz). The slope is (60.6 − 61.8) ÷ (log₁₀600 − log₁₀8) = −1.2 ÷ 1.875 = −0.64 Hz per decade. Time at 60.9 Hz = 10^(log₁₀8 + 0.9 ÷ 0.64) = 10^2.309 ≈ 204 s.
The same inverter settings cannot be copied from one province to the next. At 0.20 p.u., even the longest Alberta value of 0.150 s is 5.5 times shorter than Québec’s 0.83 s (0.83 ÷ 0.15).
Checklist for the engineer
- Identify the system operator and the document edition that apply at the connection point.
- Confirm whether the plant is transmission-connected or distribution-connected.
- Define the 1.0 p.u. reference: the high-voltage side of the step-up transformer.
- Set voltage and frequency trip curves per province, not per inverter default.
- Check blocking and momentary cessation rules, which differ between Ontario and Québec.
- Confirm that no plant protection trips inside the ride-through region.
- Match the ride-through tests to the model data you submit.
- Re-check the status of NERC standards at each milestone.
Legal frame
In Canada, electrical engineering is stamped by a professional engineer (P.Eng.) licensed in the province or territory of the project. Tiza delivers engineering and studies ready for your P.Eng. to review and stamp. Tiza does not stamp, sign or certify designs.
From the requirement to inverter and relay settings
Ride-through becomes real in the inverter parameters and the plant relays. We prepare the remote configuration plan: the settings to load, the curves to check and the evidence to keep, ready for your engineer of record to review and stamp. Contact us with the inverter model and the connection point.
Figure: voltage-time envelope with the low-voltage bands of Alberta and the Québec curve, both referred to 1.0 p.u. on the high-voltage side.
Related guides
- Ride-through requirements compared: US, UK and Australia
- IEEE 2800 ride-through and reactive capability
- G99 fault ride through and frequency response
- Voltage disturbance ride-through in the NEM
- Protection at the point of interconnection in Canada
References
- IESO, Renewed Market Rules, Chapter 4 Grid Connection Requirements, Appendices, Issue 2.0, December 3, 2025, Appendix 4.2.
- AESO, ISO rules Section 503.5 Voltage Ride-Through, effective April 1, 2024; Section 503.6 Frequency and Speed Governing, effective July 10, 2026.
- Hydro-Québec TransÉnergie, Technical Requirements for the Connection of Generating Stations to the Hydro-Québec Transmission System, Decision D-2022-088, effective July 15, 2022.
- IESO, Ontario Enforcement Dates for PRC-029-1, implementation plan.
Frequently asked questions
Is there one national ride-through standard for inverter-based plants in Canada?
No. Each province or system operator sets its own rules. Ontario uses the IESO Market Rules, Alberta uses AESO ISO rules, and Québec uses the Hydro-Québec transmission requirements. NERC standards add a layer where a province has adopted them.
Can an inverter stop injecting current during a fault in Ontario?
Not without approval. The IESO Market Rules state that momentary current cessation or reduction of output current during system disturbances is not permitted for inverter-based units without IESO approval.
Does Alberta require ride-through for a fault inside the plant?
No. ISO rule 503.5 does not require ride-through for a fault on the plant side of the connection point. Nor does it for a fault that forces out a radial line, or when a transfer trip or anti-islanding scheme disconnects the plant.